Subproject Financial report

work_package_no667
SubprojectBridge at Gangolihat Over Ramganga River at Berinag Vinayak Puranathal Bhuwani MR
Work Done cost (in lacs)565.78
MonthsPlanned ExpenditureReplanned ExpenditureCum Planned ExpenditureCum Re Planned ExpenditureExpenditureCum Expenditure
Feb 211.030.001.03565.780.000.00
Mar 212.290.003.32565.780.000.00
Apr 2161.330.0064.65565.780.000.00
May 21116.170.00180.82565.780.000.00
Jun 21112.420.00293.24565.780.000.00
Jul 21116.170.00409.40565.780.000.00
Aug 21113.270.00522.67565.7839.6239.62
Sep 2171.690.00594.37565.780.0039.62
Oct 2125.870.00620.24565.780.0039.62
Nov 2129.8074.90650.03640.68425.90465.53
Dec 21130.33133.99780.36774.670.00465.53
Jan 22188.82190.72969.17965.390.00465.53
Feb 2226.8328.55996.00993.940.00465.53
Mar 2216.2018.271012.201012.210.00465.53
Expenditure planning in Work Package