Subproject Financial report

work_package_no666
SubprojectSteel Truss Bridle Bridge on Palagwadi-Chalureseem Bridle Road on Ramganga River
Work Done cost (in lacs)2.84
MonthsPlanned ExpenditureReplanned ExpenditureCum Planned ExpenditureCum Re Planned ExpenditureExpenditureCum Expenditure
Feb 210.410.000.412.840.000.00
Mar 210.550.000.962.840.000.00
Apr 210.540.001.502.840.000.00
May 210.550.002.052.840.000.00
Jun 210.540.002.592.840.000.00
Jul 210.550.003.142.840.000.00
Aug 210.550.003.692.840.000.00
Sep 210.540.084.232.920.000.00
Oct 21115.23115.45119.45118.360.000.00
Nov 21158.09158.31277.54276.670.000.00
Dec 2183.1083.33360.65360.000.000.00
Jan 2286.7787.00447.42447.000.000.00
Feb 2223.6723.87471.09470.870.000.00
Mar 2220.3420.57491.44491.430.000.00
Expenditure planning in Work Package