Subproject Financial report

work_package_no665
SubprojectRCC Bridge at Rathuadab over Mandal River
Work Done cost (in lacs)869.42
MonthsPlanned ExpenditureReplanned ExpenditureCum Planned ExpenditureCum Re Planned ExpenditureExpenditureCum Expenditure
Dec 2017.130.0017.13869.420.000.00
Jan 2160.720.0077.85869.420.000.00
Feb 2154.850.00132.70869.42105.81105.81
Mar 2183.820.00216.52869.42105.81211.62
Apr 21234.540.00451.06869.420.00211.62
May 21182.100.00633.16869.42317.43529.04
Jun 2152.190.00685.35869.420.00529.04
Jul 2153.930.00739.28869.4288.46617.51
Aug 2172.240.00811.52869.420.00617.51
Sep 21149.660.00961.19869.4263.49680.99
Oct 21204.070.001165.26869.4231.74712.73
Nov 21220.7667.211386.02936.6395.23807.96
Dec 21199.53470.751585.551407.380.00807.96
Jan 22170.76324.581756.301731.970.00807.96
Feb 2242.3353.881798.631785.850.00807.96
Mar 2246.8759.661845.501845.510.00807.96