Subproject Financial report

work_package_no649
SubprojectSteel Tuss Bridle Bridge over Khurmola Gard at Hayudai Tok
Work Done cost (in lacs)12.83
MonthsPlanned ExpenditureReplanned ExpenditureCum Planned ExpenditureCum Re Planned ExpenditureExpenditureCum Expenditure
Nov 200.320.000.3212.830.000.00
Dec 201.670.001.9912.830.000.00
Jan 214.870.006.8512.830.000.00
Feb 214.850.0011.7012.830.000.00
Mar 215.370.0017.0712.830.000.00
Apr 2116.180.0033.2512.830.000.00
May 2113.400.0046.6612.830.000.00
Jun 216.060.0052.7212.8316.9316.93
Jul 216.960.0059.6912.830.0016.93
Aug 219.350.0069.0412.830.0016.93
Sep 2110.570.0079.6112.830.0016.93
Oct 2114.360.0093.9712.830.0016.93
Nov 216.0761.90100.0474.730.0016.93
Dec 216.2721.21106.3195.940.0016.93
Jan 223.0311.04109.33106.990.0016.93
Feb 220.632.98109.97109.970.0016.93
Expenditure planning in Work Package