Subproject Financial report

work_package_no642
Subproject40M Pedestal Bridge from Bhitarkotof Garud to Par Junior High School
Work Done cost (in lacs)76.75
MonthsPlanned ExpenditureReplanned ExpenditureCum Planned ExpenditureCum Re Planned ExpenditureExpenditureCum Expenditure
Dec 201.700.001.7076.750.000.00
Jan 211.700.003.4176.750.000.00
Feb 213.200.006.6176.750.000.00
Mar 216.390.0013.0076.750.000.00
Apr 216.180.0019.1976.750.000.00
May 2130.030.0049.2176.7521.8421.84
Jun 2128.630.0077.8476.750.0021.84
Jul 2116.170.0094.0276.750.0021.84
Aug 2116.170.00110.1976.750.0021.84
Sep 2115.650.00125.8476.7545.9867.82
Oct 2111.930.00137.7776.750.0067.82
Nov 2110.4652.19148.23128.940.0067.82
Dec 2114.9324.31163.16153.250.0067.82
Jan 2213.1822.28176.34175.540.0067.82
Feb 222.983.78179.32179.320.0067.82
Expenditure planning in Work Package