Subproject Financial report

work_package_no623
SubprojectSteel Truss Bridge on Vijay Kwetha Khatal MR KM-16
Work Done cost (in lacs)181.72
MonthsPlanned ExpenditureReplanned ExpenditureCum Planned ExpenditureCum Re Planned ExpenditureExpenditureCum Expenditure
Feb 201.190.001.19181.720.000.00
Mar 201.580.002.77181.720.000.00
Apr 201.530.004.30181.720.000.00
May 201.580.005.89181.720.000.00
Jun 203.360.009.25181.720.000.00
Jul 205.190.0014.44181.720.000.00
Aug 2011.810.0026.25181.720.000.00
Sep 2016.400.0042.65181.720.000.00
Oct 2014.860.0057.51181.7238.4038.40
Nov 2017.610.0075.13181.723.5841.98
Dec 2015.940.0091.07181.7217.1059.08
Jan 2113.520.00104.59181.7240.0999.17
Feb 2120.100.00124.70181.720.0099.17
Mar 2126.410.00151.11181.7222.70121.87
Apr 2123.360.00174.47181.7229.72151.58
May 217.250.00181.72181.7225.31176.90
Expenditure planning in Work Package