Subproject Financial report

work_package_no621
Subproject36 mtr span bridge steel girder near jakh jakeda motor road.
Work Done cost (in lacs)157.00
MonthsPlanned ExpenditureReplanned ExpenditureCum Planned ExpenditureCum Re Planned ExpenditureExpenditureCum Expenditure
Jan 200.040.000.04157.000.000.00
Feb 200.230.000.27157.000.000.00
Mar 200.520.000.79157.000.000.00
Apr 200.630.001.42157.000.000.00
May 200.650.002.07157.000.000.00
Jun 200.830.002.90157.000.000.00
Jul 201.210.004.11157.000.000.00
Aug 201.210.005.31157.000.000.00
Sep 203.110.008.42157.000.000.00
Oct 203.210.0011.64157.000.000.00
Nov 204.360.0016.00157.000.000.00
Dec 205.020.0021.02157.000.000.00
Jan 215.020.0026.04157.000.000.00
Feb 214.530.0030.57157.000.000.00
Mar 2145.400.0075.97157.000.000.00
Apr 2173.600.00149.56157.000.000.00
May 2121.310.00170.87157.000.000.00
Jun 210.000.00170.87157.0050.9050.90
Jul 210.000.00170.87157.000.0050.90
Aug 210.000.00170.87157.000.0050.90
Sep 210.000.00170.87157.000.0050.90
Oct 210.000.00170.87157.000.000.00
Nov 210.0013.87170.87170.8788.93139.83
Expenditure planning in Work Package