Subproject Financial report

work_package_no613
SubprojectBridge on KM-11 of Agrakhal Kusraila
Work Done cost (in lacs)143.62
MonthsPlanned ExpenditureReplanned ExpenditureCum Planned ExpenditureCum Re Planned ExpenditureExpenditureCum Expenditure
Feb 200.820.000.82143.620.000.00
Mar 200.880.001.70143.620.000.00
Apr 200.850.002.55143.620.000.00
May 200.880.003.42143.620.000.00
Jun 200.850.004.27143.620.000.00
Jul 202.230.006.50143.620.000.00
Aug 208.200.0014.70143.620.000.00
Sep 209.480.0024.18143.620.000.00
Oct 209.730.0033.91143.620.000.00
Nov 2014.090.0048.00143.620.000.00
Dec 2015.060.0063.06143.620.000.00
Jan 2120.300.0083.36143.620.000.00
Feb 217.600.0090.96143.6252.3052.30
Mar 2116.590.00107.55143.623.7256.01
Apr 2121.650.00129.20143.620.0056.01
May 2114.420.00143.62143.6237.6893.70
Expenditure planning in Work Package