Subproject Financial report

work_package_no610
SubprojectBridge Over Gandak River at KM-2 of Champawat to Manch Tamali MR
Work Done cost (in lacs)156.72
MonthsPlanned ExpenditureReplanned ExpenditureCum Planned ExpenditureCum Re Planned ExpenditureExpenditureCum Expenditure
Dec 201.710.001.71156.720.000.00
Jan 214.420.006.13156.720.000.00
Feb 217.380.0013.51156.720.000.00
Mar 2122.000.0035.52156.7218.4518.45
Apr 2128.590.0064.10156.720.0018.45
May 2127.290.0091.40156.7220.4838.92
Jun 2126.410.00117.81156.720.0038.92
Jul 2120.460.00138.28156.7252.2091.13
Aug 218.900.00147.18156.725.6896.80
Sep 2134.220.00181.39156.720.0096.80
Oct 2153.950.00235.34156.720.0096.80
Nov 2116.0094.62251.33251.3423.10119.91
Expenditure planning in Work Package