Project Level Summary
SNo.Project NameRequired Done % Done Passed Failed Complied % Failure Result Awaited
1UDRP-AF(Bridge/Slope)35975374141043706534000.919
2UDRP-AF(RBP)1324813278100.23132483000.230
Total 49223 50692 102.98 50313 370 0 0.73 9
Project Name: UDRP-AF(RBP)
View P Chart (Statistical Report)
SNo. Month Required Done % Done Passed Failed Complied % Failure Result Awaited
1 May,2022 8282100820000
2 April,2022 5575571005570000
3 March,2022 6966961006960000
4 February,2022 5285281005280000
5 January,2022 2962961002960000
6 December,2021 2202201002200000
7 November,2021 1231231001230000
8 July,2021 3838100380000
9 June,2021 2462461002460000
10 May,2021 3543541003540000
11 April,2021 5125121005120000
12 March,2021 1513151310015130000
13 February,2021 1557155710015570000
14 January,2021 1421142110014210000
15 December,2020 7567561007560000
16 November,2020 6286281006280000
17 October,2020 2852851002850000
18 September,2020 2929100290000
19 July,2020 2828100280000
20 June,2020 8585100850000
21 May,2020 1321321001320000
22 April,2020 6868100680000
23 March,2020 3163161003160000
24 February,2020 4644641004640000
25 January,2020 3663661003660000
26 December,2019 3203201003200000
27 November,2019 2482481002480000
28 October,2019 1171171001170000
29 September,2019 1110010000
30 August,2019 1414100140000
31 July,2019 1719111.76190000
32 June,2019 7180112.6878202.50
33 May,2019 202214105.94205904.210
34 April,2019 2542541002421204.720
35 March,2019 432435100.694350000
36 February,2019 174178102.3175301.690
37 January,2019 989810094404.080
Total 13248 13278 100.23 13248 30 0 0.23 0