Project  DEA  DSC Package Year:Month:
Project Level Summary
SNo.Project NameRequired Done % Done Passed Failed Complied % Failure Result Awaited
1UDRP-RB7437277828104.6574957287128743.690
2UEAP-RB5537858356105.385717410500.18174
3UDRP-H1435143510014350000
4UEAP-WS478479100.214790000
5UEAP-T5859101.7258101.690
6UDRP-AF3553551003233209.010
7IRRIGATION989810094404.080
Total 132174 138610 104.87 134520 3013 2874 2.17 174