Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Dewali RB Alaknanda Agreement signed
Project: IRRIGATION UID: 7412 Sanction Cost: 2566.00  lakh Length: 0.726 KM.
District: Tehri Block: Kirtinagar Constituency: Deoprayag Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision Type: River Protection Work
Procurement:
Package No.: 3002        Package Name:  UDRP/AF/RBP/05        Tender Date: 31-01-2018        Current Status: Agreement signed        Achieved on Date: 25-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/05      Contractor Name: Bharat Construction
Start Date:  05-11-2018      Intended Completion Date:  18-03-2021      Original End Date:  04-05-2020
Total Bond Cost: 222747269 (2227.47 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 55464252 for 498 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works0.00 m0.0005-11-201805-11-20180.00 m0.00 m00.00
2.Env. Man & Moni Plan2.00 Job1.7001-12-201831-08-20202.00 Job1.00 Job0.040.85
3.Other Allied Works & Finishing Work 15.00 Job6.9501-01-201931-08-202015.00 Job4.00 Job0.091.85
4.Excavation in Foundation18730.00 cum31.8415-11-201831-08-202018730.00 cum18730.00 cum1.631.84
5.PCC in Foundation581.00 cum30.7901-02-201931-08-2020581.00 cum581.00 cum1.5530.79
6.Construction Embankments40564.00 cum60.8515-06-201931-08-202040564.00 cum2547.16 cum0.193.82
7.Launching Aprons4356.00 cum117.6115-06-201931-08-20204356.00 cum3240.00 cum4.487.48
8.Excavation in soil15246.00 cum25.9215-11-201831-08-202015246.00 cum15148.00 cum1.2925.75
9.CC in R/W and B/W13318.00 cum912.4101-03-201931-08-202013318.00 cum8077.67 cum27.82553.38
10.TMT Bar in R/W1426.00 mt770.0401-03-201931-08-20201426.00 mt920.00 mt24.98496.83
11.H.P. Stone3412.00 cum30.7115-06-201931-08-20203412.00 cum635.88 cum0.295.72
Total Amount: 1988.82 62.26   1238.31
Remarks: No Remarks       Work Program Made On: 31-01-2019        Updation of work program on: 22-06-2020       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.31-March-2019171.79  lakh
2.29-June-2019149.09  lakh
3.23-October-201965.87  lakh
4.24-December-2019132.00  lakh
5.25-February-2020320.84  lakh
6.06-March-2020287.67  lakh
7.06-May-2020160.61  lakh
8.08-October-202014.97  lakh
Total 1302.84  lakh
% Payment 58.48 %
Advance Amount:  99.44  lakh        Recovered Amount:  99.44  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1959   No. of Test Done : 1972    No. of Test Passed : 1959   No. of Test Failed : 13   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.54
Number of Notice(s) issued: 110

Mobile Pic Upload

Number of Pics Available on Web Repository: 360
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.20-11-2020Panel no-44, 4th 516-528 c/WallConcrete cube testVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
2.11-11-2020Panel no-18, 3rd lift ch-204-216M-25 RCC concrete workVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
3.11-11-2020Panel no-44, 5th lift 516-528Reinforcement shuttering workVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
4.10-11-2020Panel no-43, 4th lift HPS fillingHPS FILLINGVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
5.10-11-2020Panel no-45, 528-540, 5th liftReinforcement shuttering workVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
6.09-11-2020Panel no 46,540-552, 5th liftM-25 RCC concrete workVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
7.07-11-2020Panel no-47, 5th lift ch-552-564 c/wallReinforcement shuttering workVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
8.07-11-2020Panel no-17, 3rd lift change-192-204 c/wallM-25 RCC concrete workVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
9.04-11-2020Panel no-50, 5th lift change-588-600Reinforcement shuttering workVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
10.04-11-2020Panel no-49, 5th, lift change-576-588Reinforcement workVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
11.03-11-2020Panel no-9, 2nd ch-96-108M-25 RCC concrete workVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
12.28-10-2020Panel no 46 ch-540 to 552Rcc m-25 concreting wall and counterfort 4th liftYogesh SrivastavaSite SupervisorDSC WB Irrigation Tehri See Pic
13.27-10-2020Panel no. 52 ch-612 to 624Rcc m-25 concreting wall and counterfort 4th liftYogesh SrivastavaSite SupervisorDSC WB Irrigation Tehri See Pic
14.27-10-2020Panel no. 44 ch 516-528Rcc m-25 concreting wall and counterfort 4th liftYogesh SrivastavaSite SupervisorDSC WB Irrigation Tehri See Pic
15.27-10-2020Panel no. 38 ch-444-456Rcc m-25 concreting wall 4th liftYogesh SrivastavaSite SupervisorDSC WB Irrigation Tehri See Pic
16.27-10-2020Panel no 38 ch-432 to 444RCC m-25 concreting wall and counterfort 3rd liftYogesh SrivastavaSite SupervisorDSC WB Irrigation Tehri See Pic
17.21-10-2020Panel no 52 ch-612 -624Steel stuttering work at progress wall and counterfort 4th liftYogesh SrivastavaSite SupervisorDSC WB Irrigation Tehri See Pic
18.21-10-2020Panel no-52, 4th lift 612-624Reinforcement shutteringVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
19.21-10-2020Panel no-57, 3rd lift ch-672-684M-25rcc concrete workVinod Kumar GuptaQCDSC WB Irrigation Tehri See Pic
20.20-10-2020Panel no. 53 ch-624 to 636Steel stuttering work wall and counterfort 4th liftYogesh SrivastavaSite SupervisorDSC WB Irrigation Tehri See Pic