Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Dewali RB Alaknanda Work Completed
Project: UDRP-AF(RBP) UID: 7412 Sanction Cost: 2566.00  lakh Length: 0.726 KM.
District: Tehri Block: Kirtinagar Constituency: Deoprayag Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision Type: River Protection Work
Procurement:
Package No.: 3002        Package Name:  UDRP/AF/RBP/05        Tender Date: 31-01-2018        Current Status: Agreement signed        Achieved on Date: 25-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/05      Contractor Name: Bharat Construction
Start Date:  05-11-2018      Intended Completion Date:  25-12-2021      Original End Date:  04-05-2020
Total Bond Cost: 222747269 (2227.47 lakh)        Variation Cost: 9845037.00 (98.45 lakh)    Hence Total Bond Cost is   232592306 (2325.92 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 55464252 for 498 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan2.00 Job1.9001-12-201825-12-20212.00 Job2.00 Job0.081.90
2.Other Allied Works & Finishing Work 15.00 Job8.2701-01-201925-12-202115.00 Job15.00 Job0.348.27
3.Excavation in Foundation23890.33 cum45.4915-11-201825-12-202123890.33 cum23890.33 cum1.5545.49
4.PCC in Foundation742.50 cum44.0701-02-201925-12-2021742.50 cum742.50 cum1.544.07
5.Construction Embankments37106.00 cum62.3415-06-201925-12-202137106.00 cum37106.00 cum2.9762.34
6.Launching Aprons4394.14 cum132.8815-06-201925-12-20214394.14 cum4394.14 cum5.74132.88
7.Excavation in soil16495.20 cum31.4115-11-201825-12-202116495.20 cum16495.20 cum1.2731.41
8.CC in R/W and B/W13816.55 cum1060.4801-03-201925-12-202113816.55 cum13816.55 cum44.521000.00
9.TMT Bar in R/W1410.49 mt853.0601-03-201925-12-20211410.49 mt1410.49 mt37.57853.06
10.H.P. Stone3211.73 cum32.3715-06-201925-12-20213211.73 cum3211.73 cum1.532.37
11.Construction of Ghats1.00 Job60.7009-01-202124-12-20211.00 Job1.00 Job2.9660.70
Total Amount: 2332.97 100   2272.49
Remarks: No Remarks       Work Program Made On: 31-01-2019        Updation of work program on: 28-05-2022       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-2019171.79  lakh
2.29-June-2019149.09  lakh
3.23-October-201965.87  lakh
4.24-December-2019132.00  lakh
5.25-February-2020320.84  lakh
6.06-March-2020287.67  lakh
7.06-May-2020160.61  lakh
8.08-October-202014.97  lakh
9.12-November-2020158.30  lakh
10.17-November-202056.71  lakh
11.24-December-2020216.20  lakh
12.25-January-202118.17  lakh
13.01-February-2021153.76  lakh
14.27-March-2021273.95  lakh
15.31-March-202150.00  lakh
16.30-September-202167.28  lakh
17.31-March-202219.27  lakh
18.31-May-20229.29  lakh
Total 2325.77  lakh
% Payment 100.01 %
Advance Amount:  99.44  lakh        Recovered Amount:  99.44  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 4284   No. of Test Done : 4297    No. of Test Passed : 4284   No. of Test Failed : 13   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.36
Number of Notice(s) issued: 151

Mobile Pic Upload

Number of Pics Available on Web Repository: 495
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-03-2022Devali-jakhniChanging room work is completed 24/12/21.PRABHAT BALONI ` ` See Pic
2.31-03-2022Devali-jakhniGhat work is completed 25/12/21.PRABHAT BALONI ` ` See Pic
3.31-03-2022Devali-jakhniGhat work ( staircase) is completed 25/12/21.PRABHAT BALONI ` ` See Pic
4.17-01-2022Devali-jakhniCounterfort retaining wall work is completed 18/03/21PRABHAT BALONI ` ` See Pic
5.17-01-2022Devali-jakhniCounterfort retaining wall work is completed 18/03/21PRABHAT BALONI ` ` See Pic
6.17-01-2022Devali-jakhniCounterfort retaining wall work is completed 18/03/21PRABHAT BALONI ` ` See Pic
7.17-01-2022Devali-jakhnicounterfort retaining wall work is completed 18/03/2021PRABHAT BALONI ` ` See Pic
8.07-12-2021Devali-jakhniDiversion work in progressPRABHAT ` ` See Pic
9.01-12-2021Devali-jakhniDiversion work in progressPRABHAT ` ` See Pic
10.27-11-2021Devali-jakhniDiversion work in progressPRABHAT ` ` See Pic
11.25-11-2021Devali-jakhniDiversion work in progressPRABHAT ` ` See Pic
12.24-11-2021Devali-jakhniRiver diversion work in progress.PRABHAT ` ` See Pic
13.20-11-2021Devali-jakhniRiver diversion work in progressPRABHAT BALONI ` ` See Pic
14.01-11-2021Panel no 37,38Water level approx 1.4 mtrVinod Kumar Gupta ` ` See Pic
15.30-10-2021Up stream side water level 1.2 mtrNo increase water levelVinod Kumar Gupta ` ` See Pic
16.29-10-2021Panel no 36 at water levelNo increase water level approx 1.4Vinod Kumar Gupta ` ` See Pic
17.28-10-2021Down stream side water levelWater level approx 2.4 mtrVinod Kumar Gupta ` ` See Pic
18.27-10-2021Up stream sideWater level approx at 1.00 mtrVinod Kumar Gupta ` ` See Pic
19.25-10-2021Devali-jakhniRiver water level U/S side.PRABHAT ` ` See Pic
20.25-10-2021Devali-jakhniRiver water level d/s sidePRABHAT ` ` See Pic