Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Maithana Alaknanda Agreement signed
Project: UDRP-AF(RBP) UID: 7409 Sanction Cost: 1310.00  lakh Length: 0.450 KM.
District: Chamoli Block: Dasholi Constituency: Badrinath Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision Type: River Protection Work
Procurement:
Package No.: 3004        Package Name:  UDRP/AF/RBP/08        Tender Date: 16-10-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/08      Contractor Name: M/S Ajay kumar contractor
Start Date:  29-01-2020      Intended Completion Date:  15-05-2022      Original End Date:  28-07-2021
Total Bond Cost: 107897353 (1078.97 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 27513990 for 510 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan6.00 Job3.2815-02-202015-05-20226.00 Job5.50 Job0.313.01
2.Other Allied Works & Finishing Work 15.00 Job23.4915-03-202015-05-202215.00 Job14.00 Job2.2821.93
3.Excavation in Foundation4738.00 cum14.3115-02-202015-05-20224738.00 cum4738.00 cum1.4914.31
4.PCC in Foundation380.00 cum19.8801-03-202015-05-2022380.00 cum378.70 cum2.0619.81
5.Construction Embankments19401.00 cum10.5922-03-202015-05-202219401.00 cum18500.00 cum1.0510.10
6.Launching Aprons931.50 cum78.9615-03-202015-05-2022931.50 cum921.60 cum8.1178.12
7.Excavation in soil18457.00 cum7.0615-02-202015-05-202218457.00 cum13889.00 cum0.555.31
8.CC in R/W and B/W10679.50 cum636.8201-03-202015-05-202210679.50 cum10628.49 cum65.79633.78
9.RRM in R/W and B/W4860.00 cum151.6415-03-202015-05-20224860.00 cum4860.00 cum15.74151.64
10.TMT Bar in R/W25.50 mt13.2401-03-202015-05-202225.50 mt25.50 mt1.3713.24
11.H.P. Stone3823.00 cum4.0922-03-202015-05-20223823.00 cum2869.00 cum0.323.07
Total Amount: 963.36 99.06   954.32
Remarks: No Remarks       Work Program Made On: 13-02-2020        Updation of work program on: 27-05-2022       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.27-March-2021312.92  lakh
2.31-March-202194.95  lakh
3.14-June-2021127.94  lakh
4.09-July-2021132.59  lakh
5.28-March-2022218.79  lakh
6.07-May-2022158.17  lakh
Total 1045.36  lakh
% Payment 96.89 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): EMP
Detailed report of this subproject
Quality
No. of Test Required : 2710   No. of Test Done : 2710    No. of Test Passed : 2710   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
Number of Notice(s) issued: 88

Mobile Pic Upload

Number of Pics Available on Web Repository: 160
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-01-2022M15 lift 3 shuttering work in progressMaithana sitePraveen Singh Negi ` ` See Pic
2.17-01-2022Location 190-200 raftRaft second liftVinod Kumar Gupta ` ` See Pic
3.17-01-2022Maithana D/S ch.190-200 M15 2nd liftShuttering work in progressPraveen Singh Negi ` ` See Pic
4.08-01-2022Maithana siteBoulder breakingAmit pundirunknownunknown See Pic
5.05-01-2022Maithana siteSocial and environment visitAmit pundirunknownunknown See Pic
6.05-01-2022Mainthana siteSocial and environment visitAmit pundirunknownunknown See Pic
7.04-01-2022Maithana siteDiversion workAmit pundirunknownunknown See Pic
8.04-01-2022Maithana siteBoulder breakingAmit pundirunknownunknown See Pic
9.04-01-2022MAITHANA SITEDiversion WorkAmit Pundir ` ` See Pic
10.30-12-2021Maithana siteDiversion workAmit pundirunknownunknown See Pic
11.27-12-2021Maithana siteRiver diversionAmit pundirunknownunknown See Pic
12.24-12-2021Maithana siteDiversion workAmit pundirunknownunknown See Pic
13.23-12-2021Maithana siteDiversion workAmit pundirunknownunknown See Pic
14.21-12-2021Maithana siteDiversion workAmit pundirunknownunknown See Pic
15.20-12-2021Maithana siteDiversion workAmit pundirunknownunknown See Pic
16.18-12-2021Maithana siteRiver diversionAmit pundirunknownunknown See Pic
17.17-12-2021Maithana siteDiversion workAmit pundirunknownunknown See Pic
18.16-12-2021Maithana siteRiver diversionAmit pundirunknownunknown See Pic
19.15-12-2021Maithana siteDiverson workAmit pundeer ` ` See Pic
20.15-12-2021Maithana siteDiversion workAmit pundirunknownunknown See Pic