Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Maithana Alaknanda Work Completed
Project: IRRIGATION UID: 7409 Sanction Cost: 1310.00  lakh Length: 0.450 KM.
District: Chamoli Block: Dasholi Constituency: Badrinath Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision Type: River Protection Work
Procurement:
Package No.: 3004        Package Name:  UDRP/AF/RBP/08        Tender Date: 16-10-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/08      Contractor Name: M/S Ajay kumar contractor
Start Date:  29-01-2020      Intended Completion Date:  28-07-2021     
Total Bond Cost: 107897353 (1078.97 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 16562343 for 307 days        LD Analysis for Milestone2: calculated LD is Rs 16562343 for 307 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan6.00 Job3.2815-02-202031-08-20200.00 Job0.00 Job00.00
2.Other Allied Works & Finishing Work 15.00 Job23.4915-03-202031-08-20200.00 Job0.00 Job00.00
3.Excavation in Foundation4738.00 cum14.3115-02-202031-08-20200.00 cum0.00 cum00.00
4.PCC in Foundation380.00 cum19.8801-03-202031-08-20200.00 cum0.00 cum00.00
5.Construction Embankments19401.00 cum10.5922-03-202031-08-20200.00 cum0.00 cum00.00
6.Launching Aprons931.50 cum78.9615-03-202031-08-20200.00 cum0.00 cum00.00
7.Excavation in soil18457.00 cum7.0615-02-202031-08-20200.00 cum0.00 cum00.00
8.CC in R/W and B/W10679.50 cum636.8201-03-202031-08-20200.00 cum0.00 cum00.00
9.RRM in R/W and B/W4860.00 cum151.6415-03-202031-08-20200.00 cum0.00 cum00.00
10.TMT Bar in R/W25.50 mt13.2401-03-202031-08-20200.00 mt0.00 mt00.00
11.H.P. Stone3823.00 cum4.0922-03-202031-08-20200.00 cum0.00 cum00.00
Total Amount: 963.36 0   0
Remarks: No Remarks       Work Program Made On: 13-02-2020        Updation of work program on: 23-06-2020       
Work Program Status:Program Expired.
Financial Progress
No Financial Progress.
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality ranking not done.
Number of Notice(s) issued: 16

Mobile Pic Upload

No Pics Available on Web Repository
( last 20 Pics)
No Pic uploaded.