Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Alakapuri Kathiyal Sain Alaknanda Agreement signed
Project: IRRIGATION UID: 7408 Sanction Cost: 1517.00  lakh Length: 450.000 KM.
District: Chamoli Block: Dasholi Constituency: Karanprayag Circle:
DEA: DEA RPW DSC: DSC Scope: Design and Supervision Type: River Protection Work
Procurement:
Package No.: 3000        Package Name:  UDRP/AF/RBP/02        Tender Date: 31-01-2018        Current Status: Agreement signed        Achieved on Date: 25-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/02      Contractor Name: GSCO Infrastructure Pvt Ltd.
Start Date:  05-11-2018      Intended Completion Date:  04-05-2020     
Total Bond Cost: 109958636.25 (1099.59 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 4453299 for 81 days        LD Analysis for Milestone2: 102 days remained       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works0.00 m0.0005-11-201805-11-20180.00 m0.00 m00.00
2.Env. Man & Moni Plan2.00 Job1.3601-12-201830-09-20192.00 Job1.00 Job0.060.68
3.Other Allied Works & Finishing Work 15.00 Job28.8301-01-201930-09-201915.00 Job3.00 Job0.525.77
4.Excavation in Foundation7301.00 cum18.2515-11-201830-09-20197301.00 cum2168.34 cum0.495.42
5.PCC in Foundation467.00 cum25.2215-01-201930-09-2019467.00 cum75.00 cum0.374.05
6.Construction Embankments8974.00 cum4.9401-04-201930-09-20198974.00 cum111.61 cum0.010.06
7.Launching Aprons2180.00 cum132.9815-06-201930-09-20192180.00 cum0.00 cum00.00
8.Excavation in soil33849.00 cum15.2315-11-201830-09-201933849.00 cum3938.63 cum0.161.77
9.CC in R/W and B/W7711.00 cum471.1001-03-201930-09-20197711.00 cum1609.00 cum8.9498.32
10.RRM in R/W and B/W11971.69 cum374.1201-03-201930-09-201911971.69 cum631.00 cum1.7919.72
11.TMT Bar in R/W11.00 mt6.3801-03-201930-09-201911.00 mt3.35 mt0.181.94
12.H.P. Stone3850.00 cum21.1801-03-201930-09-20193850.00 cum116.85 cum0.060.64
Total Amount: 1099.59 12.58   138.37
Remarks: No Remarks       Work Program Made On: 31-01-2019        Updation of work program on: 18-06-2019       
Work Program Status:Program Failed
Financial Progress
SNo. Date Payment
1.18-March-201938.93  lakh
2.14-May-201952.91  lakh
3.18-July-201958.51  lakh
Total 150.35  lakh
% Payment 13.67 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): Conscent to establish., conscent to operate
Environment & Social Compliances(Sub Project level): EMP, debris disposal
Detailed report of this subproject
Quality
No. of Test Required : 278   No. of Test Done : 279    No. of Test Passed : 269   No. of Test Failed : 10   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.56
Number of Notice(s) issued: 6

Mobile Pic Upload

Number of Pics Available on Web Repository: 188
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-07-2019KothiyalsainToday's kothiyalsain site sampling filled for mix desgin Grade of M20 and M30Ashutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
2.22-07-2019KothiyalsainSection-01Ashutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
3.22-07-2019KothiyalsainWater level increaseAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
4.11-07-2019KothiyalsainWater level increased todayAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
5.27-06-2019KothiyalsainWater level increaseAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
6.25-06-2019KothiyalsainCube testAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
7.24-06-2019KothiyalsainKothiyalsain siteAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
8.13-06-2019KothiyalsainLevel checking ch 160 to 170Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
9.06-06-2019KothiyalsainVisit Respected sir world bank team & FPIU and UDRPAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
10.05-06-2019KothiyalsainWaterlogging section-07Ashutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
11.05-06-2019KothiyalsainRRM work section-07 CH-300 to 310 mAshutosh UniyalSite SupervisorCSC WB Irrigation Chamoli See Pic
12.31-05-2019KothiyalsainExcavation work ch.380 to 390Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
13.24-05-2019KothiyalsainExcavation work ch .360 to 370Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
14.24-05-2019Kothiyaal sainCube test M20 28 daysManish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
15.23-05-2019KothiyalsainBoulders breaking workManish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
16.23-05-2019KothiyalsainFacia concrete nominal mix 1:2:4 ch.300 to 310Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
17.22-05-2019KothiyalsainPcc work ch.350 to 360Manish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
18.17-05-2019kothiyalsainsite visit PIU Expert TeamPraveen Singh NegiJEUDRP-AF Irrigation Chamoli See Pic
19.16-05-2019KothiyalsainSite visit.PIU. UDRP teamManish Singh PanwarJEUDRP-AF Irrigation Chamoli See Pic
20.15-05-2019kothiyalsain chainage 320-330RRM at section 320-330Praveen Singh NegiJEUDRP-AF Irrigation Chamoli See Pic