Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Banswara Mandakani Work Completed
Project: IRRIGATION UID: 7404 Sanction Cost: 738.00  lakh Length: 0.902 KM.
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA RPW DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision Type: River Protection Work
Procurement:
Package No.: 3003        Package Name:  UDRP/AF/RBP/07        Tender Date: 16-08-2019        Current Status: Agreement signed        Achieved on Date: 14-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/RBP/07      Contractor Name: Chaudhary Sandeep Contractor & Suppliers
Start Date:  21-01-2020      Intended Completion Date:  20-07-2021     
Total Bond Cost: 61098635 (610.99 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 9653484 for 316 days        LD Analysis for Milestone2: calculated LD is Rs 9653484 for 316 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan6.00 Job3.2801-02-202031-08-20200.00 Job0.00 Job00.00
2.Other Allied Works & Finishing Work 15.00 Job12.6715-03-202031-08-20200.00 Job0.00 Job00.00
3.Excavation in Foundation4119.00 cum12.1415-02-202031-08-20200.00 cum0.00 cum00.00
4.PCC in Foundation304.00 cum15.5801-03-202031-08-20200.00 cum0.00 cum00.00
5.Construction Embankments4921.00 cum2.6822-03-202031-08-20200.00 cum0.00 cum00.00
6.Launching Aprons836.00 cum69.0715-03-202031-08-20200.00 cum0.00 cum00.00
7.Excavation in soil11039.00 cum4.3115-02-202031-08-20200.00 cum0.00 cum00.00
8.CC in R/W and B/W3711.00 cum226.4201-03-202031-08-20200.00 cum0.00 cum00.00
9.RRM in R/W and B/W5534.00 cum169.2315-03-202031-08-20200.00 cum0.00 cum00.00
10.TMT Bar in R/W27.00 mt13.9401-03-202031-08-20200.00 mt0.00 mt00.00
11.H.P. Stone2470.00 cum16.2122-03-202031-08-20200.00 cum0.00 cum00.00
Total Amount: 545.53 0   0
Remarks: No Remarks       Work Program Made On: 13-02-2020        Updation of work program on: 23-06-2020       
Work Program Status:Program Expired.
Financial Progress
No Financial Progress.
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality ranking not done.
Number of Notice(s) issued: 15

Mobile Pic Upload

Number of Pics Available on Web Repository: 10
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-11-2020Banswada siteStone breaking workASHISH SINGHunknownunknown See Pic
2.06-11-2020Banswada siteExcavation workASHISH SINGHunknownunknown See Pic
3.04-11-2020Excavation workBanswada siteASHISH SINGHunknownunknown See Pic
4.03-11-2020Banswada siteExcavation workASHISH SINGHunknownunknown See Pic
5.28-10-2020Banswada siteExcavation work at Banswada siteASHISH SINGHunknownunknown See Pic
6.20-10-2020Banswada siteLevel checking at Banswada siteASHISH SINGHunknownunknown See Pic
7.13-08-2020BanswadaBanswara siteDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
8.07-08-2020BanswadaBanswara siteDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
9.15-06-2020BanswadaBoard marked as do's and don't regarding Corona at BanswadaDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
10.15-06-2020BanswadaProject information board of Banswada SiteDeepak PantSite supervisiorUDRP AF Irrigation birahi See Pic