Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Retrofitting and Renovation of Government Inter College Peeradhanpur Work Completed
Project: UDRP-H UID: 7323 Sanction Cost: 30.28  lakh Length: 0.000 KM.
District: Rudraprayag Block: August Muni Constituency: Kedarnath Circle:
DEA: DEA PB DSC: Sheladia Associates DSC Scope: Design and Supervision Type: Not known
Procurement:
Package No.: 2269        Package Name:  18A/BC/PIU/BRIDCUL/PB/2018        Tender Date: 19-12-2018        Current Status: Agreement signed        Achieved on Date: 28-01-2019

Construction Phase

Agreement Details
Bond/Agreement Name: 18A/BC/PIU/BRIDCUL/PB/2018      Contractor Name: Surat Singh & Sons
Start Date:  28-01-2019      Intended Completion Date:  30-06-2019      Original End Date:  28-05-2019
Total Bond Cost: 2734374.83 (27.34 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 209151 for 153 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan1.00 Job0.8815-03-201927-05-20191.00 Job1.00 Job3.240.88
2.Retrofitting1.00 job12.7228-01-201915-04-20191.00 job1.00 job46.5112.72
3.Renovation1.00 job13.7410-04-201927-05-20191.00 job1.00 job50.2613.74
Total Amount: 27.34 100   27.34
Remarks: No Remarks       Work Program Made On: 27-03-2019        Updation of work program on:       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.04-June-20194.21  lakh
2.29-August-201916.63  lakh
Total 20.84  lakh
% Payment 76.23 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 6   No. of Test Done : 6    No. of Test Passed : 6   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.49
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 42
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-05-2019G I C Peera DhanpurCeiling plaster work in progress.Himanshu SharmaJEUDRP-H Rudraprayag See Pic
2.28-05-2019G I C Peera DhanpurPlaster work in progress.Himanshu SharmaJEUDRP-H Rudraprayag See Pic
3.08-05-2019G I C Peera DhanpurWater proofing work in progress at Block AHimanshu SharmaJEUDRP-H Rudraprayag See Pic
4.08-05-2019G I C Peera DhanpurCuringHimanshu SharmaJEUDRP-H Rudraprayag See Pic
5.02-05-2019G I C Peera DhanpurWire mesh fixing at Block E, inner wallsHimanshu SharmaJEUDRP-H Rudraprayag See Pic
6.02-05-2019G I C Peera DhanpurFixing wire mesh at Block EHimanshu SharmaJEUDRP-H Rudraprayag See Pic
7.28-04-2019G I C Peera DhanpurWater proofing work at Block G in progress.Himanshu SharmaJEUDRP-H Rudraprayag See Pic
8.28-04-2019G I C Peera DhanpurWater proofing treatment work in progress.Himanshu SharmaJEUDRP-H Rudraprayag See Pic
9.28-04-2019G I C Peera DhanpurRetro fitting-BLOCK A, drilling holesHimanshu SharmaJEUDRP-H Rudraprayag See Pic
10.28-04-2019G I C Peera DhanpurRetro fitting-BLOCK E (Roof treatment -pre surface treatment)Himanshu SharmaJEUDRP-H Rudraprayag See Pic
11.22-04-2019G I C PEERA DHANPURBlock- GHimanshu SharmaJEUDRP-H Rudraprayag See Pic
12.22-04-2019G I C Peera DhanpurBlock AHimanshu SharmaJEUDRP-H Rudraprayag See Pic
13.22-04-2019G I C Peera DhanpurBlock AHimanshu SharmaJEUDRP-H Rudraprayag See Pic
14.22-04-2019G I C Peera DhanpurBlock-FHimanshu SharmaJEUDRP-H Rudraprayag See Pic
15.22-04-2019G I C Peera DhanpurBlock DHimanshu SharmaJEUDRP-H Rudraprayag See Pic
16.16-03-2019G I C KothgiGroove cutting for fixing additional reinforcement in Lintel band level at Block A.Himanshu SharmaJEUDRP-H Rudraprayag See Pic
17.16-03-2019G I C KothgiGroove cutting for fixing additional reinforcement at Lintel bend level at Block B.Himanshu SharmaJEUDRP-H Rudraprayag See Pic
18.16-03-2019G I C KothgiChipping of unsound material for water proofing at Block CHimanshu SharmaJEUDRP-H Rudraprayag See Pic
19.16-03-2019G I C Peera DhanpurMasonry work for closing of earlier windows in progress.Himanshu SharmaJEUDRP-H Rudraprayag See Pic
20.16-03-2019G I C Peera DhanpurChipping of unsound material over roof for water proofing at Block AHimanshu SharmaJEUDRP-H Rudraprayag See Pic