Retrofitting and Renovation of Government Inter College Peeradhanpur
Work Completed
|
Project: |
UDRP-H |
UID: |
7323 |
Sanction Cost: |
30.28 lakh |
Length:
|
0.000 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA PB |
DSC: |
Sheladia Associates |
DSC Scope: |
Design and Supervision |
Type: |
Not known |
|
Procurement: |
Package No.: 2269
Package Name: 
18A/BC/PIU/BRIDCUL/PB/2018
Tender Date: 19-12-2018
Current Status: Agreement signed
Achieved on Date: 28-01-2019 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 18A/BC/PIU/BRIDCUL/PB/2018
Contractor Name: Surat Singh & Sons
|
Start Date: 28-01-2019
Intended Completion Date: 30-06-2019
Original End Date: 28-05-2019 |
Total Bond Cost: 2734374.83 (27.34 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 209151 for 153 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Env. Man & Moni Plan | 1.00 Job | 0.88 | 15-03-2019 | 27-05-2019 | 1.00 Job | 1.00 Job | 3.24 | 0.88 | 2. | Retrofitting | 1.00 job | 12.72 | 28-01-2019 | 15-04-2019 | 1.00 job | 1.00 job | 46.51 | 12.72 | 3. | Renovation | 1.00 job | 13.74 | 10-04-2019 | 27-05-2019 | 1.00 job | 1.00 job | 50.26 | 13.74 |
Total Amount: |
27.34 |
|
100 |
27.34 |
|
Remarks:
No Remarks
Work Program Made On:
27-03-2019 } ?>
Updation of work program on:
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-June-2019 | 4.21 lakh | 2. | 29-August-2019 | 16.63 lakh |
Total |
20.84 lakh |
% Payment |
76.23 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 6 No. of Test Done : 6 No. of Test Passed : 6 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 92.49 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 42 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-05-2019 | G I C Peera Dhanpur | Ceiling plaster work in progress. | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
2. | 28-05-2019 | G I C Peera Dhanpur | Plaster work in progress. | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
3. | 08-05-2019 | G I C Peera Dhanpur | Water proofing work in progress at Block A | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
4. | 08-05-2019 | G I C Peera Dhanpur | Curing | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
5. | 02-05-2019 | G I C Peera Dhanpur | Wire mesh fixing at Block E, inner walls | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
6. | 02-05-2019 | G I C Peera Dhanpur | Fixing wire mesh at Block E | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
7. | 28-04-2019 | G I C Peera Dhanpur | Water proofing work at Block G in progress. | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
8. | 28-04-2019 | G I C Peera Dhanpur | Water proofing treatment work in progress. | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
9. | 28-04-2019 | G I C Peera Dhanpur | Retro fitting-BLOCK A, drilling holes | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
10. | 28-04-2019 | G I C Peera Dhanpur | Retro fitting-BLOCK E (Roof treatment -pre surface treatment) | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
11. | 22-04-2019 | G I C PEERA DHANPUR | Block- G | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
12. | 22-04-2019 | G I C Peera Dhanpur | Block A | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
13. | 22-04-2019 | G I C Peera Dhanpur | Block A | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
14. | 22-04-2019 | G I C Peera Dhanpur | Block-F | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
15. | 22-04-2019 | G I C Peera Dhanpur | Block D | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
16. | 16-03-2019 | G I C Kothgi | Groove cutting for fixing additional reinforcement in Lintel band level at Block A. | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
17. | 16-03-2019 | G I C Kothgi | Groove cutting for fixing additional reinforcement at Lintel bend level at Block B. | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
18. | 16-03-2019 | G I C Kothgi | Chipping of unsound material for water proofing at Block C | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
19. | 16-03-2019 | G I C Peera Dhanpur | Masonry work for closing of earlier windows in progress. | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
20. | 16-03-2019 | G I C Peera Dhanpur | Chipping of unsound material over roof for water proofing at Block A | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
|
|