Fire Station Ratura
Work Completed
|
Project: |
UDRP-H |
UID: |
7321 |
Sanction Cost: |
535.00 lakh |
Length:
|
0.000 KM. |
District: |
Rudraprayag |
Block: |
0017 |
Constituency: |
7 |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
Type: |
H1 |
|
Procurement: |
Package No.: 2265
Package Name: 
15/BC/PIU/USIDCL/PB/2015-16
Tender Date: 29-01-2016
Current Status: Agreement signed
Achieved on Date: 28-03-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 15/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Makin Developers Pvt. Ltd.
|
Start Date: 01-04-2016
Intended Completion Date: 25-06-2018
Original End Date: 01-07-2017 |
Total Bond Cost: 59740626 (597.41 lakh)
Variation Cost: 3717002.49 (37.17 lakh) Hence Total Bond Cost is 63457628.49 (634.58 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 2031160 for 68 days
LD Analysis for Milestone2: calculated LD is Rs 836360 for 28 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 21.55 Job | 136.75 | 01-04-2016 | 08-06-2018 | 21.55 Job | 21.55 Job | 21.55 | 136.75 | 2. | Foundation and Plinth Work | 17.03 Job | 108.07 | 15-04-2016 | 30-06-2017 | 17.03 Job | 17.03 Job | 17.03 | 108.07 | 3. | Structural Frame | 34.76 Job | 220.58 | 01-07-2016 | 05-06-2018 | 34.76 Job | 34.76 Job | 34.76 | 220.58 | 4. | Doors & Windows | 7.61 Job | 48.29 | 15-12-2016 | 10-06-2018 | 7.61 Job | 7.61 Job | 7.61 | 48.29 | 5. | Water Supply and Sanitary work | 1.36 Job | 8.63 | 15-01-2017 | 22-06-2018 | 1.36 Job | 1.36 Job | 1.36 | 8.63 | 6. | Electrification Works | 5.58 Job | 35.41 | 01-09-2016 | 20-06-2018 | 5.58 Job | 5.58 Job | 5.58 | 35.41 | 7. | Other Allied Works & Finishing Work | 12.10 Job | 76.85 | 15-04-2016 | 25-06-2018 | 12.10 Job | 12.10 Job | 12.11 | 76.85 |
Total Amount: |
634.58 |
|
100 |
634.58 |
|
Remarks:
No Remarks
Work Program Made On:
06-05-2016 } ?>
Updation of work program on:
10-07-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-October-2016 | 24.70 lakh | 2. | 20-December-2016 | 18.49 lakh | 3. | 20-February-2017 | 47.93 lakh | 4. | 27-February-2017 | 19.63 lakh | 5. | 31-March-2017 | 34.44 lakh | 6. | 21-June-2017 | 46.89 lakh | 7. | 12-October-2017 | 91.60 lakh | 8. | 25-January-2018 | 84.18 lakh | 9. | 26-May-2018 | 98.14 lakh | 10. | 21-August-2018 | 71.49 lakh | 11. | 30-March-2019 | 97.07 lakh |
Total |
634.56 lakh |
% Payment |
100 % |
|
Advance Amount: 11.68 lakh
Recovered Amount: 11.68 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 172 No. of Test Done : 204 No. of Test Passed : 189 No. of Test Failed : 15 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 93.00 |
Number of Notice(s) issued: 58 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 257 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-02-2019 | Ratura | Badminton court | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
2. | 23-02-2019 | Ratura | Rear view | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
3. | 23-02-2019 | Ratura | View | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
4. | 23-02-2019 | Ratura | Site View | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
5. | 08-01-2019 | Ratura | Site view, work in progress | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
6. | 08-01-2019 | Ratura | 3 D Rear view | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
7. | 08-01-2019 | Ratura | Departure of CISF Expedition team | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
8. | 08-01-2019 | Ratura | CISF Expedition team halt at building | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
9. | 08-01-2019 | Ratura | View | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
10. | 08-01-2019 | Ratura | Rear and left side elevation | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
11. | 08-01-2019 | Ratura | Rear elevation at night | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
12. | 08-01-2019 | Ratura | Front view | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
13. | 08-01-2019 | Ratura | Corner view at night | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
14. | 08-01-2019 | Ratura | Right side elevation at night | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
15. | 08-01-2019 | Ratura | Rear elevation | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
16. | 08-01-2019 | Ratura | Left side Elevation | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
17. | 08-01-2019 | Ratura | Right Side Elevation | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
18. | 08-01-2019 | Ratura | Front elevation | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
19. | 08-01-2019 | Ratura | Site view from far. | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
20. | 08-01-2019 | Ratura | Roof treatment (Brick coba), work in progress | Himanshu Sharma | JE | UDRP-H Rudraprayag | See Pic |
|
|