Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Fire Station Ratura Work Completed
Project: UDRP-H UID: 7321 Sanction Cost: 535.00  lakh Length: 0.000 KM.
District: Rudraprayag Block: 0017 Constituency: 7 Circle:
DEA: DEA PB DSC: SOWil Limited DSC Scope: Design and Supervision Type: H1
Procurement:
Package No.: 2265        Package Name:  15/BC/PIU/USIDCL/PB/2015-16        Tender Date: 29-01-2016        Current Status: Agreement signed        Achieved on Date: 28-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: 15/BC/PIU/USIDCL/PB/2015-16      Contractor Name: Makin Developers Pvt. Ltd.
Start Date:  01-04-2016      Intended Completion Date:  25-06-2018      Original End Date:  01-07-2017
Total Bond Cost: 59740626 (597.41 lakh)        Variation Cost: 3717002.49 (37.17 lakh)    Hence Total Bond Cost is   63457628.49 (634.58 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 2031160 for 68 days        LD Analysis for Milestone2: calculated LD is Rs 836360 for 28 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development21.55 Job136.7501-04-201608-06-201821.55 Job21.55 Job21.55136.75
2.Foundation and Plinth Work17.03 Job108.0715-04-201630-06-201717.03 Job17.03 Job17.03108.07
3.Structural Frame34.76 Job220.5801-07-201605-06-201834.76 Job34.76 Job34.76220.58
4.Doors & Windows 7.61 Job48.2915-12-201610-06-20187.61 Job7.61 Job7.6148.29
5.Water Supply and Sanitary work 1.36 Job8.6315-01-201722-06-20181.36 Job1.36 Job1.368.63
6.Electrification Works5.58 Job35.4101-09-201620-06-20185.58 Job5.58 Job5.5835.41
7.Other Allied Works & Finishing Work 12.10 Job76.8515-04-201625-06-201812.10 Job12.10 Job12.1176.85
Total Amount: 634.58 100   634.58
Remarks: No Remarks       Work Program Made On: 06-05-2016        Updation of work program on: 10-07-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-October-201624.70  lakh
2.20-December-201618.49  lakh
3.20-February-201747.93  lakh
4.27-February-201719.63  lakh
5.31-March-201734.44  lakh
6.21-June-201746.89  lakh
7.12-October-201791.60  lakh
8.25-January-201884.18  lakh
9.26-May-201898.14  lakh
10.21-August-201871.49  lakh
11.30-March-201997.07  lakh
Total 634.56  lakh
% Payment 100 %
Advance Amount:  11.68  lakh        Recovered Amount:  11.68  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 172   No. of Test Done : 204    No. of Test Passed : 189   No. of Test Failed : 15   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.00
Number of Notice(s) issued: 58

Mobile Pic Upload

Number of Pics Available on Web Repository: 257
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-02-2019RaturaBadminton courtHimanshu SharmaJEUDRP-H Rudraprayag See Pic
2.23-02-2019RaturaRear viewHimanshu SharmaJEUDRP-H Rudraprayag See Pic
3.23-02-2019RaturaViewHimanshu SharmaJEUDRP-H Rudraprayag See Pic
4.23-02-2019RaturaSite ViewHimanshu SharmaJEUDRP-H Rudraprayag See Pic
5.08-01-2019RaturaSite view, work in progressHimanshu SharmaJEUDRP-H Rudraprayag See Pic
6.08-01-2019Ratura3 D Rear viewHimanshu SharmaJEUDRP-H Rudraprayag See Pic
7.08-01-2019RaturaDeparture of CISF Expedition teamHimanshu SharmaJEUDRP-H Rudraprayag See Pic
8.08-01-2019RaturaCISF Expedition team halt at buildingHimanshu SharmaJEUDRP-H Rudraprayag See Pic
9.08-01-2019RaturaViewHimanshu SharmaJEUDRP-H Rudraprayag See Pic
10.08-01-2019RaturaRear and left side elevationHimanshu SharmaJEUDRP-H Rudraprayag See Pic
11.08-01-2019RaturaRear elevation at nightHimanshu SharmaJEUDRP-H Rudraprayag See Pic
12.08-01-2019RaturaFront viewHimanshu SharmaJEUDRP-H Rudraprayag See Pic
13.08-01-2019RaturaCorner view at nightHimanshu SharmaJEUDRP-H Rudraprayag See Pic
14.08-01-2019RaturaRight side elevation at nightHimanshu SharmaJEUDRP-H Rudraprayag See Pic
15.08-01-2019RaturaRear elevationHimanshu SharmaJEUDRP-H Rudraprayag See Pic
16.08-01-2019RaturaLeft side ElevationHimanshu SharmaJEUDRP-H Rudraprayag See Pic
17.08-01-2019RaturaRight Side ElevationHimanshu SharmaJEUDRP-H Rudraprayag See Pic
18.08-01-2019RaturaFront elevationHimanshu SharmaJEUDRP-H Rudraprayag See Pic
19.08-01-2019RaturaSite view from far.Himanshu SharmaJEUDRP-H Rudraprayag See Pic
20.08-01-2019RaturaRoof treatment (Brick coba), work in progressHimanshu SharmaJEUDRP-H Rudraprayag See Pic