Community center, Primary School, Aaganbadi , ANM center at village-kuwari
Work Completed
|
Project: |
UDRP-H |
UID: |
7317 |
Sanction Cost: |
428.00 lakh |
Length:
|
0.000 KM. |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
|
DEA: |
DEA PB |
DSC: |
|
DSC Scope: |
Design and Supervision |
Type: |
Primary School |
|
Procurement: |
Package No.: 2266
Package Name: 
16/BC/PIU/USIDCL/PB/2015-16
Tender Date: 05-02-2016
Current Status: Agreement signed
Achieved on Date: 09-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 16/BC/PIU/USIDCL/PB/2015-16
Contractor Name: M. S. Associates
|
Start Date: 12-04-2016
Intended Completion Date: 04-06-2018
Original End Date: 11-07-2017 |
Total Bond Cost: 40086315 (400.86 lakh)
Variation Cost: -2820435.61 (-28.2 lakh) Hence Total Bond Cost is 37265879.39 (372.66 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 3066579 for +153 days
LD Analysis for Milestone2: calculated LD is Rs 4830363 for 241 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 35.46 Job | 132.14 | 12-04-2016 | 15-05-2018 | 35.46 Job | 35.46 Job | 35.46 | 132.14 | 2. | Foundation and Plinth Work | 23.51 Job | 87.65 | 01-05-2016 | 31-03-2017 | 23.51 Job | 23.51 Job | 23.52 | 87.65 | 3. | Structural Frame | 7.84 Job | 29.22 | 01-07-2016 | 25-02-2018 | 7.84 Job | 7.84 Job | 7.84 | 29.22 | 4. | Doors & Windows | 18.24 Job | 67.97 | 15-11-2016 | 30-04-2018 | 18.24 Job | 18.24 Job | 18.24 | 67.97 | 5. | Water Supply and Sanitary work | 4.78 Job | 17.81 | 12-04-2016 | 16-05-2018 | 4.78 Job | 4.78 Job | 4.78 | 17.81 | 6. | Electrification Works | 2.88 Job | 10.73 | 15-11-2016 | 22-05-2018 | 2.88 Job | 2.88 Job | 2.88 | 10.73 | 7. | Other Allied Works & Finishing Work | 7.28 Job | 27.13 | 30-04-2016 | 15-05-2018 | 7.28 Job | 7.28 Job | 7.28 | 27.13 |
Total Amount: |
372.65 |
|
100 |
372.65 |
|
Remarks:
No Remarks
Work Program Made On:
12-05-2016 } ?>
Updation of work program on:
11-07-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-September-2016 | 58.30 lakh | 2. | 20-December-2016 | 50.12 lakh | 3. | 24-January-2017 | 15.83 lakh | 4. | 25-February-2017 | 30.41 lakh | 5. | 31-March-2017 | 40.08 lakh | 6. | 25-May-2017 | 7.71 lakh | 7. | 21-June-2017 | 10.57 lakh | 8. | 29-September-2017 | 25.42 lakh | 9. | 25-January-2018 | 65.06 lakh | 10. | 28-March-2018 | 31.89 lakh | 11. | 25-July-2018 | 19.28 lakh | 12. | 29-September-2018 | 16.94 lakh |
Total |
371.61 lakh |
% Payment |
99.73 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 107 No. of Test Done : 107 No. of Test Passed : 107 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.33 |
Number of Notice(s) issued: 48 |
Mobile Pic Upload |
No Pics Available on Web Repository |
( last 20 Pics) |
No Pic uploaded. |
|