Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Primary School Kaviltha (Kalimath) Work Completed
Project: UDRP-H UID: 7316 Sanction Cost: 71.97  lakh Length: 0.000 KM.
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA PB DSC: SOWil Limited DSC Scope: Design and Supervision Type: Primary School
Procurement:
Package No.: 2254        Package Name:  04/BC/PIU/USIDCL/PB/2015-16        Tender Date: 20-07-2015        Current Status: Agreement signed        Achieved on Date: 30-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: 04/BC/PIU/USIDCL/PB/2015-16      Contractor Name: Alok Infrabuilders (P) Ltd.
Start Date:  02-11-2015      Intended Completion Date:  15-12-2017      Original End Date:  01-02-2017
Total Bond Cost: 50455343 (504.55 lakh)        Variation Cost: -76475.58 (-0.76 lakh)    Hence Total Bond Cost is   50378867.42 (503.79 lakh) 
Sub Project Cost: 73.27  lakh        Variation Cost of Sub Project: -672821.18  (-6.73 lakh)       Total Sub Project Cost:   66.54 lakh
LD Analysis for Milestone1: calculated LD is Rs 3557148 for 141 days        LD Analysis for Milestone2: calculated LD is Rs 6155632 for 244 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development21.82 Job14.5202-11-201520-09-201721.82 Job21.82 Job21.8214.52
2.Foundation and Plinth Work25.59 Job17.0301-12-201531-05-201625.59 Job25.59 Job25.5917.03
3.Structural Frame31.00 Job20.6301-06-201602-03-201731.00 Job31.00 Job3120.63
4.Doors & Windows 7.74 Job5.1501-08-201630-04-20177.74 Job7.74 Job7.745.15
5.Electrification Works2.27 Job1.5101-07-201616-05-20172.27 Job2.27 Job2.271.51
6.Other Allied Works & Finishing Work 11.58 Job7.7101-01-201620-09-201711.58 Job11.58 Job11.587.71
Total Amount: 66.55 100   66.55
Remarks: No Remarks       Work Program Made On: 27-01-2016        Updation of work program on: 10-07-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.10-March-201615.11  lakh
2.31-March-20166.64  lakh
3.29-June-20162.26  lakh
4.11-August-20162.31  lakh
5.20-September-20160.41  lakh
6.27-October-20160.66  lakh
7.20-December-201612.63  lakh
8.24-January-20175.26  lakh
9.27-February-20171.99  lakh
10.25-March-20174.19  lakh
11.25-May-20173.21  lakh
12.21-June-20172.09  lakh
13.30-June-20171.00  lakh
14.16-September-20171.34  lakh
15.25-January-20180.65  lakh
16.29-September-20186.79  lakh
Total 66.54  lakh
% Payment100 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 162   No. of Test Done : 162    No. of Test Passed : 162   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.67
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 55
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-01-2018KavilthaBuilding viewVajid AliREUDRP-H Rudraprayag See Pic
2.29-11-2017P.S.KavilthaToilet tile worksMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
3.19-07-2017P.S.KavilthaP.S.Kaviltha plantationMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
4.16-07-2017KavilthaJhuaVajid AliREUDRP-H Rudraprayag See Pic
5.16-07-2017KavilthaJhuaVajid AliREUDRP-H Rudraprayag See Pic
6.16-07-2017KavilthaFislan pattiVajid AliREUDRP-H Rudraprayag See Pic
7.16-07-2017KavilthaPathwayVajid AliREUDRP-H Rudraprayag See Pic
8.16-07-2017KavilthaSite viewVajid AliREUDRP-H Rudraprayag See Pic
9.16-07-2017KavithaRoad RailingVajid AliREUDRP-H Rudraprayag See Pic
10.14-07-2017P.S. KavilthaPhislan pattiMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
11.14-07-2017P.S. KavilthaJhullaMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
12.23-05-2017P.S.KavilthaSite viewMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
13.21-05-2017KavilthaBala drawingVajid AliREUDRP-H Rudraprayag See Pic
14.21-05-2017KavilthaBala drawingVajid AliREUDRP-H Rudraprayag See Pic
15.21-05-2017KavilthaSite viewVajid AliREUDRP-H Rudraprayag See Pic
16.21-05-2017KavilthaBoundary wallVajid AliREUDRP-H Rudraprayag See Pic
17.21-05-2017KavilthaBuildingVajid AliREUDRP-H Rudraprayag See Pic
18.18-05-2017Govt. Inter college parkandiChemistry lab tiles workMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
19.13-05-2017P.s. kavilthaBala drawingMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
20.13-05-2017P.s.KavilthaSite viewMukesh Singh BishtJEUDRP-H Rudraprayag See Pic