Primary School panjana (Barsir)
Work Completed
|
Project: |
UDRP-H |
UID: |
7315 |
Sanction Cost: |
57.37 lakh |
Length:
|
0.000 KM. |
District: |
Rudraprayag |
Block: |
Jakholi |
Constituency: |
Rudraprayag |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
Type: |
Primary School |
|
Procurement: |
Package No.: 2253
Package Name: 
03/BC/PIU/USIDCL/PB/2015-16
Tender Date: 20-07-2015
Current Status: Agreement signed
Achieved on Date: 30-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 03/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Girish Chandra Nautiyal
|
Start Date: 02-11-2015
Intended Completion Date: 26-06-2017
|
Total Bond Cost: 12522032 (125.22 lakh)
Variation Cost: -1087008.84 (-10.87 lakh) Hence Total Bond Cost is 11435023.16 (114.35 lakh)
|
Sub Project Cost: 55.65 lakh
Variation Cost of Sub Project: -12154.42 (-0.12 lakh)
Total Sub Project Cost:
55.53 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 757581 for +121 days
LD Analysis for Milestone2: calculated LD is Rs 1771863 for 283 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 13.24 Job | 7.35 | 02-11-2015 | 26-06-2017 | 13.24 Job | 13.24 Job | 13.24 | 7.35 | 2. | Foundation and Plinth Work | 18.99 Job | 10.55 | 16-11-2015 | 29-02-2016 | 18.99 Job | 18.99 Job | 18.99 | 10.55 | 3. | Structural Frame | 34.90 Job | 19.38 | 01-03-2016 | 26-06-2017 | 34.90 Job | 34.90 Job | 34.9 | 19.38 | 4. | Doors & Windows | 4.34 Job | 2.41 | 01-06-2016 | 26-06-2017 | 4.34 Job | 4.34 Job | 4.34 | 2.41 | 5. | Water Supply and Sanitary work | 1.59 Job | 0.88 | 15-07-2016 | 26-06-2017 | 1.59 Job | 1.59 Job | 1.59 | 0.88 | 6. | Electrification Works | 2.87 Job | 1.59 | 16-05-2016 | 26-06-2017 | 2.87 Job | 2.87 Job | 2.87 | 1.59 | 7. | Other Allied Works & Finishing Work | 24.06 Job | 13.37 | 16-11-2015 | 26-06-2017 | 24.06 Job | 24.06 Job | 24.07 | 13.37 |
Total Amount: |
55.53 |
|
100 |
55.53 |
|
Remarks:
No Remarks
Work Program Made On:
01-02-2016 } ?>
Updation of work program on:
10-07-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-March-2016 | 10.64 lakh | 2. | 31-March-2016 | 8.04 lakh | 3. | 20-September-2016 | 1.29 lakh | 4. | 30-September-2016 | 2.99 lakh | 5. | 27-October-2016 | 0.88 lakh | 6. | 20-December-2016 | 5.90 lakh | 7. | 24-January-2017 | 5.22 lakh | 8. | 27-February-2017 | 2.83 lakh | 9. | 31-March-2017 | 3.59 lakh | 10. | 25-May-2017 | 2.03 lakh | 11. | 25-January-2018 | 12.12 lakh |
Total |
55.53 lakh |
% Payment | 100 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 68 No. of Test Done : 68 No. of Test Passed : 68 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 93.46 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 26 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-07-2017 | Primary School Panjana(Basir) | Tree Plantation | Atul Juyal | JE | UDRP-H Rudraprayag | See Pic |
2. | 19-07-2017 | Panajan | Building view | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
3. | 05-05-2017 | Panajan | Main gate | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
4. | 05-05-2017 | Panjana | Building | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
5. | 05-05-2017 | Panajan | Interlocking Tiles work | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
6. | 07-03-2017 | Panjana | Building | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
7. | 01-03-2017 | Panjana | Boundary wall | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
8. | 01-03-2017 | Panjana | Boundary wall | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
9. | 09-01-2017 | Panjana | kitchen counter | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
10. | 09-01-2017 | Panjana | Building | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
11. | 20-11-2016 | Timli | World Bank Team visit at site | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
12. | 20-11-2016 | Timli | World Bank Team visit at site | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
13. | 23-09-2016 | Panjana | Plaster work | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
14. | 13-07-2016 | Panjana | AAC Block work | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
15. | 13-07-2016 | Panjana | Site | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
16. | 13-07-2016 | P.S. Panjana | AAC block masonry | Atul Juyal | JE | UDRP-H Rudraprayag | See Pic |
17. | 08-07-2016 | Panjana | AAC Block Masonry | Atul Juyal | JE | UDRP-H Rudraprayag | See Pic |
18. | 21-05-2016 | Panjana | Ceiling plaster | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
19. | 21-05-2016 | Panjana | Ceiling plaster | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
20. | 16-05-2016 | Primary School Panjana | Ceiling Plaster Work | Atul Juyal | JE | UDRP-H Rudraprayag | See Pic |
|
|