Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Primary School panjana (Barsir) Work Completed
Project: UDRP-H UID: 7315 Sanction Cost: 57.37  lakh Length: 0.000 KM.
District: Rudraprayag Block: Jakholi Constituency: Rudraprayag Circle:
DEA: DEA PB DSC: SOWil Limited DSC Scope: Design and Supervision Type: Primary School
Procurement:
Package No.: 2253        Package Name:  03/BC/PIU/USIDCL/PB/2015-16        Tender Date: 20-07-2015        Current Status: Agreement signed        Achieved on Date: 30-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: 03/BC/PIU/USIDCL/PB/2015-16      Contractor Name: Girish Chandra Nautiyal
Start Date:  02-11-2015      Intended Completion Date:  26-06-2017     
Total Bond Cost: 12522032 (125.22 lakh)        Variation Cost: -1087008.84 (-10.87 lakh)    Hence Total Bond Cost is   11435023.16 (114.35 lakh) 
Sub Project Cost: 55.65  lakh        Variation Cost of Sub Project: -12154.42  (-0.12 lakh)       Total Sub Project Cost:   55.53 lakh
LD Analysis for Milestone1: calculated LD is Rs 757581 for +121 days        LD Analysis for Milestone2: calculated LD is Rs 1771863 for 283 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development13.24 Job7.3502-11-201526-06-201713.24 Job13.24 Job13.247.35
2.Foundation and Plinth Work18.99 Job10.5516-11-201529-02-201618.99 Job18.99 Job18.9910.55
3.Structural Frame34.90 Job19.3801-03-201626-06-201734.90 Job34.90 Job34.919.38
4.Doors & Windows 4.34 Job2.4101-06-201626-06-20174.34 Job4.34 Job4.342.41
5.Water Supply and Sanitary work 1.59 Job0.8815-07-201626-06-20171.59 Job1.59 Job1.590.88
6.Electrification Works2.87 Job1.5916-05-201626-06-20172.87 Job2.87 Job2.871.59
7.Other Allied Works & Finishing Work 24.06 Job13.3716-11-201526-06-201724.06 Job24.06 Job24.0713.37
Total Amount: 55.53 100   55.53
Remarks: No Remarks       Work Program Made On: 01-02-2016        Updation of work program on: 10-07-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-March-201610.64  lakh
2.31-March-20168.04  lakh
3.20-September-20161.29  lakh
4.30-September-20162.99  lakh
5.27-October-20160.88  lakh
6.20-December-20165.90  lakh
7.24-January-20175.22  lakh
8.27-February-20172.83  lakh
9.31-March-20173.59  lakh
10.25-May-20172.03  lakh
11.25-January-201812.12  lakh
Total 55.53  lakh
% Payment100 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 68   No. of Test Done : 68    No. of Test Passed : 68   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.46
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 26
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-07-2017Primary School Panjana(Basir)Tree PlantationAtul JuyalJEUDRP-H Rudraprayag See Pic
2.19-07-2017PanajanBuilding viewVajid AliREUDRP-H Rudraprayag See Pic
3.05-05-2017PanajanMain gateVajid AliREUDRP-H Rudraprayag See Pic
4.05-05-2017PanjanaBuildingVajid AliREUDRP-H Rudraprayag See Pic
5.05-05-2017PanajanInterlocking Tiles workVajid AliREUDRP-H Rudraprayag See Pic
6.07-03-2017PanjanaBuildingVajid AliREUDRP-H Rudraprayag See Pic
7.01-03-2017PanjanaBoundary wallVajid AliREUDRP-H Rudraprayag See Pic
8.01-03-2017PanjanaBoundary wallVajid AliREUDRP-H Rudraprayag See Pic
9.09-01-2017Panjanakitchen counterVajid AliREUDRP-H Rudraprayag See Pic
10.09-01-2017PanjanaBuildingVajid AliREUDRP-H Rudraprayag See Pic
11.20-11-2016TimliWorld Bank Team visit at siteVajid AliREUDRP-H Rudraprayag See Pic
12.20-11-2016TimliWorld Bank Team visit at siteVajid AliREUDRP-H Rudraprayag See Pic
13.23-09-2016PanjanaPlaster workVajid AliREUDRP-H Rudraprayag See Pic
14.13-07-2016PanjanaAAC Block workVajid AliREUDRP-H Rudraprayag See Pic
15.13-07-2016PanjanaSiteVajid AliREUDRP-H Rudraprayag See Pic
16.13-07-2016P.S. PanjanaAAC block masonryAtul JuyalJEUDRP-H Rudraprayag See Pic
17.08-07-2016PanjanaAAC Block MasonryAtul JuyalJEUDRP-H Rudraprayag See Pic
18.21-05-2016PanjanaCeiling plasterVajid AliREUDRP-H Rudraprayag See Pic
19.21-05-2016PanjanaCeiling plasterVajid AliREUDRP-H Rudraprayag See Pic
20.16-05-2016Primary School PanjanaCeiling Plaster WorkAtul JuyalJEUDRP-H Rudraprayag See Pic