Primary School Timili Badma (kailash Nagar)
Work Completed
|
Project: |
UDRP-H |
UID: |
7314 |
Sanction Cost: |
71.67 lakh |
Length:
|
0.000 KM. |
District: |
Rudraprayag |
Block: |
Jakholi |
Constituency: |
Rudraprayag |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
Type: |
Primary School |
|
Procurement: |
Package No.: 2253
Package Name: 
03/BC/PIU/USIDCL/PB/2015-16
Tender Date: 20-07-2015
Current Status: Agreement signed
Achieved on Date: 30-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 03/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Girish Chandra Nautiyal
|
Start Date: 02-11-2015
Intended Completion Date: 26-06-2017
|
Total Bond Cost: 12522032 (125.22 lakh)
Variation Cost: -1087008.84 (-10.87 lakh) Hence Total Bond Cost is 11435023.16 (114.35 lakh)
|
Sub Project Cost: 69.56 lakh
Variation Cost of Sub Project: -1074854.42 (-10.75 lakh)
Total Sub Project Cost:
58.81 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 757581 for +121 days
LD Analysis for Milestone2: calculated LD is Rs 1771863 for 283 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 19.26 Job | 11.33 | 02-11-2015 | 26-06-2017 | 19.26 Job | 19.26 Job | 19.26 | 11.33 | 2. | Foundation and Plinth Work | 20.29 Job | 11.93 | 15-11-2015 | 29-02-2016 | 20.29 Job | 20.29 Job | 20.29 | 11.93 | 3. | Structural Frame | 31.84 Job | 18.73 | 01-03-2016 | 26-06-2017 | 31.84 Job | 31.84 Job | 31.84 | 18.73 | 4. | Doors & Windows | 8.58 Job | 5.05 | 01-06-2016 | 26-06-2017 | 8.58 Job | 8.58 Job | 8.58 | 5.05 | 5. | Electrification Works | 2.50 Job | 1.47 | 16-05-2016 | 26-06-2017 | 2.50 Job | 2.50 Job | 2.5 | 1.47 | 6. | Other Allied Works & Finishing Work | 17.52 Job | 10.31 | 16-11-2015 | 26-06-2017 | 17.52 Job | 17.52 Job | 17.53 | 10.31 |
Total Amount: |
58.82 |
|
100 |
58.82 |
|
Remarks:
No Remarks
Work Program Made On:
01-02-2016 } ?>
Updation of work program on:
10-07-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-March-2016 | 5.96 lakh | 2. | 31-March-2016 | 6.43 lakh | 3. | 20-September-2016 | 7.54 lakh | 4. | 30-September-2016 | 4.53 lakh | 5. | 27-October-2016 | 5.03 lakh | 6. | 20-December-2016 | 5.47 lakh | 7. | 24-January-2017 | 2.87 lakh | 8. | 27-February-2017 | 1.21 lakh | 9. | 31-March-2017 | 2.76 lakh | 10. | 25-May-2017 | 3.74 lakh | 11. | 25-January-2018 | 13.27 lakh |
Total |
58.81 lakh |
% Payment | 100 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 68 No. of Test Done : 68 No. of Test Passed : 68 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 93.49 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 37 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-07-2017 | Primary School Timli (Badma) | Tree Plantation | Atul Juyal | JE | UDRP-H Rudraprayag | See Pic |
2. | 19-07-2017 | Primary School Timli(Badma) | Tree Plantation | Atul Juyal | JE | UDRP-H Rudraprayag | See Pic |
3. | 19-07-2017 | Timli-Badma | Site view | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
4. | 05-05-2017 | Timli-Badma | Interlocking Tiles work | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
5. | 05-05-2017 | Timli-Badma | B/wall railing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
6. | 09-03-2017 | Timli Badma | Bala drawing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
7. | 09-03-2017 | Timli Badma | Bala drawing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
8. | 08-03-2017 | Timli Badma | Bala drawing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
9. | 07-03-2017 | Timli Badma | Bala drawing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
10. | 07-03-2017 | Timli Badma | Bala drawing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
11. | 05-03-2017 | Timli Badma | Bala drawing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
12. | 05-03-2017 | Timli Badma | Bala drawing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
13. | 04-03-2017 | Timli Badma | Bala drawing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
14. | 04-03-2017 | Timli Badma | Bala Drawing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
15. | 02-03-2017 | Timli Badma | Bala drawing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
16. | 02-03-2017 | Timli Badma | Bala Drawing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
17. | 09-01-2017 | Timli-Badma | Building | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
18. | 20-11-2016 | Panjana | World Bank Team visit at site | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
19. | 20-11-2016 | Panjana | World Bank Team visit at site | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
20. | 20-11-2016 | Timli-Badma | Putty work | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
|
|