Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Primary School Timili Badma (kailash Nagar) Work Completed
Project: UDRP-H UID: 7314 Sanction Cost: 71.67  lakh Length: 0.000 KM.
District: Rudraprayag Block: Jakholi Constituency: Rudraprayag Circle:
DEA: DEA PB DSC: SOWil Limited DSC Scope: Design and Supervision Type: Primary School
Procurement:
Package No.: 2253        Package Name:  03/BC/PIU/USIDCL/PB/2015-16        Tender Date: 20-07-2015        Current Status: Agreement signed        Achieved on Date: 30-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: 03/BC/PIU/USIDCL/PB/2015-16      Contractor Name: Girish Chandra Nautiyal
Start Date:  02-11-2015      Intended Completion Date:  26-06-2017     
Total Bond Cost: 12522032 (125.22 lakh)        Variation Cost: -1087008.84 (-10.87 lakh)    Hence Total Bond Cost is   11435023.16 (114.35 lakh) 
Sub Project Cost: 69.56  lakh        Variation Cost of Sub Project: -1074854.42  (-10.75 lakh)       Total Sub Project Cost:   58.81 lakh
LD Analysis for Milestone1: calculated LD is Rs 757581 for +121 days        LD Analysis for Milestone2: calculated LD is Rs 1771863 for 283 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development19.26 Job11.3302-11-201526-06-201719.26 Job19.26 Job19.2611.33
2.Foundation and Plinth Work20.29 Job11.9315-11-201529-02-201620.29 Job20.29 Job20.2911.93
3.Structural Frame31.84 Job18.7301-03-201626-06-201731.84 Job31.84 Job31.8418.73
4.Doors & Windows 8.58 Job5.0501-06-201626-06-20178.58 Job8.58 Job8.585.05
5.Electrification Works2.50 Job1.4716-05-201626-06-20172.50 Job2.50 Job2.51.47
6.Other Allied Works & Finishing Work 17.52 Job10.3116-11-201526-06-201717.52 Job17.52 Job17.5310.31
Total Amount: 58.82 100   58.82
Remarks: No Remarks       Work Program Made On: 01-02-2016        Updation of work program on: 10-07-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-March-20165.96  lakh
2.31-March-20166.43  lakh
3.20-September-20167.54  lakh
4.30-September-20164.53  lakh
5.27-October-20165.03  lakh
6.20-December-20165.47  lakh
7.24-January-20172.87  lakh
8.27-February-20171.21  lakh
9.31-March-20172.76  lakh
10.25-May-20173.74  lakh
11.25-January-201813.27  lakh
Total 58.81  lakh
% Payment100 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 68   No. of Test Done : 68    No. of Test Passed : 68   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.49
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 37
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-07-2017Primary School Timli (Badma)Tree PlantationAtul JuyalJEUDRP-H Rudraprayag See Pic
2.19-07-2017Primary School Timli(Badma)Tree PlantationAtul JuyalJEUDRP-H Rudraprayag See Pic
3.19-07-2017Timli-BadmaSite viewVajid AliREUDRP-H Rudraprayag See Pic
4.05-05-2017Timli-BadmaInterlocking Tiles workVajid AliREUDRP-H Rudraprayag See Pic
5.05-05-2017Timli-BadmaB/wall railingVajid AliREUDRP-H Rudraprayag See Pic
6.09-03-2017Timli BadmaBala drawingVajid AliREUDRP-H Rudraprayag See Pic
7.09-03-2017Timli BadmaBala drawingVajid AliREUDRP-H Rudraprayag See Pic
8.08-03-2017Timli BadmaBala drawingVajid AliREUDRP-H Rudraprayag See Pic
9.07-03-2017Timli BadmaBala drawingVajid AliREUDRP-H Rudraprayag See Pic
10.07-03-2017Timli BadmaBala drawingVajid AliREUDRP-H Rudraprayag See Pic
11.05-03-2017Timli BadmaBala drawingVajid AliREUDRP-H Rudraprayag See Pic
12.05-03-2017Timli BadmaBala drawingVajid AliREUDRP-H Rudraprayag See Pic
13.04-03-2017Timli BadmaBala drawingVajid AliREUDRP-H Rudraprayag See Pic
14.04-03-2017Timli BadmaBala DrawingVajid AliREUDRP-H Rudraprayag See Pic
15.02-03-2017Timli BadmaBala drawingVajid AliREUDRP-H Rudraprayag See Pic
16.02-03-2017Timli BadmaBala DrawingVajid AliREUDRP-H Rudraprayag See Pic
17.09-01-2017Timli-BadmaBuildingVajid AliREUDRP-H Rudraprayag See Pic
18.20-11-2016PanjanaWorld Bank Team visit at siteVajid AliREUDRP-H Rudraprayag See Pic
19.20-11-2016PanjanaWorld Bank Team visit at siteVajid AliREUDRP-H Rudraprayag See Pic
20.20-11-2016Timli-BadmaPutty workVajid AliREUDRP-H Rudraprayag See Pic