Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Primary School Kot Talla (Nagrashu) Work Completed
Project: UDRP-H UID: 7313 Sanction Cost: 69.14  lakh Length: 0.000 KM.
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle:
DEA: DEA PB DSC: SOWil Limited DSC Scope: Design and Supervision Type: Primary School
Procurement:
Package No.: 2252        Package Name:  02/BC/PIU/USIDCL/PB/2015-16        Tender Date: 20-07-2015        Current Status: Agreement signed        Achieved on Date: 30-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: 02/BC/PIU/USIDCL/PB/2015-16      Contractor Name: Girish Chandra Nautiyal
Start Date:  02-11-2015      Intended Completion Date:  22-07-2017     
Total Bond Cost: 13383481 (133.83 lakh)        Variation Cost: -2062189.95 (-20.62 lakh)    Hence Total Bond Cost is   11321291.05 (113.21 lakh) 
Sub Project Cost: 66.87  lakh        Variation Cost of Sub Project: -1334494.18  (-13.34 lakh)       Total Sub Project Cost:   53.53 lakh
LD Analysis for Milestone1: calculated LD is Rs 809732 for +121 days        LD Analysis for Milestone2: calculated LD is Rs 2348892 for 351 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development14.27 Job9.7702-11-201522-07-201714.27 Job14.27 Job14.279.77
2.Foundation and Plinth Work21.91 Job15.0015-11-201529-02-201621.91 Job21.91 Job21.9115.00
3.Structural Frame33.77 Job23.1201-03-201622-07-201733.77 Job33.77 Job33.7723.12
4.Doors & Windows 7.79 Job5.3301-06-201622-07-20177.79 Job7.79 Job7.795.33
5.Electrification Works2.64 Job1.8115-05-201622-07-20172.64 Job2.64 Job2.641.81
6.Other Allied Works & Finishing Work 19.63 Job13.4415-11-201522-07-201719.63 Job19.63 Job19.6313.44
Total Amount: 68.47 100   68.47
Remarks: Task finished       Work Program Made On: 02-02-2016        Updation of work program on: 29-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.16-May-20168.72  lakh
2.30-June-20168.60  lakh
3.27-October-20163.90  lakh
4.20-December-20162.14  lakh
5.24-January-20175.55  lakh
6.27-February-20173.52  lakh
7.31-March-20173.09  lakh
8.25-May-20171.75  lakh
9.30-June-20174.67  lakh
10.29-September-20175.41  lakh
11.16-February-20186.16  lakh
Total 53.51  lakh
% Payment99.96 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 123   No. of Test Done : 123    No. of Test Passed : 123   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.31
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 29
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.20-07-2017Primary school KottallaTree plantation work is in progressAnil Kumar REREUDRP PB See Pic
2.13-07-2017Primary School kottallaBuilding ElevationSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
3.27-06-2017Primary School kottallaBuilding ElevationSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
4.25-05-2017Primary School kottallaWORLD BANK TEAM VISITSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
5.23-05-2017KottalaTree Plantation by World Bank TeamVajid AliREUDRP-H Rudraprayag See Pic
6.23-05-2017KottalaWorld Bank Team site visitVajid AliREUDRP-H Rudraprayag See Pic
7.23-05-2017KottalaWorld Bank Team site visitVajid AliREUDRP-H Rudraprayag See Pic
8.23-05-2017P.s kottallaTree plantation by world Bank teamAnil Kumar REREUDRP PB See Pic
9.23-05-2017P.s kottallaWorld bank team site visitAnil Kumar REREUDRP PB See Pic
10.23-05-2017P.s kottallaWorld bank team site visitAnil Kumar REREUDRP PB See Pic
11.22-05-2017Primary School kottallaBuilding ElevationSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
12.21-05-2017P.s kottallaStair case railing work is in progressAnil Kumar REREUDRP PB See Pic
13.21-05-2017P.s kottallaDPM sir site visitAnil Kumar REREUDRP PB See Pic
14.07-05-2017Primary School kottallaDPM Sir site visit at construction siteSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
15.04-05-2017Primary School kottallaBoundary wall Bala workSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
16.04-05-2017Primary School kottallaBuilding Rear Side viewSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
17.04-05-2017Primary School kottallaBuilding Top viewSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
18.15-04-2017P.s kottallaBala work is in progressAnil Kumar REREUDRP PB See Pic
19.31-03-2017Primary School kottallaBoundary wallSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
20.31-03-2017Primary School kottallaTop viewSatyendra SaklaniJEUDRP-H Rudraprayag See Pic