Primary School Barsu (Rudrapryag)
Work Completed
|
Project: |
UDRP-H |
UID: |
7312 |
Sanction Cost: |
69.18 lakh |
Length:
|
0.000 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
Type: |
Primary School |
|
Procurement: |
Package No.: 2252
Package Name: 
02/BC/PIU/USIDCL/PB/2015-16
Tender Date: 20-07-2015
Current Status: Agreement signed
Achieved on Date: 30-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 02/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Girish Chandra Nautiyal
|
Start Date: 02-11-2015
Intended Completion Date: 22-07-2017
|
Total Bond Cost: 13383481 (133.83 lakh)
Variation Cost: -2062189.95 (-20.62 lakh) Hence Total Bond Cost is 11321291.05 (113.21 lakh)
|
Sub Project Cost: 66.96 lakh
Variation Cost of Sub Project: -727695.77 (-7.28 lakh)
Total Sub Project Cost:
59.68 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 809732 for +121 days
LD Analysis for Milestone2: calculated LD is Rs 2348892 for 351 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 22.93 Job | 15.56 | 02-11-2015 | 22-07-2017 | 22.93 Job | 22.93 Job | 22.93 | 15.56 | 2. | Foundation and Plinth Work | 22.66 Job | 15.38 | 15-11-2015 | 29-02-2016 | 22.66 Job | 22.66 Job | 22.66 | 15.38 | 3. | Structural Frame | 24.59 Job | 16.68 | 01-03-2016 | 22-07-2017 | 24.59 Job | 24.59 Job | 24.59 | 16.68 | 4. | Doors & Windows | 5.92 Job | 4.02 | 01-06-2016 | 22-07-2017 | 5.92 Job | 5.92 Job | 5.92 | 4.02 | 5. | Electrification Works | 2.67 Job | 1.81 | 15-05-2016 | 22-07-2017 | 2.67 Job | 2.67 Job | 2.67 | 1.81 | 6. | Other Allied Works & Finishing Work | 21.23 Job | 14.41 | 15-11-2015 | 28-05-2017 | 21.23 Job | 21.23 Job | 21.24 | 14.41 |
Total Amount: |
67.86 |
|
100 |
67.86 |
|
Remarks:
Task finished
Work Program Made On:
02-02-2016 } ?>
Updation of work program on:
29-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-May-2016 | 6.49 lakh | 2. | 30-June-2016 | 9.47 lakh | 3. | 27-October-2016 | 4.29 lakh | 4. | 20-December-2016 | 1.29 lakh | 5. | 24-January-2017 | 9.86 lakh | 6. | 27-February-2017 | 6.39 lakh | 7. | 31-March-2017 | 3.77 lakh | 8. | 25-May-2017 | 2.49 lakh | 9. | 30-June-2017 | 7.44 lakh | 10. | 29-September-2017 | 1.59 lakh | 11. | 16-February-2018 | 6.61 lakh |
Total |
59.69 lakh |
% Payment | 100.02 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 123 No. of Test Done : 123 No. of Test Passed : 123 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 64 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-05-2018 | Primary School Barsu | School Furniture Cartons | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
2. | 27-04-2018 | Primary School Barsu | Water storage cooler Purifier machine | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
3. | 26-01-2018 | P. S barsu | World Bank team site visit | Anil Kumar RE | RE | UDRP PB | See Pic |
4. | 17-08-2017 | Primary School Barsu | Jhula work | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
5. | 19-07-2017 | Primary school barsu | Tree plantation work | Anil Kumar RE | RE | UDRP PB | See Pic |
6. | 19-07-2017 | Primary School Barsu | Trees Plantation at Primary School Barsu | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
7. | 13-07-2017 | Primary School Barsu | BALA WORK | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
8. | 07-07-2017 | Primary School Barsu | Building Elevation | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
9. | 27-06-2017 | Primary School Barsu | MS wire Fencing work | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
10. | 27-06-2017 | Primary School Barsu | Building Elevation | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
11. | 22-05-2017 | P.s Barsu | World bank site visit | Anil Kumar RE | RE | UDRP PB | See Pic |
12. | 22-05-2017 | Primary School Barsu | World Bank Team site visit at Barsu | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
13. | 22-05-2017 | Barsu | World Bank Team site visit | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
14. | 22-05-2017 | Barsu | Main Gate | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
15. | 22-05-2017 | Primary School Barsu | Interlocking tile work | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
16. | 21-05-2017 | P.s barsu | Bala work on R.R wall is in progress | Anil Kumar RE | RE | UDRP PB | See Pic |
17. | 21-05-2017 | P.s Barsu | Chain link fencying work | Anil Kumar RE | RE | UDRP PB | See Pic |
18. | 21-05-2017 | Primary School Barsu | Interlocking tile work | Satyendra Saklani | JE | UDRP-H Rudraprayag | See Pic |
19. | 07-05-2017 | P.s barsu | Site development work is in progress | Anil Kumar RE | RE | UDRP PB | See Pic |
20. | 06-05-2017 | P.s barsu | DPM sir site visit | Anil Kumar RE | RE | UDRP PB | See Pic |
|
|