Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Primary School Barsu (Rudrapryag) Work Completed
Project: UDRP-H UID: 7312 Sanction Cost: 69.18  lakh Length: 0.000 KM.
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle:
DEA: DEA PB DSC: SOWil Limited DSC Scope: Design and Supervision Type: Primary School
Procurement:
Package No.: 2252        Package Name:  02/BC/PIU/USIDCL/PB/2015-16        Tender Date: 20-07-2015        Current Status: Agreement signed        Achieved on Date: 30-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: 02/BC/PIU/USIDCL/PB/2015-16      Contractor Name: Girish Chandra Nautiyal
Start Date:  02-11-2015      Intended Completion Date:  22-07-2017     
Total Bond Cost: 13383481 (133.83 lakh)        Variation Cost: -2062189.95 (-20.62 lakh)    Hence Total Bond Cost is   11321291.05 (113.21 lakh) 
Sub Project Cost: 66.96  lakh        Variation Cost of Sub Project: -727695.77  (-7.28 lakh)       Total Sub Project Cost:   59.68 lakh
LD Analysis for Milestone1: calculated LD is Rs 809732 for +121 days        LD Analysis for Milestone2: calculated LD is Rs 2348892 for 351 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development22.93 Job15.5602-11-201522-07-201722.93 Job22.93 Job22.9315.56
2.Foundation and Plinth Work22.66 Job15.3815-11-201529-02-201622.66 Job22.66 Job22.6615.38
3.Structural Frame24.59 Job16.6801-03-201622-07-201724.59 Job24.59 Job24.5916.68
4.Doors & Windows 5.92 Job4.0201-06-201622-07-20175.92 Job5.92 Job5.924.02
5.Electrification Works2.67 Job1.8115-05-201622-07-20172.67 Job2.67 Job2.671.81
6.Other Allied Works & Finishing Work 21.23 Job14.4115-11-201528-05-201721.23 Job21.23 Job21.2414.41
Total Amount: 67.86 100   67.86
Remarks: Task finished       Work Program Made On: 02-02-2016        Updation of work program on: 29-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.16-May-20166.49  lakh
2.30-June-20169.47  lakh
3.27-October-20164.29  lakh
4.20-December-20161.29  lakh
5.24-January-20179.86  lakh
6.27-February-20176.39  lakh
7.31-March-20173.77  lakh
8.25-May-20172.49  lakh
9.30-June-20177.44  lakh
10.29-September-20171.59  lakh
11.16-February-20186.61  lakh
Total 59.69  lakh
% Payment100.02 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 123   No. of Test Done : 123    No. of Test Passed : 123   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 64
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-05-2018Primary School BarsuSchool Furniture CartonsSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
2.27-04-2018Primary School BarsuWater storage cooler Purifier machineSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
3.26-01-2018P. S barsuWorld Bank team site visitAnil Kumar REREUDRP PB See Pic
4.17-08-2017Primary School BarsuJhula workSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
5.19-07-2017Primary school barsuTree plantation workAnil Kumar REREUDRP PB See Pic
6.19-07-2017Primary School BarsuTrees Plantation at Primary School BarsuSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
7.13-07-2017Primary School BarsuBALA WORKSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
8.07-07-2017Primary School BarsuBuilding ElevationSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
9.27-06-2017Primary School BarsuMS wire Fencing workSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
10.27-06-2017Primary School BarsuBuilding ElevationSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
11.22-05-2017P.s BarsuWorld bank site visitAnil Kumar REREUDRP PB See Pic
12.22-05-2017Primary School BarsuWorld Bank Team site visit at BarsuSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
13.22-05-2017BarsuWorld Bank Team site visitVajid AliREUDRP-H Rudraprayag See Pic
14.22-05-2017BarsuMain GateVajid AliREUDRP-H Rudraprayag See Pic
15.22-05-2017Primary School BarsuInterlocking tile workSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
16.21-05-2017P.s barsuBala work on R.R wall is in progressAnil Kumar REREUDRP PB See Pic
17.21-05-2017P.s BarsuChain link fencying workAnil Kumar REREUDRP PB See Pic
18.21-05-2017Primary School BarsuInterlocking tile workSatyendra SaklaniJEUDRP-H Rudraprayag See Pic
19.07-05-2017P.s barsuSite development work is in progressAnil Kumar REREUDRP PB See Pic
20.06-05-2017P.s barsuDPM sir site visitAnil Kumar REREUDRP PB See Pic