Primary School Chopta (Chopta)
Work Completed
|
Project: |
UDRP-H |
UID: |
7311 |
Sanction Cost: |
85.55 lakh |
Length:
|
0.000 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
Type: |
Primary School |
|
Procurement: |
Package No.: 2251
Package Name: 
01/BC/PIU/USIDCL/PB/2015-16
Tender Date: 04-09-2015
Current Status: Agreement signed
Achieved on Date: 15-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 01/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Chamoli Associates
|
Start Date: 10-09-2015
Intended Completion Date: 03-09-2017
|
Total Bond Cost: 17714717.24 (177.15 lakh)
Variation Cost: -1276369.24 (-12.76 lakh) Hence Total Bond Cost is 16438348 (164.38 lakh)
|
Sub Project Cost: 89.72 lakh
Variation Cost of Sub Project: -592700.42 (-5.93 lakh)
Total Sub Project Cost:
83.79 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2152251 for +243 days
LD Analysis for Milestone2: calculated LD is Rs 2550816 for 288 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 8.03 Job | 7.19 | 10-09-2015 | 30-08-2016 | 5.58 Job | 5.58 Job | 8.03 | 7.19 | 2. | Foundation and Plinth Work | 18.09 Job | 16.20 | 20-09-2015 | 30-08-2016 | 15.82 Job | 15.82 Job | 18.09 | 16.20 | 3. | Structural Frame | 36.72 Job | 32.89 | 01-01-2016 | 01-09-2017 | 36.72 Job | 36.72 Job | 36.72 | 32.89 | 4. | Doors & Windows | 2.62 Job | 2.34 | 01-04-2016 | 29-08-2017 | 2.62 Job | 2.62 Job | 2.62 | 2.34 | 5. | Water Supply and Sanitary work | 2.26 Job | 2.02 | 10-05-2016 | 30-08-2017 | 2.26 Job | 2.26 Job | 2.26 | 2.02 | 6. | Electrification Works | 1.58 Job | 1.42 | 15-05-2016 | 30-08-2017 | 1.58 Job | 1.58 Job | 1.58 | 1.42 | 7. | Other Allied Works & Finishing Work | 30.70 Job | 27.49 | 15-11-2015 | 30-08-2017 | 30.70 Job | 30.70 Job | 30.7 | 27.49 |
Total Amount: |
89.55 |
|
100 |
89.55 |
|
Remarks:
Task finished
Work Program Made On:
01-02-2016 } ?>
Updation of work program on:
22-08-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-May-2016 | 7.74 lakh | 2. | 30-June-2016 | 5.55 lakh | 3. | 22-September-2016 | 8.47 lakh | 4. | 27-October-2016 | 5.26 lakh | 5. | 29-December-2016 | 3.39 lakh | 6. | 24-January-2017 | 4.80 lakh | 7. | 27-February-2017 | 4.99 lakh | 8. | 25-March-2017 | 2.16 lakh | 9. | 21-June-2017 | 4.87 lakh | 10. | 30-August-2017 | 7.70 lakh | 11. | 24-March-2018 | 28.86 lakh |
Total |
83.79 lakh |
% Payment | 100 % |
|
Advance Amount: 8.86 lakh
Recovered Amount: 8.86 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 193 No. of Test Done : 193 No. of Test Passed : 193 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 69 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-02-2020 | Birahi | Ch. 204 to 214 3rd lift superstructure M15 grade concrete in progress | Rohit Yadav | QC | DSC WB Irrigation Chamoli | See Pic |
2. | 02-02-2018 | P. S chopta | Checking white washing and other work | Anil Kumar RE | RE | UDRP PB | See Pic |
3. | 25-10-2017 | Primary School Chopta | Boundary wall work and inter locking Tile work finishing. | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
4. | 25-10-2017 | Primary School Chopta | Primary school chopta building | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
5. | 25-10-2017 | Primary school chopta | Water tank work complete | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
6. | 25-09-2017 | Primary School Chopta, Rudrapryag | Main Gate work in progress | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
7. | 25-09-2017 | Primary School chopta, Rudrapryag | Bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
8. | 25-09-2017 | Bala work | Bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
9. | 25-09-2017 | Primary School Chopta, Rudrapryag | Stair case railling with bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
10. | 21-07-2017 | Primary school chopta | White washing and painting work is in progress | Anil Kumar RE | RE | UDRP PB | See Pic |
11. | 09-06-2017 | Primary school chopta | 3D | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
12. | 05-05-2017 | Primary school chopta | Kota stone flooring | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
13. | 25-04-2017 | Primary school Chopta | Internal plaster work | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
14. | 17-04-2017 | P.s chopta | Plaster work is in progress | Anil Kumar RE | RE | UDRP PB | See Pic |
15. | 10-04-2017 | Primary School Chopta | Drinking Area | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
16. | 30-03-2017 | Primary school chopta | Plaster work | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
17. | 07-03-2017 | Primary school chopta | Toilet area | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
18. | 03-03-2017 | G.i.c ghimtoli | AAC Block masonry work is in progress | Anil Kumar RE | RE | UDRP PB | See Pic |
19. | 03-03-2017 | P.s chopta | AAC Block masonry work is completed and started inner and outer Plaster work | Anil Kumar RE | RE | UDRP PB | See Pic |
20. | 27-02-2017 | Primary school chopta | First floor | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
|
|