Primary School Gandhari (Chopta)
Work Completed
|
Project: |
UDRP-H |
UID: |
7310 |
Sanction Cost: |
84.17 lakh |
Length:
|
0.000 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
Type: |
Primary School |
|
Procurement: |
Package No.: 2251
Package Name: 
01/BC/PIU/USIDCL/PB/2015-16
Tender Date: 04-09-2015
Current Status: Agreement signed
Achieved on Date: 15-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 01/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Chamoli Associates
|
Start Date: 10-09-2015
Intended Completion Date: 03-09-2017
|
Total Bond Cost: 17714717.24 (177.15 lakh)
Variation Cost: -1276369.24 (-12.76 lakh) Hence Total Bond Cost is 16438348 (164.38 lakh)
|
Sub Project Cost: 87.42 lakh
Variation Cost of Sub Project: -683668.82 (-6.84 lakh)
Total Sub Project Cost:
80.58 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2152251 for +243 days
LD Analysis for Milestone2: calculated LD is Rs 2550816 for 288 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 10.06 Job | 9.25 | 10-09-2015 | 30-08-2017 | 10.06 Job | 10.06 Job | 10.06 | 9.25 | 2. | Foundation and Plinth Work | 16.63 Job | 15.30 | 20-09-2015 | 20-12-2016 | 15.21 Job | 15.21 Job | 16.63 | 15.30 | 3. | Structural Frame | 39.68 Job | 36.51 | 01-01-2016 | 25-08-2017 | 39.68 Job | 39.68 Job | 39.68 | 36.51 | 4. | Doors & Windows | 6.21 Job | 5.72 | 01-04-2016 | 31-08-2017 | 6.21 Job | 6.21 Job | 6.21 | 5.72 | 5. | Water Supply and Sanitary work | 2.29 Job | 2.11 | 01-05-2016 | 31-08-2017 | 2.29 Job | 2.29 Job | 2.29 | 2.11 | 6. | Electrification Works | 3.73 Job | 3.43 | 15-05-2016 | 30-08-2017 | 3.73 Job | 3.73 Job | 3.73 | 3.43 | 7. | Other Allied Works & Finishing Work | 21.40 Job | 19.69 | 15-11-2015 | 01-09-2017 | 21.40 Job | 21.40 Job | 21.4 | 19.69 |
Total Amount: |
92.01 |
|
100 |
92.01 |
|
Remarks:
Task finished
Work Program Made On:
01-02-2016 } ?>
Updation of work program on:
22-08-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-May-2016 | 17.17 lakh | 2. | 30-June-2016 | 8.90 lakh | 3. | 22-September-2016 | 10.46 lakh | 4. | 27-October-2016 | 3.51 lakh | 5. | 29-December-2016 | 5.66 lakh | 6. | 24-January-2017 | 0.66 lakh | 7. | 27-February-2017 | 3.32 lakh | 8. | 25-March-2017 | 2.73 lakh | 9. | 21-June-2017 | 0.72 lakh | 10. | 30-August-2017 | 6.66 lakh | 11. | 24-March-2018 | 20.81 lakh |
Total |
80.6 lakh |
% Payment | 100.02 % |
|
Advance Amount: 8.86 lakh
Recovered Amount: 8.86 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 193 No. of Test Done : 193 No. of Test Passed : 193 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 75 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-02-2018 | Primary school Gandhari | checking of completion work | Anil Kumar RE | RE | UDRP PB | See Pic |
2. | 28-09-2017 | Primary School Gandhari, Rudrapryag | Interlocking paver Tile work in progress. | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
3. | 28-09-2017 | Primary School Gandhari, Rudrapryag | School Building in finishing level. | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
4. | 25-09-2017 | Primary School Gandhari, Rudrapryag | Bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
5. | 25-09-2017 | Primary school Gandhari | Bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
6. | 25-09-2017 | Primary School Gandhari, Rudrapryag | Bala work | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
7. | 25-09-2017 | Primary School Gandhari, Rudrapryag | Stair Case railling and BaLA work. | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
8. | 19-08-2017 | Primary school Gandhari | White washing and painting work is in progress | Anil Kumar RE | RE | UDRP PB | See Pic |
9. | 22-07-2017 | Primary school Gandhari | BaLA drawing work in boundary wall. | Rahul Bhatt | JE | UDRP-H Rudraprayag | See Pic |
10. | 19-07-2017 | Primary school Gandhari | Bala work is in progress | Anil Kumar RE | RE | UDRP PB | See Pic |
11. | 23-05-2017 | Primary school Gandhari | Staircase railing work | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
12. | 15-05-2017 | Primary school gandhari | Putty work | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
13. | 29-04-2017 | Primary school gandhari | Kota stone flooring | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
14. | 29-04-2017 | Primary school Gandhari | Front side 3D | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
15. | 24-04-2017 | Primary school Gandhari | Roof top | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
16. | 15-04-2017 | P.s gandhari | Plaster and finishing work | Anil Kumar RE | RE | UDRP PB | See Pic |
17. | 13-04-2017 | Primary school gandhari | Building 3D | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
18. | 30-03-2017 | Primary school gandhari | External plaster work | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
19. | 23-03-2017 | Primary school Gandhari | External plaster | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
20. | 14-03-2017 | Primary school gandhari | Drinking area channel | Rakesh Rawat | JE | UDRP-H Rudraprayag | See Pic |
|
|