Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Govt Inter College Parkandi Work Completed
Project: UDRP-H UID: 7307 Sanction Cost: 433.61  lakh Length: 0.000 KM.
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA PB DSC: SOWil Limited DSC Scope: Design and Supervision Type: Inter College
Procurement:
Package No.: 2254        Package Name:  04/BC/PIU/USIDCL/PB/2015-16        Tender Date: 20-07-2015        Current Status: Agreement signed        Achieved on Date: 30-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: 04/BC/PIU/USIDCL/PB/2015-16      Contractor Name: Alok Infrabuilders (P) Ltd.
Start Date:  02-11-2015      Intended Completion Date:  15-12-2017      Original End Date:  01-02-2017
Total Bond Cost: 50455343 (504.55 lakh)        Variation Cost: -76475.58 (-0.76 lakh)    Hence Total Bond Cost is   50378867.42 (503.79 lakh) 
Sub Project Cost: 431.28  lakh        Variation Cost of Sub Project: 596345.60  (5.96 lakh)       Total Sub Project Cost:   437.24 lakh
LD Analysis for Milestone1: calculated LD is Rs 3557148 for 141 days        LD Analysis for Milestone2: calculated LD is Rs 6155632 for 244 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development11.89 Job51.9902-11-201514-12-201711.89 Job11.89 Job11.8951.99
2.Foundation and Plinth Work17.23 Job75.3416-11-201515-05-201617.23 Job17.23 Job17.2375.34
3.Structural Frame37.50 Job163.9701-03-201630-08-201737.50 Job37.50 Job37.5163.97
4.Doors & Windows 7.99 Job34.9415-07-201620-09-20177.99 Job7.99 Job7.9934.94
5.Water Supply and Sanitary work 2.30 Job10.0601-09-201615-12-20172.30 Job2.30 Job2.310.06
6.Electrification Works4.93 Job21.5601-06-201610-12-20174.93 Job4.93 Job4.9321.56
7.Other Allied Works & Finishing Work 18.16 Job79.4001-12-201515-12-201718.16 Job18.16 Job18.1679.40
Total Amount: 437.26 100   437.26
Remarks: No Remarks       Work Program Made On: 27-01-2016        Updation of work program on: 10-07-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.10-March-201667.47  lakh
2.31-March-201624.38  lakh
3.29-June-201659.72  lakh
4.11-August-201626.02  lakh
5.20-September-20164.66  lakh
6.27-October-201615.46  lakh
7.20-December-201628.50  lakh
8.24-January-201724.83  lakh
9.27-February-201710.01  lakh
10.25-March-201725.31  lakh
11.25-May-201713.33  lakh
12.21-June-20178.05  lakh
13.30-June-201718.91  lakh
14.16-September-20171.34  lakh
15.25-January-201882.62  lakh
16.23-May-201819.55  lakh
17.29-September-20186.14  lakh
18.01-November-20180.96  lakh
Total 437.26  lakh
% Payment100 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 162   No. of Test Done : 162    No. of Test Passed : 162   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 105
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-12-2017G.I.C.ParkandiPassage kota polish workMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
2.30-11-2017G.I.C.ParkandiBuilding back side viewMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
3.25-10-2017G.I.C.ParkandiClass room finishingMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
4.15-10-2017G.I.C.ParkandiFront viewMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
5.27-08-2017ParkandiKota grinding workVajid AliREUDRP-H Rudraprayag See Pic
6.27-08-2017ParkandiFootpath RailingVajid AliREUDRP-H Rudraprayag See Pic
7.23-08-2017G.I.C.ParkandiG.I.C.Parkandi Pathway & Railing WorkMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
8.19-07-2017ParkandiBoundary wall plasterVajid AliREUDRP-H Rudraprayag See Pic
9.17-07-2017ParkandiBuilding viewVajid AliREUDRP-H Rudraprayag See Pic
10.17-07-2017ParkandiPaint workVajid AliREUDRP-H Rudraprayag See Pic
11.17-07-2017ParkandiBuilding viewVajid AliREUDRP-H Rudraprayag See Pic
12.14-07-2017G.I.C. ParkandiBuilding Front side setting stepsMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
13.18-06-2017G.I.C. ParkandiFront viewMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
14.16-06-2017G.I.C.ParkandiBuilding back & side viewMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
15.09-06-2017G.I.C. parkandiRoom putty workMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
16.04-06-2017Govt. Intercollege parkandiGround floor Right side stairsMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
17.03-06-2017Govt. Inter college parkandiSecond floor stageMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
18.23-05-2017G.I.C. PARKANDIToilet wall tile workMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
19.21-05-2017ParkandiChemistry LabVajid AliREUDRP-H Rudraprayag See Pic
20.13-05-2017G.i.c.parkandiBuilding front viewMukesh Singh BishtJEUDRP-H Rudraprayag See Pic