Govt Inter College Parkandi
Work Completed
|
Project: |
UDRP-H |
UID: |
7307 |
Sanction Cost: |
433.61 lakh |
Length:
|
0.000 KM. |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
Type: |
Inter College |
|
Procurement: |
Package No.: 2254
Package Name: 
04/BC/PIU/USIDCL/PB/2015-16
Tender Date: 20-07-2015
Current Status: Agreement signed
Achieved on Date: 30-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 04/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Alok Infrabuilders (P) Ltd.
|
Start Date: 02-11-2015
Intended Completion Date: 15-12-2017
Original End Date: 01-02-2017 |
Total Bond Cost: 50455343 (504.55 lakh)
Variation Cost: -76475.58 (-0.76 lakh) Hence Total Bond Cost is 50378867.42 (503.79 lakh)
|
Sub Project Cost: 431.28 lakh
Variation Cost of Sub Project: 596345.60 (5.96 lakh)
Total Sub Project Cost:
437.24 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 3557148 for 141 days
LD Analysis for Milestone2: calculated LD is Rs 6155632 for 244 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 11.89 Job | 51.99 | 02-11-2015 | 14-12-2017 | 11.89 Job | 11.89 Job | 11.89 | 51.99 | 2. | Foundation and Plinth Work | 17.23 Job | 75.34 | 16-11-2015 | 15-05-2016 | 17.23 Job | 17.23 Job | 17.23 | 75.34 | 3. | Structural Frame | 37.50 Job | 163.97 | 01-03-2016 | 30-08-2017 | 37.50 Job | 37.50 Job | 37.5 | 163.97 | 4. | Doors & Windows | 7.99 Job | 34.94 | 15-07-2016 | 20-09-2017 | 7.99 Job | 7.99 Job | 7.99 | 34.94 | 5. | Water Supply and Sanitary work | 2.30 Job | 10.06 | 01-09-2016 | 15-12-2017 | 2.30 Job | 2.30 Job | 2.3 | 10.06 | 6. | Electrification Works | 4.93 Job | 21.56 | 01-06-2016 | 10-12-2017 | 4.93 Job | 4.93 Job | 4.93 | 21.56 | 7. | Other Allied Works & Finishing Work | 18.16 Job | 79.40 | 01-12-2015 | 15-12-2017 | 18.16 Job | 18.16 Job | 18.16 | 79.40 |
Total Amount: |
437.26 |
|
100 |
437.26 |
|
Remarks:
No Remarks
Work Program Made On:
27-01-2016 } ?>
Updation of work program on:
10-07-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 10-March-2016 | 67.47 lakh | 2. | 31-March-2016 | 24.38 lakh | 3. | 29-June-2016 | 59.72 lakh | 4. | 11-August-2016 | 26.02 lakh | 5. | 20-September-2016 | 4.66 lakh | 6. | 27-October-2016 | 15.46 lakh | 7. | 20-December-2016 | 28.50 lakh | 8. | 24-January-2017 | 24.83 lakh | 9. | 27-February-2017 | 10.01 lakh | 10. | 25-March-2017 | 25.31 lakh | 11. | 25-May-2017 | 13.33 lakh | 12. | 21-June-2017 | 8.05 lakh | 13. | 30-June-2017 | 18.91 lakh | 14. | 16-September-2017 | 1.34 lakh | 15. | 25-January-2018 | 82.62 lakh | 16. | 23-May-2018 | 19.55 lakh | 17. | 29-September-2018 | 6.14 lakh | 18. | 01-November-2018 | 0.96 lakh |
Total |
437.26 lakh |
% Payment | 100 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 162 No. of Test Done : 162 No. of Test Passed : 162 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 105 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-12-2017 | G.I.C.Parkandi | Passage kota polish work | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
2. | 30-11-2017 | G.I.C.Parkandi | Building back side view | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
3. | 25-10-2017 | G.I.C.Parkandi | Class room finishing | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
4. | 15-10-2017 | G.I.C.Parkandi | Front view | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
5. | 27-08-2017 | Parkandi | Kota grinding work | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
6. | 27-08-2017 | Parkandi | Footpath Railing | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
7. | 23-08-2017 | G.I.C.Parkandi | G.I.C.Parkandi Pathway & Railing Work | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
8. | 19-07-2017 | Parkandi | Boundary wall plaster | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
9. | 17-07-2017 | Parkandi | Building view | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
10. | 17-07-2017 | Parkandi | Paint work | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
11. | 17-07-2017 | Parkandi | Building view | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
12. | 14-07-2017 | G.I.C. Parkandi | Building Front side setting steps | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
13. | 18-06-2017 | G.I.C. Parkandi | Front view | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
14. | 16-06-2017 | G.I.C.Parkandi | Building back & side view | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
15. | 09-06-2017 | G.I.C. parkandi | Room putty work | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
16. | 04-06-2017 | Govt. Intercollege parkandi | Ground floor Right side stairs | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
17. | 03-06-2017 | Govt. Inter college parkandi | Second floor stage | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
18. | 23-05-2017 | G.I.C. PARKANDI | Toilet wall tile work | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
19. | 21-05-2017 | Parkandi | Chemistry Lab | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
20. | 13-05-2017 | G.i.c.parkandi | Building front view | Mukesh Singh Bisht | JE | UDRP-H Rudraprayag | See Pic |
|
|