Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Govt Inter College Peera Dhanpura Work Completed
Project: UDRP-H UID: 7306 Sanction Cost: 404.43  lakh Length: 0.000 KM.
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle:
DEA: DEA PB DSC: SOWil Limited DSC Scope: Design and Supervision Type: Inter College
Procurement:
Package No.: 2257        Package Name:  07/BC/PIU/USIDCL/PB/2015-16        Tender Date: 20-07-2015        Current Status: Agreement signed        Achieved on Date: 30-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: 07/BC/PIU/USIDCL/PB/2015-16      Contractor Name: Surat Singh & Sons
Start Date:  02-11-2015      Intended Completion Date:  28-02-2018      Original End Date:  01-02-2017
Total Bond Cost: 44686685 (446.87 lakh)        Variation Cost: 762294.13 (7.62 lakh)    Hence Total Bond Cost is   45448979.13 (454.49 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 3396136 for +152 days        LD Analysis for Milestone2: calculated LD is Rs 11484302 for 514 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development32.60 Job148.1802-11-201520-12-201732.60 Job32.60 Job32.6148.18
2.Foundation and Plinth Work17.46 Job79.3515-11-201530-03-201614.73 Job14.73 Job17.4679.35
3.Structural Frame25.17 Job114.3901-04-201620-12-201725.17 Job25.17 Job25.17114.39
4.Doors & Windows 11.35 Job51.6115-07-201631-12-201711.35 Job11.35 Job11.3651.61
5.Water Supply and Sanitary work 2.22 Job10.0901-10-201605-12-20172.22 Job2.22 Job2.2210.09
6.Electrification Works2.79 Job12.6901-07-201620-12-20172.79 Job2.79 Job2.7912.69
7.Other Allied Works & Finishing Work 8.40 Job38.1915-11-201530-01-20188.40 Job8.40 Job8.438.19
Total Amount: 454.5 100   454.5
Remarks: No Remarks       Work Program Made On: 02-02-2016        Updation of work program on: 25-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.10-March-201645.00  lakh
2.16-May-201641.78  lakh
3.06-September-201618.04  lakh
4.27-October-201627.14  lakh
5.20-December-20165.36  lakh
6.25-February-201730.42  lakh
7.18-March-20179.59  lakh
8.25-May-201733.85  lakh
9.21-June-20174.83  lakh
10.23-November-201718.42  lakh
11.25-January-201825.23  lakh
12.28-March-201875.63  lakh
13.26-May-201842.13  lakh
14.29-September-201833.07  lakh
Total 410.49  lakh
% Payment 90.31 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 162   No. of Test Done : 162    No. of Test Passed : 162   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
Number of Notice(s) issued: 65

Mobile Pic Upload

Number of Pics Available on Web Repository: 48
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-01-2018ParkandiBuilding viewVajid AliREUDRP-H Rudraprayag See Pic
2.15-10-2017G.I.C.ParkandiFront viewMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
3.13-10-2017G.I.C. ParkandiPointing workMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
4.13-09-2017G.I.C.ParkandiDrinking water shelvesMukesh Singh BishtJEUDRP-H Rudraprayag See Pic
5.22-07-2017G. I. C peeradhanpur3D view of buildingAnil Kumar REREUDRP PB See Pic
6.06-05-2017G.i.c peeradhanpurDPM sir site visitAnil Kumar REREUDRP PB See Pic
7.17-04-2017G.i.c peeradhanpurPlaster and kota stone flooring work is in progressAnil Kumar REREUDRP PB See Pic
8.01-04-2017govt. inter college peeradhanpurcounter slab in lab work in progress.Rahul BhattJEUDRP-H Rudraprayag See Pic
9.01-04-2017govt. inter college peeradhanpurtoilet block footingRahul BhattJEUDRP-H Rudraprayag See Pic
10.18-03-2017govt. inter college peeradhanpurkota stone flooring workRahul BhattJEUDRP-H Rudraprayag See Pic
11.16-03-2017govt. inter college peeradhanpur2nd flor door & windows frame work in progressRahul BhattJEUDRP-H Rudraprayag See Pic
12.07-03-2017govt. inter college peeradhanpurAAC block Masonry work with concrete bendRahul BhattJEUDRP-H Rudraprayag See Pic
13.07-03-2017govt. inter college peeradhanpurboundary wall work in progressRahul BhattJEUDRP-H Rudraprayag See Pic
14.04-03-2017govt.inter college peeradhanpurkota stone flooring work in progressRahul BhattJEUDRP-H Rudraprayag See Pic
15.28-02-2017govt. inter college peeradhanpurboundary wallRahul BhattJEUDRP-H Rudraprayag See Pic
16.28-02-2017govt. inter college peeradhanpurbuilding viewRahul BhattJEUDRP-H Rudraprayag See Pic
17.23-02-2017govt. inter college peeradhanpurboundary wall plaster & grillRahul BhattJEUDRP-H Rudraprayag See Pic
18.23-02-2017govt. inter college peeradhanpurAAC block work in 2nd floorRahul BhattJEUDRP-H Rudraprayag See Pic
19.13-02-2017govt. inter college peeradhanpurRR wall workRahul BhattJEUDRP-H Rudraprayag See Pic
20.13-02-2017govt.inter college peeradhanpurBack side building structure viewRahul BhattJEUDRP-H Rudraprayag See Pic