Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

60 seater Hostel Building in Govt PG College Agastmuni Work Completed
Project: UDRP-H UID: 7305 Sanction Cost: 473.55  lakh Length: 0.000 KM.
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle:
DEA: DEA PB DSC: SOWil Limited DSC Scope: Design and Supervision Type: P.G.College
Procurement:
Package No.: 2263        Package Name:  13/BC/PIU/USIDCL/PB/2015-16        Tender Date: 19-10-2015        Current Status: Agreement signed        Achieved on Date: 27-01-2016

Construction Phase

Agreement Details
Bond/Agreement Name: 13/BC/PIU/USIDCL/PB/2015-16      Contractor Name: Alok Infrabuilders (P) Ltd.
Start Date:  02-02-2016      Intended Completion Date:  04-08-2018      Original End Date:  01-05-2017
Total Bond Cost: 45555555 (455.56 lakh)        Variation Cost: -8200138.52 (-82 lakh)    Hence Total Bond Cost is   37355416.48 (373.55 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 3439478 for +151 days        LD Analysis for Milestone2: calculated LD is Rs 8587306 for 377 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development8.31 Job31.0402-02-201610-02-20188.31 Job8.31 Job8.3131.04
2.Foundation and Plinth Work14.76 Job55.1401-03-201630-06-201614.76 Job14.76 Job14.7655.14
3.Structural Frame32.95 Job123.0901-06-201615-07-201832.95 Job32.95 Job32.95123.09
4.Doors & Windows 16.52 Job61.7101-10-201620-07-201816.52 Job16.52 Job16.5261.71
5.Water Supply and Sanitary work 5.99 Job22.3801-12-201630-07-20185.99 Job5.99 Job5.9922.38
6.Electrification Works11.23 Job41.9501-10-201620-07-201811.23 Job11.23 Job11.23419.50
7.Other Allied Works & Finishing Work 10.24 Job38.2501-03-201604-08-201810.24 Job10.24 Job10.2438.25
Total Amount: 373.56 100   751.11
Remarks: No Remarks       Work Program Made On: 25-02-2016        Updation of work program on: 10-07-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-201617.58  lakh
2.16-May-201627.12  lakh
3.11-August-201625.97  lakh
4.20-September-201626.66  lakh
5.27-October-201642.95  lakh
6.20-December-20169.81  lakh
7.24-January-20177.53  lakh
8.27-February-201714.68  lakh
9.25-March-201713.69  lakh
10.25-May-201711.01  lakh
11.21-June-201711.15  lakh
12.30-June-201713.37  lakh
13.16-September-201731.38  lakh
14.16-October-201731.38  lakh
15.25-January-201813.98  lakh
16.23-May-201822.29  lakh
17.21-August-201814.67  lakh
18.04-June-201938.34  lakh
Total 373.56  lakh
% Payment 100.01 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 14   No. of Test Done : 14    No. of Test Passed : 14   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.12
Number of Notice(s) issued: 62

Mobile Pic Upload

Number of Pics Available on Web Repository: 171
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-08-2017RaturaSite viewVajid AliREUDRP-H Rudraprayag See Pic
2.27-08-2017Solar systemAgaustmuniVajid AliREUDRP-H Rudraprayag See Pic
3.27-08-2017AgastmuniBuilding viewVajid AliREUDRP-H Rudraprayag See Pic
4.27-08-2017AgaustmuniBuilding Road side viewVajid AliREUDRP-H Rudraprayag See Pic
5.19-07-2017AgustimumiTree plantationVajid AliREUDRP-H Rudraprayag See Pic
6.19-07-2017AgaustmuniTree plantationVajid AliREUDRP-H Rudraprayag See Pic
7.19-07-2017AgustimumTiles workVajid AliREUDRP-H Rudraprayag See Pic
8.19-07-2017AgustimumBuilding viewVajid AliREUDRP-H Rudraprayag See Pic
9.19-07-2017AgustimumPaint workVajid AliREUDRP-H Rudraprayag See Pic
10.19-07-2017P.G. College AgastmuniTree Plantation in P.G.College AgastmuniAtul JuyalJEUDRP-H Rudraprayag See Pic
11.19-07-2017AgaustmuniWindowVajid AliREUDRP-H Rudraprayag See Pic
12.14-07-2017P.G. College AgastmuniAluminum Window fixing in wallsAtul JuyalJEUDRP-H Rudraprayag See Pic
13.14-07-2017P.G.College AgastmuniFloor tiles fixing for Common hallAtul JuyalJEUDRP-H Rudraprayag See Pic
14.31-05-2017P.G. College AgastmuniStair Case RailingAtul JuyalJEUDRP-H Rudraprayag See Pic
15.27-05-2017P.G. College AgastmuniAluminum Grill fixing in Aluminum Window FrameAtul JuyalJEUDRP-H Rudraprayag See Pic
16.24-05-2017AgustimuniBuildingVajid AliREUDRP-H Rudraprayag See Pic
17.21-05-2017AgastmuniKota stoneVajid AliREUDRP-H Rudraprayag See Pic
18.21-05-2017AgastmuniFlush doorVajid AliREUDRP-H Rudraprayag See Pic
19.05-05-2017AgastmuniBuilding side viewVajid AliREUDRP-H Rudraprayag See Pic
20.05-05-2017AgastmuniPutty workVajid AliREUDRP-H Rudraprayag See Pic