60 seater Hostel Building in Govt PG College Agastmuni
Work Completed
|
Project: |
UDRP-H |
UID: |
7305 |
Sanction Cost: |
473.55 lakh |
Length:
|
0.000 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
Type: |
P.G.College |
|
Procurement: |
Package No.: 2263
Package Name: 
13/BC/PIU/USIDCL/PB/2015-16
Tender Date: 19-10-2015
Current Status: Agreement signed
Achieved on Date: 27-01-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 13/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Alok Infrabuilders (P) Ltd.
|
Start Date: 02-02-2016
Intended Completion Date: 04-08-2018
Original End Date: 01-05-2017 |
Total Bond Cost: 45555555 (455.56 lakh)
Variation Cost: -8200138.52 (-82 lakh) Hence Total Bond Cost is 37355416.48 (373.55 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 3439478 for +151 days
LD Analysis for Milestone2: calculated LD is Rs 8587306 for 377 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 8.31 Job | 31.04 | 02-02-2016 | 10-02-2018 | 8.31 Job | 8.31 Job | 8.31 | 31.04 | 2. | Foundation and Plinth Work | 14.76 Job | 55.14 | 01-03-2016 | 30-06-2016 | 14.76 Job | 14.76 Job | 14.76 | 55.14 | 3. | Structural Frame | 32.95 Job | 123.09 | 01-06-2016 | 15-07-2018 | 32.95 Job | 32.95 Job | 32.95 | 123.09 | 4. | Doors & Windows | 16.52 Job | 61.71 | 01-10-2016 | 20-07-2018 | 16.52 Job | 16.52 Job | 16.52 | 61.71 | 5. | Water Supply and Sanitary work | 5.99 Job | 22.38 | 01-12-2016 | 30-07-2018 | 5.99 Job | 5.99 Job | 5.99 | 22.38 | 6. | Electrification Works | 11.23 Job | 41.95 | 01-10-2016 | 20-07-2018 | 11.23 Job | 11.23 Job | 11.23 | 419.50 | 7. | Other Allied Works & Finishing Work | 10.24 Job | 38.25 | 01-03-2016 | 04-08-2018 | 10.24 Job | 10.24 Job | 10.24 | 38.25 |
Total Amount: |
373.56 |
|
100 |
751.11 |
|
Remarks:
No Remarks
Work Program Made On:
25-02-2016 } ?>
Updation of work program on:
10-07-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2016 | 17.58 lakh | 2. | 16-May-2016 | 27.12 lakh | 3. | 11-August-2016 | 25.97 lakh | 4. | 20-September-2016 | 26.66 lakh | 5. | 27-October-2016 | 42.95 lakh | 6. | 20-December-2016 | 9.81 lakh | 7. | 24-January-2017 | 7.53 lakh | 8. | 27-February-2017 | 14.68 lakh | 9. | 25-March-2017 | 13.69 lakh | 10. | 25-May-2017 | 11.01 lakh | 11. | 21-June-2017 | 11.15 lakh | 12. | 30-June-2017 | 13.37 lakh | 13. | 16-September-2017 | 31.38 lakh | 14. | 16-October-2017 | 31.38 lakh | 15. | 25-January-2018 | 13.98 lakh | 16. | 23-May-2018 | 22.29 lakh | 17. | 21-August-2018 | 14.67 lakh | 18. | 04-June-2019 | 38.34 lakh |
Total |
373.56 lakh |
% Payment |
100.01 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 14 No. of Test Done : 14 No. of Test Passed : 14 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 94.12 |
Number of Notice(s) issued: 62 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 171 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-08-2017 | Ratura | Site view | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
2. | 27-08-2017 | Solar system | Agaustmuni | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
3. | 27-08-2017 | Agastmuni | Building view | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
4. | 27-08-2017 | Agaustmuni | Building Road side view | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
5. | 19-07-2017 | Agustimumi | Tree plantation | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
6. | 19-07-2017 | Agaustmuni | Tree plantation | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
7. | 19-07-2017 | Agustimum | Tiles work | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
8. | 19-07-2017 | Agustimum | Building view | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
9. | 19-07-2017 | Agustimum | Paint work | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
10. | 19-07-2017 | P.G. College Agastmuni | Tree Plantation in P.G.College Agastmuni | Atul Juyal | JE | UDRP-H Rudraprayag | See Pic |
11. | 19-07-2017 | Agaustmuni | Window | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
12. | 14-07-2017 | P.G. College Agastmuni | Aluminum Window fixing in walls | Atul Juyal | JE | UDRP-H Rudraprayag | See Pic |
13. | 14-07-2017 | P.G.College Agastmuni | Floor tiles fixing for Common hall | Atul Juyal | JE | UDRP-H Rudraprayag | See Pic |
14. | 31-05-2017 | P.G. College Agastmuni | Stair Case Railing | Atul Juyal | JE | UDRP-H Rudraprayag | See Pic |
15. | 27-05-2017 | P.G. College Agastmuni | Aluminum Grill fixing in Aluminum Window Frame | Atul Juyal | JE | UDRP-H Rudraprayag | See Pic |
16. | 24-05-2017 | Agustimuni | Building | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
17. | 21-05-2017 | Agastmuni | Kota stone | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
18. | 21-05-2017 | Agastmuni | Flush door | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
19. | 05-05-2017 | Agastmuni | Building side view | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
20. | 05-05-2017 | Agastmuni | Putty work | Vajid Ali | RE | UDRP-H Rudraprayag | See Pic |
|
|