Police Station Lambagad
Work Completed
|
Project: |
UDRP-H |
UID: |
7302 |
Sanction Cost: |
214.00 lakh |
Length:
|
0.000 KM. |
District: |
Chamoli |
Block: |
Joshimath |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA PB |
DSC: |
SOWil Limited |
DSC Scope: |
Design and Supervision |
Type: |
Police station |
|
Procurement: |
Package No.: 2261
Package Name: 
11/BC/PIU/USIDCL/PB/2015-16
Tender Date: 08-04-2016
Current Status: Agreement signed
Achieved on Date: 30-06-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: 11/BC/PIU/USIDCL/PB/2015-16
Contractor Name: Ayush Construction Pvt. Ltd.
|
Start Date: 30-06-2016
Intended Completion Date: 10-06-2019
Original End Date: 29-09-2017 |
Total Bond Cost: 87304781 (873.05 lakh)
Variation Cost: -37279261.55 (-372.79 lakh) Hence Total Bond Cost is 50025519.45 (500.26 lakh)
|
Sub Project Cost: 411.53 lakh
Variation Cost of Sub Project: 4908179.63 (49.08 lakh)
Total Sub Project Cost:
460.61 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 15671068 for +359 days
LD Analysis for Milestone2: calculated LD is Rs 15409156 for 353 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 6.86 Job | 31.60 | 30-06-2016 | 10-06-2019 | 6.86 Job | 6.86 Job | 6.86 | 31.60 | 2. | Foundation and Plinth Work | 5.37 Job | 24.73 | 15-08-2016 | 30-04-2018 | 5.37 Job | 5.37 Job | 5.37 | 24.73 | 3. | Structural Frame | 58.13 Job | 267.75 | 30-11-2016 | 15-03-2019 | 58.13 Job | 58.13 Job | 58.13 | 267.75 | 4. | Doors & Windows | 8.90 Job | 40.99 | 02-04-2018 | 31-05-2019 | 8.90 Job | 8.90 Job | 8.9 | 40.99 | 5. | Water Supply and Sanitary work | 1.75 Job | 8.06 | 01-03-2018 | 31-05-2019 | 1.75 Job | 1.75 Job | 1.75 | 8.06 | 6. | Electrification Works | 7.25 Job | 33.39 | 30-11-2016 | 05-06-2019 | 7.25 Job | 7.25 Job | 7.25 | 33.39 | 7. | Other Allied Works & Finishing Work | 11.74 Job | 54.08 | 30-06-2016 | 10-06-2019 | 11.74 Job | 11.74 Job | 11.74 | 54.08 |
Total Amount: |
460.6 |
|
100 |
460.6 |
|
Remarks:
No Remarks
Work Program Made On:
07-11-2016 } ?>
Updation of work program on:
19-07-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 21-June-2017 | 23.73 lakh | 2. | 30-June-2017 | 22.07 lakh | 3. | 31-January-2019 | 198.50 lakh | 4. | 14-May-2019 | 81.74 lakh | 5. | 28-May-2019 | 38.31 lakh | 6. | 11-June-2019 | 54.79 lakh | 7. | 24-June-2019 | 32.83 lakh | 8. | 18-October-2019 | 8.65 lakh |
Total |
460.62 lakh |
% Payment | 100 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 357 No. of Test Done : 357 No. of Test Passed : 357 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.52 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 204 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 05-06-2019 | Lambagad | Tree plantation on environment day | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
2. | 05-06-2019 | Lambagad | Plantation on Environment day | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
3. | 05-06-2019 | Lambagad | Plantation on Environment day | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
4. | 04-06-2019 | Lambagad | Front light board | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
5. | 04-06-2019 | Lambagad | Final light testing front building | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
6. | 04-06-2019 | Lambagad | Back side light testing | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
7. | 04-06-2019 | Lambagad | Kitchen geyser, sink, mixture | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
8. | 01-06-2019 | Lambagad | Fire system | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
9. | 01-06-2019 | Lambagad | Smoke detector | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
10. | 01-06-2019 | Lambagad | Fire alarm | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
11. | 01-06-2019 | Lambagad | Testing of CCTV Camera | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
12. | 01-06-2019 | Lambagad | Fixing CCTV Camera | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
13. | 01-06-2019 | Lambagad | Truss fixing work | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
14. | 01-06-2019 | Lambagad | Fire seafty, and CCTV Camera work | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
15. | 01-06-2019 | Lambagd | Fixing truss and polycarbonate sheet | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
16. | 01-06-2019 | Lambagad | Fan and tube light | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
17. | 01-06-2019 | Lambagad | Truss fixing | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
18. | 16-05-2019 | Lambagad | Boundary wall wire fencing | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
19. | 16-05-2019 | Lambagad | Priming on wall | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
20. | 16-05-2019 | Lambagad | Priming on wall | Neeraj Kumar | JE | UDRP-H Chamoli | See Pic |
|
|