Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

FRP Huts at Supi Agreement signed
Project: UEAP-T UID: 7267 Sanction Cost: 97.16  lakh Length: 0.000 KM.
District: Bageshwar Block: Kapkot Constituency: Kapkote Circle: KMVN
DEA: KMVN Bageshwar DSC: DSC Scope: Design and Supervision Type: FRP Huts
Procurement:
Package No.: 2227        Package Name:  UK/UEAP-T(KMVN)/NTL/02(R) BAGESHWAR        Tender Date: 30-10-2014        Current Status: Agreement signed        Achieved on Date: 31-01-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(KMVN)/NTL/02(R) BAGESHWAR      Contractor Name: Enertech Engineering Private Limited
Start Date:  07-02-2015      Intended Completion Date:  06-02-2017     
Total Bond Cost: 73720885.2 (737.21 lakh)       
Sub Project Cost: 81.91  lakh       
LD Analysis for Milestone1: calculated LD is Rs 6450500 for 175 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development1.00 Job5.8010-05-201510-09-20161.00 Job0.90 Job6.555.22
2.Foundation and Plinth Work1.00 Job7.5015-09-201509-11-20151.00 Job1.00 Job9.417.50
3.Structural Frame1.00 Job47.5408-12-201529-02-20161.00 Job1.00 Job59.6547.54
4.Water Supply and Sanitary work 1.00 Job4.7001-05-201610-10-20161.00 Job0.00 Job00.00
5.Electrification Works1.00 Job5.9015-04-201631-10-20161.00 Job0.00 Job00.00
6.Furnishing Work1.00 Job8.2528-01-201615-10-20161.00 Job0.00 Job00.00
Total Amount: 79.69 75.62   60.26
Remarks: No Remarks       Work Program Made On: 18-05-2016        Updation of work program on:       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.05-December-201540.20  lakh
2.14-March-201628.53  lakh
3.02-July-201613.84  lakh
4.14-February-20172.34  lakh
Total 84.91  lakh
% Payment103.66 %
Advance Amount:  111.14  lakh        Recovered Amount:  86.75  lakh        Balance to be Recovered  24.39  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): debris disposal, Query, Borrow pits, DG set
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 18
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.20-03-2017Supi5 Frp hut installed with door windowMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
2.02-03-2017Supi5 GDP AND 5 BATHROOM HAS ALSO BEEN INSTALLED SANITARY WORK IN PROGRESSMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
3.02-03-2017Supi5 FRP AND 5 BATHROOM HAS ALSO BEEN INSTALLEDMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
4.27-09-2016supi5 FRP HUT INSTALLED WITH DOOR window fittingsMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
5.27-09-2016supi5 FRP HUT INSTALLED WITH DOOR WINDOWMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
6.08-08-2016supi5 FRP HUT INSTALLED WITH DOOR WINDOWSMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
7.08-08-2016supi5 FRP HUT INSTALLED WITH DOOR WINDOW FITTINGSMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
8.18-05-2016supiprogress rr work supiHarsh GabaAEUEAP-T KMVN Bageshwar See Pic
9.12-05-2016supihut installed and door window installation in progressMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
10.12-05-2016supi5 hut installed and door window installation in progressMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
11.29-01-2016SupiFive has been installed and bathroom plinth work in progressMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
12.29-01-2016SupiBathroom and stairs step work in progressMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
13.29-01-2016SupiHut has been installed and floor completed.. And stairs step work in progressMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
14.29-01-2016SupiFive Hut has been installed approach and bathroom plinth work in progressMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
15.29-01-2016SupiFive Hut has been installed approach and bathroom plinth work in progressMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
16.14-12-2015SupiTwo Hut has been installed,three Hut plinth complete and RR wall Work In progressMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
17.18-11-2015Site SupiHut installation and stone wall Work In progressMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic
18.18-11-2015SupiHut work installation and stone wall Work In progressMohd. Shazar KhanJEUEAP T-KMVN Bageshwar See Pic