FRP Huts at Supi
Agreement signed
|
Project: |
UEAP-T |
UID: |
7267 |
Sanction Cost: |
97.16 lakh |
Length:
|
0.000 KM. |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
KMVN |
DEA: |
KMVN Bageshwar |
DSC: |
|
DSC Scope: |
Design and Supervision |
Type: |
FRP Huts |
|
Procurement: |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(KMVN)/NTL/02(R) BAGESHWAR
Contractor Name: Enertech Engineering Private Limited
|
Start Date: 07-02-2015
Intended Completion Date: 06-02-2017
|
Total Bond Cost: 73720885.2 (737.21 lakh)
|
Sub Project Cost: 81.91 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 6450500 for 175 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 1.00 Job | 5.80 | 10-05-2015 | 10-09-2016 | 1.00 Job | 0.90 Job | 6.55 | 5.22 | 2. | Foundation and Plinth Work | 1.00 Job | 7.50 | 15-09-2015 | 09-11-2015 | 1.00 Job | 1.00 Job | 9.41 | 7.50 | 3. | Structural Frame | 1.00 Job | 47.54 | 08-12-2015 | 29-02-2016 | 1.00 Job | 1.00 Job | 59.65 | 47.54 | 4. | Water Supply and Sanitary work | 1.00 Job | 4.70 | 01-05-2016 | 10-10-2016 | 1.00 Job | 0.00 Job | 0 | 0.00 | 5. | Electrification Works | 1.00 Job | 5.90 | 15-04-2016 | 31-10-2016 | 1.00 Job | 0.00 Job | 0 | 0.00 | 6. | Furnishing Work | 1.00 Job | 8.25 | 28-01-2016 | 15-10-2016 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
79.69 |
|
75.62 |
60.26 |
|
Remarks:
No Remarks
Work Program Made On:
18-05-2016 } ?>
Updation of work program on:
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 05-December-2015 | 40.20 lakh | 2. | 14-March-2016 | 28.53 lakh | 3. | 02-July-2016 | 13.84 lakh | 4. | 14-February-2017 | 2.34 lakh |
Total |
84.91 lakh |
% Payment | 103.66 % |
|
Advance Amount: 111.14 lakh
Recovered Amount: 86.75 lakh
Balance to be Recovered 24.39 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
No Pending Issue
Environment & Social Compliances(Sub Project level):
debris disposal, Query, Borrow pits, DG set |
Detailed report of this subproject
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 18 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 20-03-2017 | Supi | 5 Frp hut installed with door window | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
2. | 02-03-2017 | Supi | 5 GDP AND 5 BATHROOM HAS ALSO BEEN INSTALLED SANITARY WORK IN PROGRESS | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
3. | 02-03-2017 | Supi | 5 FRP AND 5 BATHROOM HAS ALSO BEEN INSTALLED | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
4. | 27-09-2016 | supi | 5 FRP HUT INSTALLED WITH DOOR window fittings | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
5. | 27-09-2016 | supi | 5 FRP HUT INSTALLED WITH DOOR WINDOW | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
6. | 08-08-2016 | supi | 5 FRP HUT INSTALLED WITH DOOR WINDOWS | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
7. | 08-08-2016 | supi | 5 FRP HUT INSTALLED WITH DOOR WINDOW FITTINGS | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
8. | 18-05-2016 | supi | progress rr work supi | Harsh Gaba | AE | UEAP-T KMVN Bageshwar | See Pic |
9. | 12-05-2016 | supi | hut installed and door window installation in progress | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
10. | 12-05-2016 | supi | 5 hut installed and door window installation in progress | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
11. | 29-01-2016 | Supi | Five has been installed and bathroom plinth work in progress | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
12. | 29-01-2016 | Supi | Bathroom and stairs step work in progress | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
13. | 29-01-2016 | Supi | Hut has been installed and floor completed.. And stairs step work in progress | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
14. | 29-01-2016 | Supi | Five Hut has been installed approach and bathroom plinth work in progress | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
15. | 29-01-2016 | Supi | Five Hut has been installed approach and bathroom plinth work in progress | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
16. | 14-12-2015 | Supi | Two Hut has been installed,three Hut plinth complete and RR wall Work In progress | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
17. | 18-11-2015 | Site Supi | Hut installation and stone wall Work In progress | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
18. | 18-11-2015 | Supi | Hut work installation and stone wall Work In progress | Mohd. Shazar Khan | JE | UEAP T-KMVN Bageshwar | See Pic |
|
|