Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

T.L. Barkot Agreement signed
Project: UEAP-T UID: 7248 Sanction Cost: 76.45  lakh Length: 0.000 KM.
District: Uttarkashi Block: Naugaon Constituency: Yamunotri Circle:
DEA: GMVN Uttarkashi DSC: DSC Scope: Design and Supervision Type: Restoration of TRH
Procurement:
Package No.: 2230        Package Name:  UK/UEAP-T(GMVN)/DDN/09/LOT U3 ( T.L. BARKOT)        Tender Date: 16-05-2016        Current Status: Agreement signed        Achieved on Date: 28-10-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/09/LOT U3 ( T.L. BARKOT)      Contractor Name: Manmohan Singh Rawat
Start Date:  06-11-2016      Intended Completion Date:  31-08-2017      Original End Date:  05-05-2017
Total Bond Cost: 6890000 (68.9 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 1057615 for 307 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development2.00 Job8.6110-11-201621-08-20172.00 Job1.50 Job9.376.45
2.Foundation and Plinth Work2.00 Job10.0530-11-201618-08-20172.00 Job1.80 Job13.139.05
3.Structural Frame2.00 Job2.9810-01-201727-08-20172.00 Job0.40 Job0.860.60
4.Doors & Windows 1.00 Job0.9805-03-201722-08-20171.00 Job0.00 Job00.00
5.Water Supply and Sanitary work 1.00 Job1.3810-03-201729-08-20171.00 Job0.00 Job00.00
6.Electrification Works2.00 Job11.9810-03-201730-08-20172.00 Job1.40 Job12.188.39
7.Other Allied Works & Finishing Work 2.00 Job7.5316-01-201731-08-20172.00 Job0.00 Job00.00
8.Furnishing Work2.00 Job25.3918-01-201730-08-20172.00 Job1.40 Job25.7917.77
Total Amount: 68.9 61.33   42.26
Remarks: No Remarks       Work Program Made On: 13-06-2017        Updation of work program on: 30-08-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.21-September-201714.74  lakh
Total 14.74  lakh
% Payment 21.39 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill should be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles, labour licence, workmen Insurance
Environment & Social Compliances(Sub Project level): Land Owner Consent, Helmet, Jacket, Boot, Glove, Signs, project information board, debris disposal, Query
Detailed report of this subproject
Quality
Test Information not Available.
Quality ranking not done.
Number of Notice(s) issued: 8

Mobile Pic Upload

Number of Pics Available on Web Repository: 9
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-09-2017TL BarkotFixing of chequred tiles has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
2.02-09-2017TL BarkotAluminum Windows has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
3.29-07-2017TRH SyanachattiWork of fixing of flush Doors has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
4.29-07-2017TRH SyanachattiWork of wall tiles in toilet is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
5.29-07-2017TRH SyanachattiWork of ceilng in Reception has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
6.29-07-2017TRH SyanachattiWork of ceilng has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
7.27-06-2017TRH BarkotInstallation of DG Set has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
8.27-06-2017TRH BarkotVitrified tiles in flooring has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
9.27-06-2017TRH BarkotWork of ceilng has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic