TRH Adibadri Work Completed
Project: UEAP-T UID: 7242 Sanction Cost: 41.08  lakh Length: 0.000 KM.
District: Chamoli Block: Gairsain Constituency: Karanprayag Circle:
DEA: GMVN Chamoli DSC: DSC Scope: Design and Supervision Type: Restoration of TRH
Procurement:
Package No.: 2222        Package Name:  UK/UEAP-T(GMVN)/DDN/09/LOT C2 (TRH AADIBADRI)        Tender Date: 16-05-2016        Current Status: Agreement signed        Achieved on Date: 28-10-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/09/LOT C2 (TRH AADIBADRI)      Contractor Name: Sthapati Consultants
Start Date:  06-11-2016      Intended Completion Date:  31-08-2017      Original End Date:  05-05-2017
Total Bond Cost: 3734000 (37.34 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 573169 for 307 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development3.00 Job10.2311-11-201627-04-20173.00 Job3.00 Job27.3910.23
2.Electrification Works2.00 Job9.6001-02-201730-04-20172.00 Job2.00 Job25.719.60
3.Furnishing Work3.00 Job17.5116-01-201725-04-20173.00 Job3.00 Job46.917.51
Total Amount: 37.34 100   37.34
Remarks: No Remarks       Work Program Made On: 09-06-2017        Updation of work program on:       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.13-September-201715.20  lakh
Total 15.2  lakh
% Payment 40.71 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill should be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality ranking not done.
Number of Notice(s) issued: 13

Mobile Pic Upload

Number of Pics Available on Web Repository: 1
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-06-2017TRH AdibadriUpgradation work is in progressRajat RajputAEUEAP-T GMVN Chamoli See Pic