Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

TRH Pipalkoti Agreement signed
Project: UEAP-T UID: 7235 Sanction Cost: 125.69  lakh Length: 0.000 KM.
District: Chamoli Block: 0008 Constituency: 4 Circle:
DEA: GMVN Chamoli DSC: Sheladia Associates DSC Scope: Design and Supervision Type: Restoration of TRH
Procurement:
Package No.: 2215        Package Name:  UK/UEAP-T(GMVN)/DDN/08/Lot C5        Tender Date: 22-01-2016        Current Status: Agreement signed        Achieved on Date: 30-07-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/08/Lot C5      Contractor Name: Sameer Construction Co.
Start Date:  17-04-2016      Intended Completion Date:  31-07-2017      Original End Date:  16-01-2017
Total Bond Cost: 12909000 (129.09 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 2362530 for 366 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan2.00 Job3.5717-04-201631-10-20172.00 Job0.00 Job00.00
2.Site Development3.00 Job1.0718-04-201631-10-20173.00 Job0.00 Job00.00
3.Foundation and Plinth Work3.00 Job14.8019-05-201631-10-20173.00 Job0.00 Job00.00
4.Structural Frame3.00 Job16.4011-07-201631-10-20173.00 Job0.00 Job00.00
5.Doors & Windows 2.00 Job9.3115-07-201631-10-20172.00 Job0.00 Job00.00
6.Water Supply and Sanitary work 3.00 Job15.3310-08-201631-10-20173.00 Job0.00 Job00.00
7.Electrification Works3.00 Job31.3322-06-201631-10-20173.00 Job0.00 Job00.00
8.Other Allied Works & Finishing Work 3.00 Job23.0316-06-201631-10-20173.00 Job0.00 Job00.00
9.Furnishing Work3.00 Job14.2520-09-201631-10-20173.00 Job0.00 Job00.00
Total Amount: 129.09 0   0
Remarks: No Remarks       Work Program Made On: 25-10-2017        Updation of work program on: 25-10-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.21-August-201716.04  lakh
Total 16.04  lakh
% Payment 12.43 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): labour licence
Environment & Social Compliances(Sub Project level): project information board
Detailed report of this subproject
Quality
No. of Test Required : 4   No. of Test Done : 4    No. of Test Passed : 4   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality ranking not done.
Number of Notice(s) issued: 13

Mobile Pic Upload

Number of Pics Available on Web Repository: 25
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-06-2017TRH PipalkotiUpgraded receptionRajat RajputAEUEAP-T GMVN Chamoli See Pic
2.14-06-2017TRH PipalkotiUpgraded Delux roomRajat RajputAEUEAP-T GMVN Chamoli See Pic
3.14-06-2017TRH PipalkotiUpgraded passageRajat RajputAEUEAP-T GMVN Chamoli See Pic
4.14-06-2017TRH PipalkotiSD Room upgraded toiletRajat RajputAEUEAP-T GMVN Chamoli See Pic
5.14-06-2017TRH PipalkotiTV & AC installed in SD RoomRajat RajputAEUEAP-T GMVN Chamoli See Pic
6.14-06-2017TRH PipalkotiUpgraded SD RoomRajat RajputAEUEAP-T GMVN Chamoli See Pic
7.14-06-2017TRH PipalkotiKitchen equipment installed in trhRajat RajputAEUEAP-T GMVN Chamoli See Pic
8.14-06-2017TRH PipalkotiUpgraded dining hallRajat RajputAEUEAP-T GMVN Chamoli See Pic
9.06-06-2017PipalkotiDining hall finishing work is completedAshish KumarJEUEAP-T GMVN Chamoli See Pic
10.06-06-2017PipalkotiPassage finishing work is completedAshish KumarJEUEAP-T GMVN Chamoli See Pic
11.26-04-2017PipalkotiSS railing work is in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
12.26-04-2017PipalkotiDismantling work in super Deluxe room is in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
13.15-04-2017PipalkotiElectrical fixtures fitment waork under progressAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
14.15-04-2017PipalkotiFixture fitment work under progressAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
15.05-03-2017PipalkotiGranite work in staircaseRajat RajputAEUEAP-T GMVN Chamoli See Pic
16.05-03-2017PipalkotiTucking work on walls for popRajat RajputAEUEAP-T GMVN Chamoli See Pic
17.05-03-2017PipalkotiFalse ceiling work in receptionRajat RajputAEUEAP-T GMVN Chamoli See Pic
18.05-03-2017PipalkotiFalse ceiling work in dinning hallRajat RajputAEUEAP-T GMVN Chamoli See Pic
19.22-12-2016PipalkotiDinning hall upgradation work is in progressRajat RajputAEUEAP-T GMVN Chamoli See Pic
20.07-12-2016PipalkotiFalse ceiling work at siteRajat RajputAEUEAP-T GMVN Chamoli See Pic