Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

LGFS Huts at Guptkashi Agreement signed
Project: UEAP-T UID: 7216 Sanction Cost: 52.09  lakh Length: KM.
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle: GMVN
DEA: GMVN Rudraprayag DSC: DSC Scope: Design & Supervision Type: LGFS Huts
Procurement:
Package No.: 2204        Package Name:  UK/UEAP-T(GMVN)/DDN/06        Tender Date: 02-05-2014        Current Status: Agreement signed        Achieved on Date: 01-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/06      Contractor Name: Loom Crafts Shade Systems Pvt. Ltd
Start Date:  09-10-2014      Intended Completion Date:  31-08-2017      Original End Date:  08-04-2016
Total Bond Cost: 176686392 (1766.86 lakh)        Variation Cost: 26127450.68 (261.27 lakh)    Hence Total Bond Cost is   202813842.68 (2028.14 lakh) 
Sub Project Cost: 52.09  lakh       
LD Analysis for Milestone1: calculated LD is Rs 16166769 for +183 days        LD Analysis for Milestone2: calculated LD is Rs 61133356 for 692 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development1.00 Job2.0816-01-201515-03-20151.00 Job1.00 Job4.182.08
2.Foundation and Plinth Work1.00 Job1.4201-02-201531-03-20151.00 Job1.00 Job2.861.42
3.Structural Frame1.00 Job27.7001-02-201530-04-20151.00 Job1.00 Job55.8227.70
4.Doors & Windows 1.00 Job1.7301-05-201515-05-20151.00 Job1.00 Job3.491.73
5.Water Supply and Sanitary work 1.00 Job3.4401-05-201531-05-20151.00 Job1.00 Job6.923.44
6.Electrification Works1.00 Job1.0701-05-201531-05-20151.00 Job1.00 Job2.161.07
7.Other Allied Works & Finishing Work 1.00 Job8.5215-04-201515-06-20151.00 Job0.60 Job10.35.11
8.Furnishing Work1.00 Job3.6816-06-201530-06-20151.00 Job1.00 Job7.413.68
Total Amount: 49.64 93.14   46.23
Remarks: No Remarks       Work Program Made On: 05-01-2015        Updation of work program on:       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.07-September-20153.80  lakh
2.30-November-20151.59  lakh
3.30-January-201619.05  lakh
4.29-February-20164.50  lakh
5.30-April-20160.00  lakh
6.31-May-201621.47  lakh
7.16-August-20169.71  lakh
8.22-September-201625.78  lakh
Total 85.9  lakh
% Payment164.91 %
Advance Amount:  175.00  lakh        Recovered Amount:  19.69  lakh        Balance to be Recovered  155.31  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): project information board
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 95.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 13
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.09-05-2016Lgfs hut guptkashiFixing of Internal G.I work in progressHarish ChauhanJEGMVN Rudraprayag See Pic
2.09-05-2016GuptkashiElectrical wiring complete in hut at guptkashiManoj Kumar DobhalJEUEAP-T GMVN Rudraprayag See Pic
3.08-05-2016Lgfs hut guptkashiAluminium and stone cladding work in progressHarish ChauhanJEGMVN Rudraprayag See Pic
4.30-04-2016GuptkashiElectrical wiring under progressAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
5.29-04-2016GuptkashiELectrification work under progressAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
6.08-02-2016Lgfs hut at GuptkashiInstallation of exterior OSB boardHarish ChauhanJEGMVN Rudraprayag See Pic
7.25-01-2016Erection of lgfs structureGuptkashiHarish ChauhanJEGMVN Rudraprayag See Pic
8.29-09-2015GuptkashiCasting of foundation columnsHarish ChauhanJEGMVN Rudraprayag See Pic
9.24-06-2015GuptkashiRetaining wall work in progressGambhir SinghDPMPIU UEAP Tourism See Pic
10.23-06-2015GuptkashiRetaining wall work in progressGambhir SinghDPMPIU UEAP Tourism See Pic
11.11-06-2015GuptkashiGuptkashiHarish ChauhanJEGMVN Rudraprayag See Pic
12.14-05-2015GuptkashiReinforcement work of retaining wall in progressGambhir SinghDPMPIU UEAP Tourism See Pic
13.15-04-2015Guptkashi TRHArchitect from DSC is required to supervise extra land cutting.JitendraEnv ExpertADB Tourism See Pic