LGFS Huts, Multi Purpose Hall & Meditation Center at Tilwara
Agreement signed
|
Project: |
UEAP-T |
UID: |
7213 |
Sanction Cost: |
810.49 lakh |
Length:
|
KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
GMVN |
DEA: |
GMVN Rudraprayag |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
LGFS Huts |
|
Procurement: |
Package No.: 2204
Package Name: 
UK/UEAP-T(GMVN)/DDN/06
Tender Date: 02-05-2014
Current Status: Agreement signed
Achieved on Date: 01-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/06
Contractor Name: Loom Crafts Shade Systems Pvt. Ltd
|
Start Date: 09-10-2014
Intended Completion Date: 31-08-2017
Original End Date: 08-04-2016 |
Total Bond Cost: 176686392 (1766.86 lakh)
Variation Cost: 26127450.68 (261.27 lakh) Hence Total Bond Cost is 202813842.68 (2028.14 lakh)
|
Sub Project Cost: 810.49 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 16166769 for +183 days
LD Analysis for Milestone2: calculated LD is Rs 61133356 for 692 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 1.00 Job | 34.09 | 01-01-2015 | 31-10-2017 | 1.00 Job | 1.00 Job | 4.32 | 34.09 | 2. | Foundation and Plinth Work | 1.00 Job | 27.71 | 16-01-2015 | 31-10-2017 | 1.00 Job | 1.00 Job | 3.51 | 27.71 | 3. | Structural Frame | 1.00 Job | 418.68 | 01-02-2015 | 31-08-2015 | 1.00 Job | 1.00 Job | 53.03 | 418.68 | 4. | Doors & Windows | 1.00 Job | 31.63 | 01-01-2016 | 31-10-2017 | 1.00 Job | 1.00 Job | 4.01 | 31.63 | 5. | Water Supply and Sanitary work | 1.00 Job | 49.10 | 01-09-2015 | 31-10-2017 | 1.00 Job | 0.90 Job | 5.6 | 44.19 | 6. | Electrification Works | 1.00 Job | 22.96 | 01-09-2015 | 31-10-2017 | 1.00 Job | 0.90 Job | 2.62 | 20.66 | 7. | Other Allied Works & Finishing Work | 1.00 Job | 121.66 | 01-08-2015 | 31-10-2017 | 1.00 Job | 0.80 Job | 12.33 | 97.33 | 8. | Furnishing Work | 1.00 Job | 83.70 | 01-12-2015 | 31-10-2017 | 1.00 Job | 1.00 Job | 10.6 | 83.70 |
Total Amount: |
789.53 |
|
96.01 |
757.99 |
|
Remarks:
No Remarks
Work Program Made On:
02-01-2015 } ?>
Updation of work program on:
11-10-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 07-September-2015 | 8.72 lakh | 2. | 10-September-2015 | 36.90 lakh | 3. | 31-October-2015 | 14.60 lakh | 4. | 30-November-2015 | 48.63 lakh | 5. | 31-December-2015 | 73.60 lakh | 6. | 30-January-2016 | 31.34 lakh | 7. | 29-February-2016 | 36.33 lakh | 8. | 30-April-2016 | 53.86 lakh | 9. | 31-May-2016 | 52.02 lakh | 10. | 16-August-2016 | 27.79 lakh | 11. | 22-September-2016 | 61.38 lakh | 12. | 31-August-2017 | 35.06 lakh |
Total |
480.23 lakh |
% Payment | 59.25 % |
|
Advance Amount: 175.00 lakh
Recovered Amount: 19.69 lakh
Balance to be Recovered 155.31 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 95.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 113 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 10-08-2017 | Construction of Lgfs hut at tilwara | Fixing of CFB & wall cladding work is in progress at lgfs hut | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
2. | 05-08-2017 | Construction of lgfs huts at tilwara | Fixing of membrane of MPH is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
3. | 05-08-2017 | Construction of lgfs huts | Fixing of lgfs ceiling of MPH is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
4. | 19-07-2017 | Multipurpose hall | Fixing of roof shingle of MPH is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
5. | 19-07-2017 | Lgfs hut at tilwara | Internal plumbing work in hut no 13 is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
6. | 19-07-2017 | Lgfs huts at tilwara | Construction of RR Retaining wall behind hut no 9 to 13 is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
7. | 19-07-2017 | Lgfs hut at tilwara | Fixing of CFB at corners of hut no 11 is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
8. | 19-07-2017 | Lgfs huts | Tile work in toilets of hut no 12 is in progress. | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
9. | 19-07-2017 | Lgfs hut | Wall cladding work is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
10. | 27-06-2017 | Construction of lgfs hut at tilwara | Landscaping work is in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
11. | 06-06-2017 | LGFS HUT AT TILWARA | Installation of concealed cistern jaquar make at hut no 13 | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
12. | 05-05-2017 | Construction of LGFS Huts at Tilwara | Lgfs huts at Tilwara made available for tourist use | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
13. | 02-05-2017 | Tilwara | Fixing of 160 KVA DG set | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
14. | 02-05-2017 | Tilwara | Fixing of main feeder panal at tilwara site. | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
15. | 02-05-2017 | Tilwara | Hut no 6 7 and 8 | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
16. | 02-05-2017 | Tilwara | Hut no 13 | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
17. | 15-04-2017 | Tilwara | LGFS huts at Tilwara | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
18. | 15-04-2017 | Tilwara | Work is in progress at tilwara in Multipurpose Hall. | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
19. | 11-04-2017 | Multipurpose Hall | Installation of ISMB BUILT UP SECTION Beam | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
20. | 28-01-2017 | Mph tilwara | Construction of MPH lgfs wall in progress | Harish Chauhan | JE | GMVN Rudraprayag | See Pic |
|
|