Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

LGFS Huts, Multi Purpose Hall & Meditation Center at Tilwara Agreement signed
Project: UEAP-T UID: 7213 Sanction Cost: 810.49  lakh Length: KM.
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle: GMVN
DEA: GMVN Rudraprayag DSC: DSC Scope: Design & Supervision Type: LGFS Huts
Procurement:
Package No.: 2204        Package Name:  UK/UEAP-T(GMVN)/DDN/06        Tender Date: 02-05-2014        Current Status: Agreement signed        Achieved on Date: 01-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/06      Contractor Name: Loom Crafts Shade Systems Pvt. Ltd
Start Date:  09-10-2014      Intended Completion Date:  31-08-2017      Original End Date:  08-04-2016
Total Bond Cost: 176686392 (1766.86 lakh)        Variation Cost: 26127450.68 (261.27 lakh)    Hence Total Bond Cost is   202813842.68 (2028.14 lakh) 
Sub Project Cost: 810.49  lakh       
LD Analysis for Milestone1: calculated LD is Rs 16166769 for +183 days        LD Analysis for Milestone2: calculated LD is Rs 61133356 for 692 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development1.00 Job34.0901-01-201531-10-20171.00 Job1.00 Job4.3234.09
2.Foundation and Plinth Work1.00 Job27.7116-01-201531-10-20171.00 Job1.00 Job3.5127.71
3.Structural Frame1.00 Job418.6801-02-201531-08-20151.00 Job1.00 Job53.03418.68
4.Doors & Windows 1.00 Job31.6301-01-201631-10-20171.00 Job1.00 Job4.0131.63
5.Water Supply and Sanitary work 1.00 Job49.1001-09-201531-10-20171.00 Job0.90 Job5.644.19
6.Electrification Works1.00 Job22.9601-09-201531-10-20171.00 Job0.90 Job2.6220.66
7.Other Allied Works & Finishing Work 1.00 Job121.6601-08-201531-10-20171.00 Job0.80 Job12.3397.33
8.Furnishing Work1.00 Job83.7001-12-201531-10-20171.00 Job1.00 Job10.683.70
Total Amount: 789.53 96.01   757.99
Remarks: No Remarks       Work Program Made On: 02-01-2015        Updation of work program on: 11-10-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.07-September-20158.72  lakh
2.10-September-201536.90  lakh
3.31-October-201514.60  lakh
4.30-November-201548.63  lakh
5.31-December-201573.60  lakh
6.30-January-201631.34  lakh
7.29-February-201636.33  lakh
8.30-April-201653.86  lakh
9.31-May-201652.02  lakh
10.16-August-201627.79  lakh
11.22-September-201661.38  lakh
12.31-August-201735.06  lakh
Total 480.23  lakh
% Payment59.25 %
Advance Amount:  175.00  lakh        Recovered Amount:  19.69  lakh        Balance to be Recovered  155.31  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 95.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 113
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-08-2017Construction of Lgfs hut at tilwaraFixing of CFB & wall cladding work is in progress at lgfs hutHarish ChauhanJEGMVN Rudraprayag See Pic
2.05-08-2017Construction of lgfs huts at tilwaraFixing of membrane of MPH is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
3.05-08-2017Construction of lgfs hutsFixing of lgfs ceiling of MPH is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
4.19-07-2017Multipurpose hallFixing of roof shingle of MPH is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
5.19-07-2017Lgfs hut at tilwaraInternal plumbing work in hut no 13 is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
6.19-07-2017Lgfs huts at tilwaraConstruction of RR Retaining wall behind hut no 9 to 13 is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
7.19-07-2017Lgfs hut at tilwaraFixing of CFB at corners of hut no 11 is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
8.19-07-2017Lgfs hutsTile work in toilets of hut no 12 is in progress.Harish ChauhanJEGMVN Rudraprayag See Pic
9.19-07-2017Lgfs hutWall cladding work is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
10.27-06-2017Construction of lgfs hut at tilwaraLandscaping work is in progressHarish ChauhanJEGMVN Rudraprayag See Pic
11.06-06-2017LGFS HUT AT TILWARAInstallation of concealed cistern jaquar make at hut no 13Harish ChauhanJEGMVN Rudraprayag See Pic
12.05-05-2017Construction of LGFS Huts at TilwaraLgfs huts at Tilwara made available for tourist useHarish ChauhanJEGMVN Rudraprayag See Pic
13.02-05-2017TilwaraFixing of 160 KVA DG setAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
14.02-05-2017TilwaraFixing of main feeder panal at tilwara site.Ashish AswalAEUEAP-T GMVN Rudraprayag See Pic
15.02-05-2017TilwaraHut no 6 7 and 8Ashish AswalAEUEAP-T GMVN Rudraprayag See Pic
16.02-05-2017TilwaraHut no 13Ashish AswalAEUEAP-T GMVN Rudraprayag See Pic
17.15-04-2017TilwaraLGFS huts at TilwaraAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
18.15-04-2017TilwaraWork is in progress at tilwara in Multipurpose Hall.Ashish AswalAEUEAP-T GMVN Rudraprayag See Pic
19.11-04-2017Multipurpose HallInstallation of ISMB BUILT UP SECTION BeamHarish ChauhanJEGMVN Rudraprayag See Pic
20.28-01-2017Mph tilwaraConstruction of MPH lgfs wall in progressHarish ChauhanJEGMVN Rudraprayag See Pic