Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Hybrid Huts at Lohjung Agreement signed
Project: UEAP-T UID: 7212 Sanction Cost: 109.57  lakh Length: KM.
District: Chamoli Block: Dewal Constituency: Tharali Circle: GMVN
DEA: GMVN Chamoli DSC: DSC Scope: Design & Supervision Type: Hybrid Huts
Procurement:
Package No.: 2203        Package Name:  UK/UEAP-T(GMVN)/DDN/05        Tender Date: 12-06-2014        Current Status: Agreement signed        Achieved on Date: 01-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/05      Contractor Name: ACME Clean Tech Solutions Ltd
Start Date:  10-10-2014      Intended Completion Date:  30-06-2017      Original End Date:  09-04-2016
Total Bond Cost: 44096194.28 (440.96 lakh)        Variation Cost: 6605615.89 (66.06 lakh)    Hence Total Bond Cost is   50701810.17 (507.02 lakh) 
Sub Project Cost: 109.57  lakh       
LD Analysis for Milestone1: calculated LD is Rs 4034784 for +183 days        LD Analysis for Milestone2: calculated LD is Rs 13868192 for 629 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development1.00 Job1.7801-03-201515-05-20151.00 Job0.95 Job2.351.69
2.Foundation and Plinth Work1.00 Job11.5016-03-201531-05-20151.00 Job1.00 Job15.9811.50
3.Structural Frame1.00 Job42.6516-04-201515-08-20151.00 Job0.90 Job53.3438.38
4.Doors & Windows 1.00 Job3.0916-08-201515-09-20151.00 Job0.00 Job00.00
5.Water Supply and Sanitary work 1.00 Job2.9201-09-201530-09-20151.00 Job0.00 Job00.00
6.Electrification Works1.00 Job1.0501-09-201530-09-20151.00 Job0.00 Job00.00
7.Other Allied Works & Finishing Work 1.00 Job3.2216-08-201530-11-20151.00 Job0.20 Job0.90.64
8.Furnishing Work1.00 Job5.7501-12-201531-12-20151.00 Job0.00 Job00.00
Total Amount: 71.96 72.56   52.21
Remarks: No Remarks       Work Program Made On: 07-01-2015        Updation of work program on:       
Work Program Status:Program Expired.
Financial Progress
No Financial Progress.
Advance Amount:  210.99  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  210.99  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): project information board
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 93.44
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 47
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-10-2016LohajungFinishing work in progressAshish AswalAEUEAP-T GMVN Rudraprayag See Pic
2.18-10-2016LohajungApproch staircase work to hybrid hut is in progressRajat RajputAEUEAP-T GMVN Chamoli See Pic
3.18-10-2016LohajungFloor tile work completedRajat RajputAEUEAP-T GMVN Chamoli See Pic
4.18-10-2016LohajungMaterial viz OHT structure, tiles, wall paneling material, false ceiling etc transported at site.Rajat RajputAEUEAP-T GMVN Chamoli See Pic
5.07-09-2016lohajungstair work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
6.07-09-2016lohajunginterior work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
7.07-09-2016lohajunginterior work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
8.02-08-2016Lgfs hut tilwaraFinishing of lgfs hut is in progress.Gambhir SinghDPMPIU UEAP Tourism See Pic
9.24-06-2016LohajungHybrid Hut at LohajungRajat RajputAEUEAP-T GMVN Chamoli See Pic
10.24-06-2016LohajungFalse ceiling work at lohajung, no labourers present at siteRajat RajputAEUEAP-T GMVN Chamoli See Pic
11.22-06-2016LohjungFalse Ceiling work at Lohjung site.Ashish AswalAEUEAP-T GMVN Rudraprayag See Pic
12.23-03-2016LohjungNo work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
13.23-03-2016LohjungNo work in progress due to material not availableAshish KumarJEUEAP-T GMVN Chamoli See Pic
14.23-03-2016LohjungNo work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
15.23-03-2016LohjungNo work in progress last 7 daysAshish KumarJEUEAP-T GMVN Chamoli See Pic
16.22-03-2016LohjungNo work in progress at siteAshish KumarJEUEAP-T GMVN Chamoli See Pic
17.22-03-2016LohjungNo work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
18.22-03-2016LohjungNo work in progress last 7 daysAshish KumarJEUEAP-T GMVN Chamoli See Pic
19.22-03-2016LohjungNo work in progressAshish KumarJEUEAP-T GMVN Chamoli See Pic
20.22-03-2016LohjungNo work due to manpower unavailabilityAshish KumarJEUEAP-T GMVN Chamoli See Pic