Hybrid Huts at Lohjung
Agreement signed
|
Project: |
UEAP-T |
UID: |
7212 |
Sanction Cost: |
109.57 lakh |
Length:
|
KM. |
District: |
Chamoli |
Block: |
Dewal |
Constituency: |
Tharali |
Circle: |
GMVN |
DEA: |
GMVN Chamoli |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
Hybrid Huts |
|
Procurement: |
Package No.: 2203
Package Name: 
UK/UEAP-T(GMVN)/DDN/05
Tender Date: 12-06-2014
Current Status: Agreement signed
Achieved on Date: 01-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/05
Contractor Name: ACME Clean Tech Solutions Ltd
|
Start Date: 10-10-2014
Intended Completion Date: 30-06-2017
Original End Date: 09-04-2016 |
Total Bond Cost: 44096194.28 (440.96 lakh)
Variation Cost: 6605615.89 (66.06 lakh) Hence Total Bond Cost is 50701810.17 (507.02 lakh)
|
Sub Project Cost: 109.57 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4034784 for +183 days
LD Analysis for Milestone2: calculated LD is Rs 13868192 for 629 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 1.00 Job | 1.78 | 01-03-2015 | 15-05-2015 | 1.00 Job | 0.95 Job | 2.35 | 1.69 | 2. | Foundation and Plinth Work | 1.00 Job | 11.50 | 16-03-2015 | 31-05-2015 | 1.00 Job | 1.00 Job | 15.98 | 11.50 | 3. | Structural Frame | 1.00 Job | 42.65 | 16-04-2015 | 15-08-2015 | 1.00 Job | 0.90 Job | 53.34 | 38.38 | 4. | Doors & Windows | 1.00 Job | 3.09 | 16-08-2015 | 15-09-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 | 5. | Water Supply and Sanitary work | 1.00 Job | 2.92 | 01-09-2015 | 30-09-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 | 6. | Electrification Works | 1.00 Job | 1.05 | 01-09-2015 | 30-09-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 | 7. | Other Allied Works & Finishing Work | 1.00 Job | 3.22 | 16-08-2015 | 30-11-2015 | 1.00 Job | 0.20 Job | 0.9 | 0.64 | 8. | Furnishing Work | 1.00 Job | 5.75 | 01-12-2015 | 31-12-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
71.96 |
|
72.56 |
52.21 |
|
Remarks:
No Remarks
Work Program Made On:
07-01-2015 } ?>
Updation of work program on:
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
No Financial Progress.
|
Advance Amount: 210.99 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 210.99 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
PUC vehicles
Environment & Social Compliances(Sub Project level):
project information board |
Detailed report of this subproject
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 93.44 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 47 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 18-10-2016 | Lohajung | Finishing work in progress | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
2. | 18-10-2016 | Lohajung | Approch staircase work to hybrid hut is in progress | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
3. | 18-10-2016 | Lohajung | Floor tile work completed | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
4. | 18-10-2016 | Lohajung | Material viz OHT structure, tiles, wall paneling material, false ceiling etc transported at site. | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
5. | 07-09-2016 | lohajung | stair work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
6. | 07-09-2016 | lohajung | interior work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
7. | 07-09-2016 | lohajung | interior work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
8. | 02-08-2016 | Lgfs hut tilwara | Finishing of lgfs hut is in progress. | Gambhir Singh | DPM | PIU UEAP Tourism | See Pic |
9. | 24-06-2016 | Lohajung | Hybrid Hut at Lohajung | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
10. | 24-06-2016 | Lohajung | False ceiling work at lohajung, no labourers present at site | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
11. | 22-06-2016 | Lohjung | False Ceiling work at Lohjung site. | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
12. | 23-03-2016 | Lohjung | No work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
13. | 23-03-2016 | Lohjung | No work in progress due to material not available | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
14. | 23-03-2016 | Lohjung | No work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
15. | 23-03-2016 | Lohjung | No work in progress last 7 days | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
16. | 22-03-2016 | Lohjung | No work in progress at site | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
17. | 22-03-2016 | Lohjung | No work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
18. | 22-03-2016 | Lohjung | No work in progress last 7 days | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
19. | 22-03-2016 | Lohjung | No work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
20. | 22-03-2016 | Lohjung | No work due to manpower unavailability | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
|
|