Hybrid Huts at Deval
Agreement signed
|
Project: |
UEAP-T |
UID: |
7211 |
Sanction Cost: |
92.24 lakh |
Length:
|
KM. |
District: |
Chamoli |
Block: |
Dewal |
Constituency: |
Tharali |
Circle: |
GMVN |
DEA: |
GMVN Chamoli |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
Hybrid Huts |
|
Procurement: |
Package No.: 2203
Package Name: 
UK/UEAP-T(GMVN)/DDN/05
Tender Date: 12-06-2014
Current Status: Agreement signed
Achieved on Date: 01-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/05
Contractor Name: ACME Clean Tech Solutions Ltd
|
Start Date: 10-10-2014
Intended Completion Date: 30-06-2017
Original End Date: 09-04-2016 |
Total Bond Cost: 44096194.28 (440.96 lakh)
Variation Cost: 6605615.89 (66.06 lakh) Hence Total Bond Cost is 50701810.17 (507.02 lakh)
|
Sub Project Cost: 92.24 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4034784 for +183 days
LD Analysis for Milestone2: calculated LD is Rs 13868192 for 629 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 1.00 Job | 1.78 | 01-02-2015 | 28-02-2015 | 1.00 Job | 0.70 Job | 1.73 | 1.24 | 2. | Foundation and Plinth Work | 1.00 Job | 11.50 | 16-02-2015 | 15-03-2015 | 1.00 Job | 1.00 Job | 15.98 | 11.50 | 3. | Structural Frame | 1.00 Job | 42.65 | 01-03-2015 | 30-04-2015 | 1.00 Job | 0.90 Job | 53.34 | 38.38 | 4. | Doors & Windows | 1.00 Job | 3.09 | 01-05-2015 | 31-05-2015 | 1.00 Job | 0.70 Job | 3 | 2.16 | 5. | Water Supply and Sanitary work | 1.00 Job | 2.92 | 16-05-2015 | 15-06-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 | 6. | Electrification Works | 1.00 Job | 1.05 | 16-05-2015 | 15-06-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 | 7. | Other Allied Works & Finishing Work | 1.00 Job | 3.22 | 01-05-2015 | 31-07-2015 | 1.00 Job | 0.20 Job | 0.9 | 0.64 | 8. | Furnishing Work | 1.00 Job | 5.75 | 01-08-2015 | 15-08-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
71.96 |
|
74.95 |
53.92 |
|
Remarks:
No Remarks
Work Program Made On:
07-01-2015 } ?>
Updation of work program on:
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-September-2015 | 11.13 lakh | 2. | 29-September-2015 | 0.21 lakh | 3. | 31-May-2016 | 5.17 lakh |
Total |
16.51 lakh |
% Payment | 17.9 % |
|
Advance Amount: 210.99 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 210.99 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
PUC vehicles
Environment & Social Compliances(Sub Project level):
project information board |
Detailed report of this subproject
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 94.04 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 59 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-12-2016 | deval | false ceiling work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
2. | 13-12-2016 | hybrid hut Dewal | wall panelling work in progress | Gambhir Singh | DPM | PIU UEAP Tourism | See Pic |
3. | 21-10-2016 | Deval | Wiring for MCB distribution box | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
4. | 18-10-2016 | Deval | False ceiling work in progress.. | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
5. | 18-10-2016 | Deval | Finishing work in progress | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
6. | 18-10-2016 | Deval | Hybrid hut at Deval | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
7. | 18-10-2016 | Deval | Tile work completed in complete hut. | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
8. | 18-10-2016 | Deval | Tile work completed | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
9. | 18-10-2016 | Deval | Wall paneling work in progress | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
10. | 08-09-2016 | deval | flooring work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
11. | 08-09-2016 | deval | flooring work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
12. | 08-09-2016 | deval | flooring work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
13. | 08-09-2016 | deval | finishing work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
14. | 21-06-2016 | Dewal | Approach stair to hybrid hut | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
15. | 21-06-2016 | Dewal | Plint protection work completed | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
16. | 21-06-2016 | Deval | False ceiling work at deval site | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
17. | 21-06-2016 | Dewal | False Ceiling work at dewal site | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
18. | 28-03-2016 | Deval | Fall ceiling work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
19. | 28-03-2016 | Deval | False ceiling work under progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
20. | 23-03-2016 | Deval | Fall ceiling work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
|
|