Hybrid Huts at Joshimath
Agreement signed
|
Project: |
UEAP-T |
UID: |
7209 |
Sanction Cost: |
92.56 lakh |
Length:
|
KM. |
District: |
Chamoli |
Block: |
Joshimath |
Constituency: |
Badrinath |
Circle: |
GMVN |
DEA: |
GMVN Chamoli |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
Hybrid Huts |
|
Procurement: |
Package No.: 2203
Package Name: 
UK/UEAP-T(GMVN)/DDN/05
Tender Date: 12-06-2014
Current Status: Agreement signed
Achieved on Date: 01-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/05
Contractor Name: ACME Clean Tech Solutions Ltd
|
Start Date: 10-10-2014
Intended Completion Date: 30-06-2017
Original End Date: 09-04-2016 |
Total Bond Cost: 44096194.28 (440.96 lakh)
Variation Cost: 6605615.89 (66.06 lakh) Hence Total Bond Cost is 50701810.17 (507.02 lakh)
|
Sub Project Cost: 92.56 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4034784 for +183 days
LD Analysis for Milestone2: calculated LD is Rs 13868192 for 629 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 1.00 Job | 1.78 | 01-02-2015 | 28-02-2015 | 1.00 Job | 0.95 Job | 2.34 | 1.69 | 2. | Foundation and Plinth Work | 1.00 Job | 11.50 | 16-02-2015 | 15-03-2015 | 1.00 Job | 0.95 Job | 15.18 | 10.93 | 3. | Structural Frame | 1.00 Job | 42.65 | 01-03-2015 | 30-04-2015 | 1.00 Job | 0.90 Job | 53.32 | 38.38 | 4. | Doors & Windows | 1.00 Job | 3.09 | 01-05-2015 | 31-05-2015 | 1.00 Job | 0.60 Job | 2.57 | 1.85 | 5. | Water Supply and Sanitary work | 1.00 Job | 2.94 | 16-05-2015 | 15-06-2015 | 1.00 Job | 0.30 Job | 1.23 | 0.88 | 6. | Electrification Works | 1.00 Job | 1.05 | 16-05-2015 | 15-06-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 | 7. | Other Allied Works & Finishing Work | 1.00 Job | 3.22 | 01-05-2015 | 31-07-2015 | 1.00 Job | 0.60 Job | 2.69 | 1.93 | 8. | Furnishing Work | 1.00 Job | 5.75 | 01-08-2015 | 15-08-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
71.98 |
|
77.34 |
55.66 |
|
Remarks:
No Remarks
Work Program Made On:
07-01-2015 } ?>
Updation of work program on:
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-September-2015 | 9.29 lakh | 2. | 29-September-2015 | 0.21 lakh | 3. | 31-October-2015 | 6.92 lakh | 4. | 31-May-2016 | 81.25 lakh |
Total |
97.67 lakh |
% Payment | 105.52 % |
|
Advance Amount: 210.99 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 210.99 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 92.31 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 70 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-12-2016 | Joshimath | Sanitary fixtures installing work is in progress | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
2. | 17-09-2016 | joshimath | furnishing material in site | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
3. | 16-09-2016 | Joshimath | Furniture transported at site. | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
4. | 15-09-2016 | Joshimath | Room interior | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
5. | 25-06-2016 | Pandukeshwar | Erection work in left most hybrid hut | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
6. | 24-06-2016 | Joshimath | Fixing of electrical switch board in hybrid hut at joshimath site.. | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
7. | 24-06-2016 | Joshimath | 5 watt LED Ceiling downlighter fixed in hybrid hut | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
8. | 24-06-2016 | Joshimath | Balcony / entrance false ceiling | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
9. | 24-06-2016 | Joshimath | Key switch fixed in hybrid hut at joshimath... | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
10. | 24-06-2016 | Joshimath | Tiles and hand rail in balcony | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
11. | 24-06-2016 | Joshimath | Granite fixing in staircase | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
12. | 24-06-2016 | Joshimath | Internal finishing work in rooms of hybrid hut | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
13. | 21-05-2016 | Joshimath | Laminated panel work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
14. | 21-05-2016 | Joshimath | Laminated panels work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
15. | 13-05-2016 | Joshimath | Staircase railing | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
16. | 13-05-2016 | Joshimath | Tile work in progress | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
17. | 13-05-2016 | Joshimath | Outer floor tiles work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
18. | 08-05-2016 | Joshimath | Ground floor Tiles work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
19. | 07-05-2016 | Joshimath | Tiles work progress in ground floor lobby | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
20. | 07-05-2016 | Joshimath | Railings work in progress in stairs | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
|
|