Hybrid Huts at Pandukeshwar
Agreement signed
|
Project: |
UEAP-T |
UID: |
7208 |
Sanction Cost: |
179.56 lakh |
Length:
|
KM. |
District: |
Chamoli |
Block: |
Joshimath |
Constituency: |
Badrinath |
Circle: |
GMVN |
DEA: |
GMVN Chamoli |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
Hybrid Huts |
|
Procurement: |
Package No.: 2203
Package Name: 
UK/UEAP-T(GMVN)/DDN/05
Tender Date: 12-06-2014
Current Status: Agreement signed
Achieved on Date: 01-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/05
Contractor Name: ACME Clean Tech Solutions Ltd
|
Start Date: 10-10-2014
Intended Completion Date: 30-06-2017
Original End Date: 09-04-2016 |
Total Bond Cost: 44096194.28 (440.96 lakh)
Variation Cost: 6605615.89 (66.06 lakh) Hence Total Bond Cost is 50701810.17 (507.02 lakh)
|
Sub Project Cost: 179.56 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4034784 for +183 days
LD Analysis for Milestone2: calculated LD is Rs 13868192 for 629 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 1.00 Job | 1.78 | 16-02-2015 | 30-04-2015 | 1.00 Job | 0.55 Job | 0.7 | 0.98 | 2. | Foundation and Plinth Work | 1.00 Job | 23.01 | 01-03-2015 | 31-05-2015 | 1.00 Job | 1.00 Job | 16.49 | 23.01 | 3. | Structural Frame | 1.00 Job | 85.30 | 16-03-2015 | 31-07-2015 | 1.00 Job | 0.70 Job | 42.78 | 59.71 | 4. | Doors & Windows | 1.00 Job | 6.18 | 01-08-2015 | 31-08-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 | 5. | Water Supply and Sanitary work | 1.00 Job | 5.88 | 01-08-2015 | 15-09-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 | 6. | Electrification Works | 1.00 Job | 2.09 | 01-08-2015 | 15-09-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 | 7. | Other Allied Works & Finishing Work | 1.00 Job | 5.78 | 16-07-2015 | 31-10-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 | 8. | Furnishing Work | 1.00 Job | 9.55 | 01-11-2015 | 30-11-2015 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
139.57 |
|
59.97 |
83.7 |
|
Remarks:
No Remarks
Work Program Made On:
06-01-2015 } ?>
Updation of work program on:
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
No Financial Progress.
|
Advance Amount: 210.99 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 210.99 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 95.91 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 65 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-04-2017 | pandukeshwar | interiors work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
2. | 05-03-2017 | Pandukeshwar | Hybrid hut at Pandukeshwar | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
3. | 03-03-2017 | pandukeshwar | finishing work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
4. | 03-03-2017 | pandukeshwar | furniture supply | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
5. | 30-01-2017 | Pandukeshwar | Hybrid hut at Pandukeshwar | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
6. | 27-01-2017 | Pandukeshwar | Wall paneling work is in progress | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
7. | 27-01-2017 | Pandukeshwar | Furniture transported at site | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
8. | 30-12-2016 | Pandukeshwar | Hybrid hut in Pandukeshwar | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
9. | 29-12-2016 | Pandukeshwar | Beds, wardrobe & mattress transported at site | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
10. | 29-12-2016 | Pandukeshwar | Wall paneling work | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
11. | 23-12-2016 | pandukeshwar | finishing work in progress | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
12. | 23-12-2016 | pandukeshwar | furniture transported in site | Ashish Kumar | JE | UEAP-T GMVN Chamoli | See Pic |
13. | 07-12-2016 | Pandukeshwar | Finishing work is in progress | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
14. | 07-12-2016 | Pandukeshwar | Breast wall work is in progress | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
15. | 22-10-2016 | Pandukeshwar | Exterior finishing work is in progress. | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
16. | 22-10-2016 | Pandukeshwar | Wall paneling work is in progress. | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
17. | 22-10-2016 | Pandukeshwar | False ceiling work in toilet | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
18. | 22-10-2016 | Pandukeshwar | Left side hut exterior finishing work in progress. | Rajat Rajput | AE | UEAP-T GMVN Chamoli | See Pic |
19. | 22-10-2016 | Pandukeshwar | Fixing of downlighters | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
20. | 22-10-2016 | Pandukeshwar | Finishing work in progress | Ashish Aswal | AE | UEAP-T GMVN Rudraprayag | See Pic |
|
|