Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Hybrid Huts at Harsil Work Completed
Project: UEAP-T UID: 7206 Sanction Cost: 40.18  lakh Length: KM.
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle: GMVN
DEA: GMVN Uttarkashi DSC: DSC Scope: Design & Supervision Type: Hybrid Huts
Procurement:
Package No.: 2201        Package Name:  UK/UEAP-T(GMVN)/DDN/03        Tender Date: 12-06-2014        Current Status: Agreement signed        Achieved on Date: 01-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/03      Contractor Name: ACME Clean Tech Solutions Ltd
Start Date:  10-10-2014      Intended Completion Date:  30-06-2017      Original End Date:  09-04-2016
Total Bond Cost: 30317675.03 (303.18 lakh)        Variation Cost: 4498797.22 (44.99 lakh)    Hence Total Bond Cost is   34816472.25 (348.16 lakh) 
Sub Project Cost: 40.18  lakh       
LD Analysis for Milestone1: calculated LD is Rs 2774097 for 183 days        LD Analysis for Milestone2: calculated LD is Rs 9535011 for 629 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development1.00 Job1.8301-04-201515-05-20151.00 Job1.00 Job5.851.83
2.Foundation and Plinth Work1.00 Job4.7416-04-201530-06-20151.00 Job1.00 Job15.134.74
3.Structural Frame1.00 Job16.6901-04-201531-08-20151.00 Job1.00 Job53.2216.69
4.Doors & Windows 1.00 Job1.2001-09-201515-09-20151.00 Job1.00 Job3.821.20
5.Water Supply and Sanitary work 1.00 Job1.5401-09-201515-10-20151.00 Job1.00 Job4.921.54
6.Electrification Works1.00 Job0.4201-09-201515-10-20151.00 Job1.00 Job1.350.42
7.Other Allied Works & Finishing Work 1.00 Job1.4016-08-201530-11-20151.00 Job1.00 Job4.461.40
8.Furnishing Work1.00 Job3.5301-12-201515-12-20151.00 Job1.00 Job11.263.53
Total Amount: 31.35 100   31.35
Remarks: No Remarks       Work Program Made On: 16-01-2015        Updation of work program on:       
Work Program Status:Task Finish.
Financial Progress
No Financial Progress.
Advance Amount:  114.74  lakh        Recovered Amount:  114.74  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 89.71
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 14
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-09-2017Hybrid Hut at HarsilCeiling and Panelling work have been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
2.02-09-2017Hybrid Hut at HarsilWork of fixing of door shutter has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
3.02-09-2017Hybrid Hut at HarsilBeds and linen have been placedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
4.02-09-2017Hybrid Hut at HarsilWork of toilet has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
5.28-09-2016Internal electrification work is in progressHybrid Hut at HarsilSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
6.28-09-2016Hybrid Hut at HarsilElectrification work is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
7.28-09-2016Hybrid Hut at HarsilPlumbing work is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
8.09-05-2016HarsilConst of hybrid but at HarsilSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
9.09-05-2016HarsilConst of hybrid but at HarsilSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
10.09-01-2016HarsilRoof,floor and wall panels fitting work in progressBrij Mohan AswalJEUEAP-T GMVN Uttarkashi See Pic
11.09-01-2016HarsilHutBrij Mohan AswalJEUEAP-T GMVN Uttarkashi See Pic
12.06-11-2015HarsilHybrid hut foundation up to plinth has been completeSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
13.06-11-2015HarsilHybrid hut foundation up to plinth has been completefSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
14.03-08-2015Hybrid hut foundationSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic