Hybrid Huts at Harsil
Work Completed
|
Project: |
UEAP-T |
UID: |
7206 |
Sanction Cost: |
40.18 lakh |
Length:
|
KM. |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
GMVN |
DEA: |
GMVN Uttarkashi |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
Hybrid Huts |
|
Procurement: |
Package No.: 2201
Package Name: 
UK/UEAP-T(GMVN)/DDN/03
Tender Date: 12-06-2014
Current Status: Agreement signed
Achieved on Date: 01-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/03
Contractor Name: ACME Clean Tech Solutions Ltd
|
Start Date: 10-10-2014
Intended Completion Date: 30-06-2017
Original End Date: 09-04-2016 |
Total Bond Cost: 30317675.03 (303.18 lakh)
Variation Cost: 4498797.22 (44.99 lakh) Hence Total Bond Cost is 34816472.25 (348.16 lakh)
|
Sub Project Cost: 40.18 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2774097 for 183 days
LD Analysis for Milestone2: calculated LD is Rs 9535011 for 629 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 1.00 Job | 1.83 | 01-04-2015 | 15-05-2015 | 1.00 Job | 1.00 Job | 5.85 | 1.83 | 2. | Foundation and Plinth Work | 1.00 Job | 4.74 | 16-04-2015 | 30-06-2015 | 1.00 Job | 1.00 Job | 15.13 | 4.74 | 3. | Structural Frame | 1.00 Job | 16.69 | 01-04-2015 | 31-08-2015 | 1.00 Job | 1.00 Job | 53.22 | 16.69 | 4. | Doors & Windows | 1.00 Job | 1.20 | 01-09-2015 | 15-09-2015 | 1.00 Job | 1.00 Job | 3.82 | 1.20 | 5. | Water Supply and Sanitary work | 1.00 Job | 1.54 | 01-09-2015 | 15-10-2015 | 1.00 Job | 1.00 Job | 4.92 | 1.54 | 6. | Electrification Works | 1.00 Job | 0.42 | 01-09-2015 | 15-10-2015 | 1.00 Job | 1.00 Job | 1.35 | 0.42 | 7. | Other Allied Works & Finishing Work | 1.00 Job | 1.40 | 16-08-2015 | 30-11-2015 | 1.00 Job | 1.00 Job | 4.46 | 1.40 | 8. | Furnishing Work | 1.00 Job | 3.53 | 01-12-2015 | 15-12-2015 | 1.00 Job | 1.00 Job | 11.26 | 3.53 |
Total Amount: |
31.35 |
|
100 |
31.35 |
|
Remarks:
No Remarks
Work Program Made On:
16-01-2015 } ?>
Updation of work program on:
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
No Financial Progress.
|
Advance Amount: 114.74 lakh
Recovered Amount: 114.74 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 89.71 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 14 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-09-2017 | Hybrid Hut at Harsil | Ceiling and Panelling work have been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
2. | 02-09-2017 | Hybrid Hut at Harsil | Work of fixing of door shutter has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
3. | 02-09-2017 | Hybrid Hut at Harsil | Beds and linen have been placed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
4. | 02-09-2017 | Hybrid Hut at Harsil | Work of toilet has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
5. | 28-09-2016 | Internal electrification work is in progress | Hybrid Hut at Harsil | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
6. | 28-09-2016 | Hybrid Hut at Harsil | Electrification work is in progress | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
7. | 28-09-2016 | Hybrid Hut at Harsil | Plumbing work is in progress | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
8. | 09-05-2016 | Harsil | Const of hybrid but at Harsil | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
9. | 09-05-2016 | Harsil | Const of hybrid but at Harsil | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
10. | 09-01-2016 | Harsil | Roof,floor and wall panels fitting work in progress | Brij Mohan Aswal | JE | UEAP-T GMVN Uttarkashi | See Pic |
11. | 09-01-2016 | Harsil | Hut | Brij Mohan Aswal | JE | UEAP-T GMVN Uttarkashi | See Pic |
12. | 06-11-2015 | Harsil | Hybrid hut foundation up to plinth has been complete | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
13. | 06-11-2015 | Harsil | Hybrid hut foundation up to plinth has been completef | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
14. | 03-08-2015 | | Hybrid hut foundation | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
|
|