Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Hybrid Huts at Phoolchatti Work Completed
Project: UEAP-T UID: 7205 Sanction Cost: 73.77  lakh Length: KM.
District: Uttarkashi Block: Naugaon Constituency: Yamunotri Circle: GMVN
DEA: GMVN Uttarkashi DSC: DSC Scope: Design & Supervision Type: Hybrid Huts
Procurement:
Package No.: 2201        Package Name:  UK/UEAP-T(GMVN)/DDN/03        Tender Date: 12-06-2014        Current Status: Agreement signed        Achieved on Date: 01-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/03      Contractor Name: ACME Clean Tech Solutions Ltd
Start Date:  10-10-2014      Intended Completion Date:  30-06-2017      Original End Date:  09-04-2016
Total Bond Cost: 30317675.03 (303.18 lakh)        Variation Cost: 4498797.22 (44.99 lakh)    Hence Total Bond Cost is   34816472.25 (348.16 lakh) 
Sub Project Cost: 73.77  lakh       
LD Analysis for Milestone1: calculated LD is Rs 2774097 for 183 days        LD Analysis for Milestone2: calculated LD is Rs 9535011 for 629 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development1.00 Job1.8301-04-201515-05-20151.00 Job1.00 Job3.131.83
2.Foundation and Plinth Work1.00 Job9.4916-04-201530-06-20151.00 Job1.00 Job16.219.49
3.Structural Frame1.00 Job33.3701-04-201531-08-20151.00 Job1.00 Job57.0333.37
4.Doors & Windows 1.00 Job2.3901-09-201515-09-20151.00 Job1.00 Job4.092.39
5.Water Supply and Sanitary work 1.00 Job3.0801-09-201515-10-20151.00 Job1.00 Job5.273.08
6.Electrification Works1.00 Job0.8401-09-201515-10-20151.00 Job1.00 Job1.440.84
7.Other Allied Works & Finishing Work 1.00 Job2.4416-08-201515-12-20151.00 Job1.00 Job4.172.44
8.Furnishing Work1.00 Job5.0716-12-201515-01-20161.00 Job1.00 Job8.665.07
Total Amount: 58.51 100   58.51
Remarks: No Remarks       Work Program Made On: 16-01-2015        Updation of work program on:       
Work Program Status:Task Finish.
Financial Progress
No Financial Progress.
Advance Amount:  114.74  lakh        Recovered Amount:  114.74  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 89.79
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 55
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-09-2017Hybrid Hut at PhoolchattiSite Development work has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
2.02-09-2017Hybrid Hut at PhoolchattiHybrid Hut at PhoolchattiSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
3.02-09-2017Hybrid HutWork of Hybrid Hut has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
4.29-07-2017Hybrid Hut at PhoolchattiWork of fixing of doors and windows has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
5.29-07-2017Hybrid Hut at PhoolchattiWork of fixing of electric fixtures has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
6.29-07-2017Hybrid Hut at PhoolchattiWork of Installation of beds including curtains has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
7.29-07-2017Hybrid Hut at PhoolchattiToilet work including water connection has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
8.27-06-2017Hybrid Hut PhoolchattiWork of toilets has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
9.27-06-2017Hybrid Hut PhoolchattiVitrified tiles in flooring has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
10.27-06-2017Hybrid Hut PhoolchattiWork of fixing of door shutter has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
11.27-06-2017Hybrid Hut PhoolchattiPlacing of Furniture is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
12.15-04-2017Hybrid Hut at PhoolchattiBeds, wardrobes and mattress has been transported to siteSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
13.15-04-2017Hybrid Hut at PhoolchattiVitrified tiles in flooring is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
14.15-04-2017Hybrid Hut at PhoolchattiWork of ceilng and Panelling is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
15.03-03-2017Phoolchatti, hybrid hutPhoolchatti, hybrid hutVijendra Prem Kumar TamtaAEUEAP-T KMVN Pithoragarh See Pic
16.03-03-2017Phoolchatti, PVC ceilingPhoolchatti, Hybrid hutVijendra Prem Kumar TamtaAEUEAP-T KMVN Pithoragarh See Pic
17.03-03-2017Phoolchatti, hybrid hutPhoolchattiVijendra Prem Kumar TamtaAEUEAP-T KMVN Pithoragarh See Pic
18.13-12-2016Hybrid Hut at PhoolchattiInternal wiring work is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
19.13-12-2016Hybrid Hut at PhoolchattiFrame work for paneling is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
20.13-12-2016Hybrid Hut at PhoolchattiCeiling work is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic