Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Hybrid Huts at Barkot Work Completed
Project: UEAP-T UID: 7204 Sanction Cost: 73.77  lakh Length: KM.
District: Uttarkashi Block: Naugaon Constituency: Yamunotri Circle: GMVN
DEA: GMVN Uttarkashi DSC: DSC Scope: Design & Supervision Type: Hybrid Huts
Procurement:
Package No.: 2201        Package Name:  UK/UEAP-T(GMVN)/DDN/03        Tender Date: 12-06-2014        Current Status: Agreement signed        Achieved on Date: 01-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/03      Contractor Name: ACME Clean Tech Solutions Ltd
Start Date:  10-10-2014      Intended Completion Date:  30-06-2017      Original End Date:  09-04-2016
Total Bond Cost: 30317675.03 (303.18 lakh)        Variation Cost: 4498797.22 (44.99 lakh)    Hence Total Bond Cost is   34816472.25 (348.16 lakh) 
Sub Project Cost: 73.77  lakh       
LD Analysis for Milestone1: calculated LD is Rs 2774097 for 183 days        LD Analysis for Milestone2: calculated LD is Rs 9535011 for 629 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Site Development1.00 Job1.8301-02-201515-03-20151.00 Job1.00 Job3.131.83
2.Foundation and Plinth Work1.00 Job9.4916-02-201515-04-20151.00 Job1.00 Job16.219.49
3.Structural Frame1.00 Job33.3701-03-201530-04-20151.00 Job1.00 Job57.0333.37
4.Doors & Windows 1.00 Job2.3901-05-201515-05-20151.00 Job1.00 Job4.092.39
5.Water Supply and Sanitary work 1.00 Job3.0801-05-201515-06-20151.00 Job1.00 Job5.273.08
6.Electrification Works1.00 Job0.8401-05-201515-06-20151.00 Job1.00 Job1.440.84
7.Other Allied Works & Finishing Work 1.00 Job2.4416-04-201531-08-20151.00 Job1.00 Job4.172.44
8.Furnishing Work1.00 Job5.0701-09-201515-09-20151.00 Job1.00 Job8.665.07
Total Amount: 58.51 100   58.51
Remarks: No Remarks       Work Program Made On: 16-01-2015        Updation of work program on:       
Work Program Status:Task Finish.
Financial Progress
No Financial Progress.
Advance Amount:  114.74  lakh        Recovered Amount:  114.74  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 90.75
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 47
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-07-2017Hybrid Huts at PurolaWork of fixing of doors shutter has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
2.29-07-2017Hybrid Hut at PurolaPlacing of beds mattress and curtains has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
3.29-07-2017Hybrid Hut at BarkotWork of fixing of doors shutter has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
4.29-07-2017Hybrid Hut at BarkotWork of placing of beds,mattress and curtains has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
5.29-07-2017Hybrid Hut at BarkotWork of fixing of electric fixtures has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
6.29-07-2017Hybrid Hut at BarkotWork of fixing of sanitary fixtures in toilet has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
7.27-06-2017Hybrid Hut BarkotWork of fixing of door shutter has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
8.27-06-2017Hybrid Hut BarkotPlacing of Furniture is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
9.27-06-2017Hybrid Hut BarkotWork of toilets has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
10.21-11-2016Hybrid hut Barkotwall paneling , pvc ceiling and tiling work in progress.Gambhir SinghDPMPIU UEAP Tourism See Pic
11.11-11-2016Hybrid Hut at BarkotWork of Retaining Wall is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
12.10-11-2016Hybrid Hut at BarkotFixing of toilet door shutter has been completedSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
13.10-11-2016Hybrid Hut at BarkotVitrified tiles and ceiling materials have been procured at siteSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
14.10-10-2016BarkotPublic consultationBrij Mohan AswalJEUEAP-T GMVN Uttarkashi See Pic
15.30-08-2016Hybrid Hut BarkotPath way & Plinth protection work are in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
16.30-08-2016Hybrid Hut BarkotAluminium Doors & Windows work is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
17.30-08-2016Hybrid Hut BarkotRetaining Wall work is in progressSanjay GuptaProcurement OfficerUEAP-T GMVN See Pic
18.26-07-2016BarkotConst. Of hybrid hut at Barkot.Brij Mohan AswalJEUEAP-T GMVN Uttarkashi See Pic
19.11-07-2016Barkot.Const. Of hybrid hutBrij Mohan AswalJEUEAP-T GMVN Uttarkashi See Pic
20.26-06-2016BarkotConst of hybrid hut at Barkot.Brij Mohan AswalJEUEAP-T GMVN Uttarkashi See Pic