FRP Huts at Barsu
Work Completed
|
Project: |
UEAP-T |
UID: |
7202 |
Sanction Cost: |
68.03 lakh |
Length:
|
KM. |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
GMVN |
DEA: |
GMVN Uttarkashi |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
FRP Huts |
|
Procurement: |
Package No.: 2201
Package Name: 
UK/UEAP-T(GMVN)/DDN/03
Tender Date: 12-06-2014
Current Status: Agreement signed
Achieved on Date: 01-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-T(GMVN)/DDN/03
Contractor Name: ACME Clean Tech Solutions Ltd
|
Start Date: 10-10-2014
Intended Completion Date: 30-06-2017
Original End Date: 09-04-2016 |
Total Bond Cost: 30317675.03 (303.18 lakh)
Variation Cost: 4498797.22 (44.99 lakh) Hence Total Bond Cost is 34816472.25 (348.16 lakh)
|
Sub Project Cost: 68.03 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2774097 for 183 days
LD Analysis for Milestone2: calculated LD is Rs 9535011 for 629 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Site Development | 1.00 Job | 1.85 | 01-03-2015 | 30-04-2015 | 1.00 Job | 1.00 Job | 3.22 | 1.85 | 2. | Foundation and Plinth Work | 1.00 Job | 4.39 | 16-03-2015 | 31-05-2015 | 1.00 Job | 1.00 Job | 7.66 | 4.39 | 3. | Structural Frame | 1.00 Job | 42.53 | 01-04-2015 | 15-06-2015 | 1.00 Job | 1.00 Job | 74.22 | 42.53 | 4. | Water Supply and Sanitary work | 1.00 Job | 3.47 | 16-06-2015 | 31-07-2015 | 1.00 Job | 1.00 Job | 6.06 | 3.47 | 5. | Electrification Works | 1.00 Job | 1.20 | 16-06-2015 | 31-07-2015 | 1.00 Job | 1.00 Job | 2.1 | 1.20 | 6. | Other Allied Works & Finishing Work | 1.00 Job | 1.07 | 01-06-2015 | 31-08-2015 | 1.00 Job | 1.00 Job | 1.87 | 1.07 | 7. | Furnishing Work | 1.00 Job | 2.80 | 01-09-2015 | 15-09-2015 | 1.00 Job | 1.00 Job | 4.88 | 2.80 |
Total Amount: |
57.31 |
|
100 |
57.31 |
|
Remarks:
No Remarks
Work Program Made On:
16-01-2015 } ?>
Updation of work program on:
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-October-2015 | 4.39 lakh |
Total |
4.39 lakh |
% Payment | 6.45 % |
|
Advance Amount: 114.74 lakh
Recovered Amount: 114.74 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 90.08 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 64 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-09-2017 | Hybrid Hut at Barsu | Ceiling and Panelling work have been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
2. | 02-09-2017 | Hybrid Hut at Barsu | Beds and linen have been placed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
3. | 02-09-2017 | Hybrid Hut at Barsu | Work of fixing of Aluminium doors shutter has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
4. | 02-09-2017 | Hybrid Hut at Barsu | Work of Hybrid Huts have been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
5. | 06-07-2017 | Hybrid Hut at Barsu | Painting work on railing at Barsu | Vijendra Prem Kumar Tamta | AE | UEAP-T GMVN Uttarkashi | See Pic |
6. | 06-07-2017 | Hybrid Hut at Barsu | Tiling work in progress at Hybrid Hut, Barsu | Vijendra Prem Kumar Tamta | AE | UEAP-T GMVN Uttarkashi | See Pic |
7. | 27-06-2017 | Hybrid Hut Barsu | Work of fixing of Aluminum Doors and windows has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
8. | 27-06-2017 | Hybrid Hut Barsu | Work of internal plumbing is in progress | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
9. | 27-06-2017 | Hybrid Hut Barsu | Work of fixing of TV Console is in progress | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
10. | 14-04-2017 | Hybrid Hut at Barsu | Work of vitrified tiles in flooring and Panelling is in progress | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
11. | 14-04-2017 | Hybrid Hut at Barsu | The work of ceilng and Panelling is in progress | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
12. | 14-04-2017 | Hybrid Hut Barsu | Internal electrification work is in progress | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
13. | 14-04-2017 | Hybrid Hut at Barsu | Work of Bio Digester has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
14. | 14-04-2017 | Hybrid Hut at Barsu | Internal plumbing work is in progress | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
15. | 23-12-2016 | Hybrid Hut at Barsu | Beds, mattress and wardrobes has been transported to site | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
16. | 23-12-2016 | Hybrid Hut at Barsu | Vitrified tiles in flooring in 1 no Hut has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
17. | 23-12-2016 | Hybrid Hut at Barsu | Fixing of frames for paneling in 6 no Hut is in progress | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
18. | 23-12-2016 | Hybrid Hut at Barsu | Ceiling work has been completed | Sanjay Gupta | Procurement Officer | UEAP-T GMVN | See Pic |
19. | 20-11-2016 | Barsu, Uttarkashi | Electrical wiring under process at Barsu | Vijendra Prem Kumar Tamta | AE | UEAP-T KMVN Pithoragarh | See Pic |
20. | 20-11-2016 | Barsu, Uttarkashi | Electrical wiring under process at Barsu, Uttarkashi | Vijendra Prem Kumar Tamta | AE | UEAP-T KMVN Pithoragarh | See Pic |
|
|