Srinagar-And-Pauri-Water-Supply-Scheme Phase1
Work Completed
|
Project: |
UEAP-WS |
UID: |
7109 |
Sanction Cost: |
3047.00 lakh |
Length:
|
KM. |
District: |
Pauri |
Block: |
Khirsu |
Constituency: |
Srinagar |
Circle: |
|
DEA: |
DEA WS Srinagar And Pauri |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
Not known |
|
Procurement: |
Package No.: 2109
Package Name: 
UK/UEAP-WSS/UJS/GW/02
Tender Date: 10-10-2014
Current Status: Agreement signed
Achieved on Date: 05-12-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/02
Contractor Name: RK Engineers Sales Ltd
|
Start Date: 19-01-2015
Intended Completion Date: 30-06-2017
Original End Date: 18-07-2016 |
Total Bond Cost: 333299052 (3332.99 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 30330300 for +182 days
LD Analysis for Milestone2: calculated LD is Rs 59327400 for 356 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Infiltration Well/Tube Well | 3.00 No | 384.00 | 01-01-2015 | 01-03-2016 | 3.00 No | 3.00 No | 12.68 | 384.00 | 2. | Pump House | 1.00 No | 24.65 | 01-04-2015 | 30-09-2015 | 1.00 No | 1.00 No | 0.81 | 24.65 | 3. | GLSRs | 3.00 No | 190.00 | 01-05-2015 | 31-12-2015 | 3.00 No | 3.00 No | 6.28 | 190.00 | 4. | Rehabilitation of WTP/HFRF | 3.00 No | 247.85 | 01-10-2015 | 31-12-2015 | 3.00 No | 3.00 No | 8.19 | 247.85 | 5. | Pipe Line Works with (Main/ Distribution) | 37400.00 m | 1000.00 | 01-03-2015 | 28-02-2016 | 37400.00 m | 37400.00 m | 33.03 | 1000.00 | 6. | Electrical and Instrumentation work | 7.00 No | 795.61 | 01-04-2015 | 31-03-2016 | 7.00 No | 7.00 No | 26.28 | 795.61 | 7. | Office Building | 1.00 No | 59.20 | 01-03-2015 | 31-12-2015 | 1.00 No | 1.00 No | 1.96 | 59.20 | 8. | Env. Man & Moni Plan | 1.00 Job | 5.61 | 01-02-2015 | 31-07-2016 | 1.00 Job | 1.00 Job | 0.19 | 5.61 | 9. | Provisional Sum | 1.00 Job | 321.00 | 01-01-2015 | 31-07-2016 | 1.00 Job | 1.00 Job | 10.6 | 321.00 |
Total Amount: |
3027.92 |
|
100 |
3027.92 |
|
Remarks:
No Remarks
Work Program Made On:
30-03-2015 } ?>
Updation of work program on:
30-03-2015
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-September-2015 | 98.85 lakh | 2. | 30-October-2015 | 153.09 lakh | 3. | 18-December-2015 | 120.08 lakh | 4. | 17-March-2016 | 259.06 lakh | 5. | 22-March-2016 | 131.20 lakh | 6. | 17-June-2016 | 124.00 lakh | 7. | 25-June-2016 | 107.53 lakh | 8. | 24-September-2016 | 52.66 lakh | 9. | 26-October-2016 | 172.30 lakh | 10. | 07-January-2017 | 447.06 lakh | 11. | 14-March-2017 | 76.28 lakh | 12. | 29-April-2017 | 123.42 lakh | 13. | 22-June-2017 | 450.37 lakh | 14. | 28-June-2017 | 262.72 lakh | 15. | 24-August-2017 | 155.70 lakh |
Total |
2734.32 lakh |
% Payment |
82.03 % |
|
Advance Amount: 479.41 lakh
Recovered Amount: 479.41 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 4 No. of Test Done : 4 No. of Test Passed : 4 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.01 |
Number of Notice(s) issued: 181 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 152 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-03-2017 | Raw water | Raw water | Ashok Negi | DPM | PIU WS | See Pic |
2. | 28-03-2017 | Panel room | Raw water | Ashok Negi | DPM | PIU WS | See Pic |
3. | 28-03-2017 | Raw water pumphouse | Finishing | Ashok Negi | DPM | PIU WS | See Pic |
4. | 28-03-2017 | Raw water p house | Finishing | Ashok Negi | DPM | PIU WS | See Pic |
5. | 28-03-2017 | Paving area | Finishing | Ashok Negi | DPM | PIU WS | See Pic |
6. | 28-03-2017 | Wtp | Finishing | Ashok Negi | DPM | PIU WS | See Pic |
7. | 28-03-2017 | Scada room | Finishing | Ashok Negi | DPM | PIU WS | See Pic |
8. | 04-03-2017 | Scada Rm. At WTP | Final touch is in progress | Dilip Chand Gupta | Construction Supervisor | DSC WS ADB Pauri | See Pic |
9. | 25-01-2017 | Tubewell | Pumps installation | Ashok Negi | DPM | PIU WS | See Pic |
10. | 25-01-2017 | Wtp | Repair works | Ashok Negi | DPM | PIU WS | See Pic |
11. | 24-01-2017 | 500kl sump | inspection being mad by the seanior officls of pmu.dsc staff membr concerned contractors staff membar at sringar | Rakesh Sharma | Contractor Project Manager | UEAP-WS Pauri | See Pic |
12. | 24-01-2017 | 500kl and tubewell area | Inspection being carried on by senior officals . Dse staff member and concerned contractors staff members | Parveen Saini | AE | UEAP UJS Pauri | See Pic |
13. | 21-01-2017 | Tuble srinager | Valve fixing | Parveen Saini | AE | UEAP UJS Pauri | See Pic |
14. | 20-01-2017 | raw water pump house | landscaping at raw water pump house sringar | Rakesh Sharma | Contractor Project Manager | UEAP-WS Pauri | See Pic |
15. | 17-01-2017 | clear water pump house | 6mld clear water pump house | Rakesh Sharma | Contractor Project Manager | UEAP-WS Pauri | See Pic |
16. | 16-01-2017 | raw water pump house | raw water pump house wall work | Rakesh Sharma | Contractor Project Manager | UEAP-WS Pauri | See Pic |
17. | 04-01-2017 | Pump house | Finishing | Ashok Negi | DPM | PIU WS | See Pic |
18. | 04-01-2017 | 500 kl sump | Finishing | Ashok Negi | DPM | PIU WS | See Pic |
19. | 07-12-2016 | sringar automation work | automation work in. progress | Rakesh Sharma | Contractor Project Manager | UEAP-WS Pauri | See Pic |
20. | 06-12-2016 | sringar rbf site | pump house and 500kl sump | Rakesh Sharma | Contractor Project Manager | UEAP-WS Pauri | See Pic |
|
|