Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Srinagar-And-Pauri-Water-Supply-Scheme Phase1 Work Completed
Project: UEAP-WS UID: 7109 Sanction Cost: 3047.00  lakh Length: KM.
District: Pauri Block: Khirsu Constituency: Srinagar Circle:
DEA: DEA WS Srinagar And Pauri DSC: DSC Scope: Design & Supervision Type: Not known
Procurement:
Package No.: 2109        Package Name:  UK/UEAP-WSS/UJS/GW/02        Tender Date: 10-10-2014        Current Status: Agreement signed        Achieved on Date: 05-12-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/02      Contractor Name: RK Engineers Sales Ltd
Start Date:  19-01-2015      Intended Completion Date:  30-06-2017      Original End Date:  18-07-2016
Total Bond Cost: 333299052 (3332.99 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 30330300 for +182 days        LD Analysis for Milestone2: calculated LD is Rs 59327400 for 356 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Infiltration Well/Tube Well3.00 No384.0001-01-201501-03-20163.00 No3.00 No12.68384.00
2.Pump House1.00 No24.6501-04-201530-09-20151.00 No1.00 No0.8124.65
3.GLSRs3.00 No190.0001-05-201531-12-20153.00 No3.00 No6.28190.00
4.Rehabilitation of WTP/HFRF 3.00 No247.8501-10-201531-12-20153.00 No3.00 No8.19247.85
5.Pipe Line Works with (Main/ Distribution)37400.00 m1000.0001-03-201528-02-201637400.00 m37400.00 m33.031000.00
6.Electrical and Instrumentation work7.00 No795.6101-04-201531-03-20167.00 No7.00 No26.28795.61
7.Office Building1.00 No59.2001-03-201531-12-20151.00 No1.00 No1.9659.20
8.Env. Man & Moni Plan1.00 Job5.6101-02-201531-07-20161.00 Job1.00 Job0.195.61
9.Provisional Sum1.00 Job321.0001-01-201531-07-20161.00 Job1.00 Job10.6321.00
Total Amount: 3027.92 100   3027.92
Remarks: No Remarks       Work Program Made On: 30-03-2015        Updation of work program on: 30-03-2015       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-September-201598.85  lakh
2.30-October-2015153.09  lakh
3.18-December-2015120.08  lakh
4.17-March-2016259.06  lakh
5.22-March-2016131.20  lakh
6.17-June-2016124.00  lakh
7.25-June-2016107.53  lakh
8.24-September-201652.66  lakh
9.26-October-2016172.30  lakh
10.07-January-2017447.06  lakh
11.14-March-201776.28  lakh
12.29-April-2017123.42  lakh
13.22-June-2017450.37  lakh
14.28-June-2017262.72  lakh
15.24-August-2017155.70  lakh
Total 2734.32  lakh
% Payment 82.03 %
Advance Amount:  479.41  lakh        Recovered Amount:  479.41  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 4   No. of Test Done : 4    No. of Test Passed : 4   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.01
Number of Notice(s) issued: 181

Mobile Pic Upload

Number of Pics Available on Web Repository: 152
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-03-2017Raw waterRaw waterAshok NegiDPMPIU WS See Pic
2.28-03-2017Panel roomRaw waterAshok NegiDPMPIU WS See Pic
3.28-03-2017Raw water pumphouseFinishingAshok NegiDPMPIU WS See Pic
4.28-03-2017Raw water p houseFinishingAshok NegiDPMPIU WS See Pic
5.28-03-2017Paving areaFinishingAshok NegiDPMPIU WS See Pic
6.28-03-2017WtpFinishingAshok NegiDPMPIU WS See Pic
7.28-03-2017Scada roomFinishingAshok NegiDPMPIU WS See Pic
8.04-03-2017Scada Rm. At WTPFinal touch is in progressDilip Chand GuptaConstruction SupervisorDSC WS ADB Pauri See Pic
9.25-01-2017TubewellPumps installationAshok NegiDPMPIU WS See Pic
10.25-01-2017WtpRepair worksAshok NegiDPMPIU WS See Pic
11.24-01-2017500kl sumpinspection being mad by the seanior officls of pmu.dsc staff membr concerned contractors staff membar at sringarRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic
12.24-01-2017500kl and tubewell areaInspection being carried on by senior officals . Dse staff member and concerned contractors staff membersParveen SainiAEUEAP UJS Pauri See Pic
13.21-01-2017Tuble srinagerValve fixingParveen SainiAEUEAP UJS Pauri See Pic
14.20-01-2017raw water pump houselandscaping at raw water pump house sringarRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic
15.17-01-2017clear water pump house6mld clear water pump houseRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic
16.16-01-2017raw water pump houseraw water pump house wall workRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic
17.04-01-2017Pump houseFinishingAshok NegiDPMPIU WS See Pic
18.04-01-2017500 kl sumpFinishingAshok NegiDPMPIU WS See Pic
19.07-12-2016sringar automation workautomation work in. progressRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic
20.06-12-2016sringar rbf sitepump house and 500kl sumpRakesh SharmaContractor Project ManagerUEAP-WS Pauri See Pic