Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Uttarkashi-Water-Supply-Scheme Work Completed
Project: UEAP-WS UID: 7107 Sanction Cost: 480.00  lakh Length: KM.
District: Tehri Block: Bhatwari Constituency: Gangotri Circle:
DEA: DEA WS Rudraprayag DSC: DSC Scope: Design & Supervision Type: Not known
Procurement:
Package No.: 2107        Package Name:  UK/UEAP-WSS/UJS/GW/01/lot4        Tender Date: 10-11-2014        Current Status: Agreement signed        Achieved on Date: 15-01-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/01/lot4      Contractor Name: RK Engineers Sales Ltd
Start Date:  19-01-2015      Intended Completion Date:  30-09-2017      Original End Date:  18-07-2016
Total Bond Cost: 63357051.75 (633.57 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 3611406 for 114 days        LD Analysis for Milestone2: calculated LD is Rs 12228094 for 386 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Infiltration Well/Tube Well2.00 No112.7501-03-201531-07-20152.00 No2.00 No17.8112.75
2.Rehabilitation of WTP/HFRF 3.00 No84.1401-05-201531-10-20153.00 No3.00 No13.2884.14
3.Pipe Line Works with (Main/ Distribution)7680.00 m301.9301-03-201530-09-20157680.00 m7680.00 m47.66301.93
4.Electrical and Instrumentation work1.00 No106.3530-09-201531-05-20161.00 No1.00 No16.79106.35
5.Env. Man & Moni Plan1.00 Job5.5401-02-201531-05-20161.00 Job1.00 Job0.875.54
6.Provisional Sum1.00 Job22.8501-02-201531-05-20161.00 Job1.00 Job3.6122.85
Total Amount: 633.56 100   633.56
Remarks: No Remarks       Work Program Made On: 30-03-2015        Updation of work program on:       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-September-201573.08  lakh
2.30-October-201547.89  lakh
3.18-December-201523.01  lakh
4.22-March-201675.04  lakh
5.17-June-201616.85  lakh
6.24-October-201654.97  lakh
7.07-January-201719.00  lakh
8.14-March-201714.71  lakh
9.21-June-201742.71  lakh
10.24-August-201727.18  lakh
Total 394.44  lakh
% Payment 62.25 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1   No. of Test Done : 1    No. of Test Passed : 1   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.08
Number of Notice(s) issued: 120

Mobile Pic Upload

Number of Pics Available on Web Repository: 242
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-07-2017Back side of Gufiyara wtpExcavation and disposal work is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
2.04-07-2017Back side of WTP gufiyaraExcavation and disposal work is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
3.03-07-2017Back side of Gufiyara WTPExcavation & Disposal of earth is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
4.02-07-2017Back side of Gufiyara WTPExcavation and disposal work is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
5.01-07-2017Back side of Gufiyara WTPExcavation and disposal work is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
6.29-06-2017Back side of Gufiyara WTPExcavation and disposal of surplus earthMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
7.29-06-2017Back side of Gufiyara WTPExcavation and disposal of surplus earth work is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
8.29-06-2017Back side Gufiyara WTPExcavation and disposal of surplus earth work for retaining wall is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
9.19-06-2017Back side of Gufiyara WTPDisposal of surplus earthMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
10.17-06-2017Back side of Gufiyara WTPCasting of 6th lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
11.16-06-2017Back side of Gufiyara WTPShuttering of 6th lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
12.15-06-2017Back side of Gufiyara WTPReinforcement of 6th lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
13.15-06-2017Back side of Gufiyara WTPCasting of 5th lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
14.09-06-2017Back side of Gufiyara WTPCasting of 3rd lift of retaining wall in 11 MTR lengthMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
15.09-06-2017Back side of Gufiyara WTPCasting of 3rd lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
16.08-06-2017Back side of Gufiyara WTPShuttering of 3rd lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
17.05-06-2017Back side of Gufiyara WTPCasting of 2nd lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
18.05-06-2017Back side of Gufiyara WTPCasting of 2nd lift of retaining wallMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
19.03-06-2017Back side of Gufiyara WTPShuttering of the 2nd lift of retaining wall is in progressMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic
20.02-06-2017Back side of Gufiyara WTPReinforcement of 2nd liftMonendra Singh RanaConstruction supervisorDSC WS ADB Tehri See Pic