Karanprayag-Water-Supply-Scheme
Work Completed
|
Project: |
UEAP-WS |
UID: |
7105 |
Sanction Cost: |
883.00 lakh |
Length:
|
KM. |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
|
DEA: |
DEA WS Rudraprayag |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
Not known |
|
Procurement: |
Package No.: 2105
Package Name: 
UK/UEAP-WSS/UJS/GW/01/lot2
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 24-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/01/lot2
Contractor Name: RK Engineers Sales Ltd
|
Start Date: 19-01-2015
Intended Completion Date: 31-05-2017
Original End Date: 18-07-2016 |
Total Bond Cost: 96748526 (967.49 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 10545532 for 218 days
LD Analysis for Milestone2: calculated LD is Rs 20607324 for 426 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Infiltration Well/Tube Well | 1.00 No | 190.40 | 01-01-2015 | 31-10-2015 | 1.00 No | 1.00 No | 19.68 | 190.40 | 2. | GLSRs | 3.00 No | 72.00 | 01-03-2015 | 31-12-2015 | 3.00 No | 3.00 No | 7.44 | 72.00 | 3. | Pipe Line Works with (Main/ Distribution) | 14200.00 m | 318.48 | 01-02-2015 | 31-12-2015 | 14200.00 m | 14200.00 m | 32.92 | 318.48 | 4. | Electrical and Instrumentation work | 1.00 No | 154.58 | 01-01-2016 | 31-05-2016 | 1.00 No | 1.00 No | 15.98 | 154.58 | 5. | Office Building | 1.00 No | 183.89 | 01-03-2015 | 31-12-2015 | 1.00 No | 1.00 No | 19.01 | 183.89 | 6. | Env. Man & Moni Plan | 1.00 Job | 6.01 | 01-02-2015 | 31-07-2016 | 1.00 Job | 1.00 Job | 0.62 | 6.01 | 7. | Provisional Sum | 1.00 Job | 42.10 | 01-01-2015 | 31-07-2016 | 1.00 Job | 1.00 Job | 4.35 | 42.10 |
Total Amount: |
967.46 |
|
100 |
967.46 |
|
Remarks:
No Remarks
Work Program Made On:
30-03-2015 } ?>
Updation of work program on:
01-04-2015
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-September-2015 | 18.87 lakh | 2. | 18-December-2015 | 68.15 lakh | 3. | 11-March-2016 | 133.76 lakh | 4. | 22-March-2016 | 64.72 lakh | 5. | 23-June-2016 | 28.15 lakh | 6. | 19-September-2016 | 66.25 lakh | 7. | 26-October-2016 | 30.48 lakh | 8. | 14-March-2017 | 67.50 lakh | 9. | 29-April-2017 | 50.88 lakh | 10. | 08-June-2017 | 93.77 lakh |
Total |
622.53 lakh |
% Payment |
64.35 % |
|
Advance Amount: 136.35 lakh
Recovered Amount: 136.35 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 286 No. of Test Done : 286 No. of Test Passed : 286 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
Number of Notice(s) issued: 139 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 61 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 28-05-2017 | I Well Karanparyag | I Well Karanparyag | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
2. | 28-05-2017 | Pump House Karanparyag | Pump House Karanparyag | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
3. | 24-05-2017 | I Well Karanparyag | I Well Karanparyag | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
4. | 24-05-2017 | Pumphouse Karanparyag | Pumphouse Karanparyag | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
5. | 16-05-2017 | I Well Karanparyag | I Well Karanparyag | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
6. | 09-05-2017 | Pumphouse Karnparyag | Pumphouse Karnparyag | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
7. | 09-05-2017 | I Well Karnparyag | I Well Karnparyag | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
8. | 04-05-2017 | I Well & Pumphouse kaleshwer | Karnparyag | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
9. | 25-04-2017 | Pumphouse Karnparyag | Pumphouse Karnparyag | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
10. | 25-04-2017 | Pumphouse kaleshwer karnparyag | Pumphouse Karnparyag | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
11. | 25-04-2017 | I Well Karnparyag | I Well kaleshwer karnparyag | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
12. | 25-04-2017 | I Well Karnparyag | Civil work is complete | Bharat Singh Bisht | Quantity Surveyor | DSC WS ADB Pithoragarh | See Pic |
13. | 29-03-2017 | Sump and p house | Trial run | Ashok Negi | DPM | PIU WS | See Pic |
14. | 29-03-2017 | Sump and p house | Finishing works | Ashok Negi | DPM | PIU WS | See Pic |
15. | 29-03-2017 | Pumphouse | Pumphouse | Ashok Negi | DPM | PIU WS | See Pic |
16. | 05-03-2017 | 150kl GLSR Karanprayag | Boundary wall work in progress | Goutam Sengupta | Construction Supervisor | DSC WS ADB Chamoli | See Pic |
17. | 15-02-2017 | I well Kaleswar.... | Main Gate fixing complete..... | Goutam Sengupta | Construction Supervisor | DSC WS ADB Chamoli | See Pic |
18. | 25-01-2017 | Pumphouse | Pump installation | Ashok Negi | DPM | PIU WS | See Pic |
19. | 25-01-2017 | Pumphouse premises | Landscaping works | Ashok Negi | DPM | PIU WS | See Pic |
20. | 25-01-2017 | Pumphouse | Finishing works | Ashok Negi | DPM | PIU WS | See Pic |
|
|