Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Karanprayag-Water-Supply-Scheme Work Completed
Project: UEAP-WS UID: 7105 Sanction Cost: 883.00  lakh Length: KM.
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle:
DEA: DEA WS Rudraprayag DSC: DSC Scope: Design & Supervision Type: Not known
Procurement:
Package No.: 2105        Package Name:  UK/UEAP-WSS/UJS/GW/01/lot2        Tender Date: 20-09-2014        Current Status: Agreement signed        Achieved on Date: 24-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/01/lot2      Contractor Name: RK Engineers Sales Ltd
Start Date:  19-01-2015      Intended Completion Date:  31-05-2017      Original End Date:  18-07-2016
Total Bond Cost: 96748526 (967.49 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 10545532 for 218 days        LD Analysis for Milestone2: calculated LD is Rs 20607324 for 426 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Infiltration Well/Tube Well1.00 No190.4001-01-201531-10-20151.00 No1.00 No19.68190.40
2.GLSRs3.00 No72.0001-03-201531-12-20153.00 No3.00 No7.4472.00
3.Pipe Line Works with (Main/ Distribution)14200.00 m318.4801-02-201531-12-201514200.00 m14200.00 m32.92318.48
4.Electrical and Instrumentation work1.00 No154.5801-01-201631-05-20161.00 No1.00 No15.98154.58
5.Office Building1.00 No183.8901-03-201531-12-20151.00 No1.00 No19.01183.89
6.Env. Man & Moni Plan1.00 Job6.0101-02-201531-07-20161.00 Job1.00 Job0.626.01
7.Provisional Sum1.00 Job42.1001-01-201531-07-20161.00 Job1.00 Job4.3542.10
Total Amount: 967.46 100   967.46
Remarks: No Remarks       Work Program Made On: 30-03-2015        Updation of work program on: 01-04-2015       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-September-201518.87  lakh
2.18-December-201568.15  lakh
3.11-March-2016133.76  lakh
4.22-March-201664.72  lakh
5.23-June-201628.15  lakh
6.19-September-201666.25  lakh
7.26-October-201630.48  lakh
8.14-March-201767.50  lakh
9.29-April-201750.88  lakh
10.08-June-201793.77  lakh
Total 622.53  lakh
% Payment 64.35 %
Advance Amount:  136.35  lakh        Recovered Amount:  136.35  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 286   No. of Test Done : 286    No. of Test Passed : 286   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.00
Number of Notice(s) issued: 139

Mobile Pic Upload

Number of Pics Available on Web Repository: 61
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-05-2017I Well KaranparyagI Well KaranparyagBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
2.28-05-2017Pump House KaranparyagPump House KaranparyagBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
3.24-05-2017I Well KaranparyagI Well KaranparyagBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
4.24-05-2017Pumphouse KaranparyagPumphouse KaranparyagBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
5.16-05-2017I Well KaranparyagI Well KaranparyagBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
6.09-05-2017Pumphouse KarnparyagPumphouse KarnparyagBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
7.09-05-2017I Well KarnparyagI Well KarnparyagBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
8.04-05-2017I Well & Pumphouse kaleshwerKarnparyagBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
9.25-04-2017Pumphouse KarnparyagPumphouse KarnparyagBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
10.25-04-2017Pumphouse kaleshwer karnparyagPumphouse KarnparyagBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
11.25-04-2017I Well KarnparyagI Well kaleshwer karnparyagBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
12.25-04-2017I Well KarnparyagCivil work is completeBharat Singh BishtQuantity SurveyorDSC WS ADB Pithoragarh See Pic
13.29-03-2017Sump and p houseTrial runAshok NegiDPMPIU WS See Pic
14.29-03-2017Sump and p houseFinishing worksAshok NegiDPMPIU WS See Pic
15.29-03-2017PumphousePumphouseAshok NegiDPMPIU WS See Pic
16.05-03-2017150kl GLSR KaranprayagBoundary wall work in progressGoutam SenguptaConstruction SupervisorDSC WS ADB Chamoli See Pic
17.15-02-2017I well Kaleswar....Main Gate fixing complete.....Goutam SenguptaConstruction SupervisorDSC WS ADB Chamoli See Pic
18.25-01-2017PumphousePump installationAshok NegiDPMPIU WS See Pic
19.25-01-2017Pumphouse premisesLandscaping worksAshok NegiDPMPIU WS See Pic
20.25-01-2017PumphouseFinishing worksAshok NegiDPMPIU WS See Pic