Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Rudraprayag-Water-Supply-Scheme Work Completed
Project: UEAP-WS UID: 7104 Sanction Cost: 177.00  lakh Length: KM.
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle:
DEA: DEA WS Rudraprayag DSC: DSC Scope: Design & Supervision Type: Not known
Procurement:
Package No.: 2104        Package Name:  UK/UEAP-WSS/UJS/GW/01/lot1        Tender Date: 20-09-2014        Current Status: Agreement signed        Achieved on Date: 29-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/01/lot1      Contractor Name: RK Engineers Sales Ltd
Start Date:  19-01-2015      Intended Completion Date:  28-02-2016      Original End Date:  18-07-2016
Total Bond Cost: 17508790 (175.09 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 463962 for 53 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Uttaranchal Koop3.00 No4.0501-02-201530-04-20153.00 No3.00 No2.314.05
2.Pipe Line Works with (Main/ Distribution)6000.00 m100.6201-02-201531-12-20156000.00 m6000.00 m57.47100.62
3.Office Building1.00 No55.9001-03-201531-12-20151.00 No1.00 No31.9355.90
4.Env. Man & Moni Plan1.00 Job6.0101-01-201530-06-20161.00 Job1.00 Job3.436.01
5.Provisional Sum1.00 Job8.5001-01-201530-06-20161.00 Job1.00 Job4.868.50
Total Amount: 175.08 100   175.08
Remarks: Confirmatory survey and approval of QAPof pipe has been completed        Work Program Made On: 30-03-2015        Updation of work program on: 01-04-2015       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-December-201568.87  lakh
2.22-March-201621.12  lakh
3.17-June-201629.97  lakh
4.25-October-201617.51  lakh
5.07-January-201714.19  lakh
6.31-May-201718.19  lakh
Total 169.85  lakh
% Payment 97 %
Advance Amount:  6.91  lakh        Recovered Amount:  6.91  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 81   No. of Test Done : 81    No. of Test Passed : 81   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.32
Number of Notice(s) issued: 115

Mobile Pic Upload

Number of Pics Available on Web Repository: 6
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-10-2016Office building, RudraprayagAlmost completeGoutam SenguptaConstruction SupervisorDSC WS ADB Chamoli See Pic
2.18-10-2016Office buildingFinishing worksAshok NegiDPMPIU WS See Pic
3.27-04-2015Sujibagadh RurapayagConformatory surveyOwais A ShahQCDSC ADB WS See Pic
4.07-04-2015Old Intake chamberWork not started yetOwais A ShahQCDSC ADB WS See Pic
5.07-04-2015Old ofice structureWork not startedOwais A ShahQCDSC ADB WS See Pic
6.31-03-2015Old office buildingWork not started yetOwais A ShahQCDSC ADB WS See Pic