Rudraprayag-Water-Supply-Scheme
Work Completed
|
Project: |
UEAP-WS |
UID: |
7104 |
Sanction Cost: |
177.00 lakh |
Length:
|
KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
|
DEA: |
DEA WS Rudraprayag |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
Not known |
|
Procurement: |
Package No.: 2104
Package Name: 
UK/UEAP-WSS/UJS/GW/01/lot1
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 29-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UK/UEAP-WSS/UJS/GW/01/lot1
Contractor Name: RK Engineers Sales Ltd
|
Start Date: 19-01-2015
Intended Completion Date: 28-02-2016
Original End Date: 18-07-2016 |
Total Bond Cost: 17508790 (175.09 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 463962 for 53 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Uttaranchal Koop | 3.00 No | 4.05 | 01-02-2015 | 30-04-2015 | 3.00 No | 3.00 No | 2.31 | 4.05 | 2. | Pipe Line Works with (Main/ Distribution) | 6000.00 m | 100.62 | 01-02-2015 | 31-12-2015 | 6000.00 m | 6000.00 m | 57.47 | 100.62 | 3. | Office Building | 1.00 No | 55.90 | 01-03-2015 | 31-12-2015 | 1.00 No | 1.00 No | 31.93 | 55.90 | 4. | Env. Man & Moni Plan | 1.00 Job | 6.01 | 01-01-2015 | 30-06-2016 | 1.00 Job | 1.00 Job | 3.43 | 6.01 | 5. | Provisional Sum | 1.00 Job | 8.50 | 01-01-2015 | 30-06-2016 | 1.00 Job | 1.00 Job | 4.86 | 8.50 |
Total Amount: |
175.08 |
|
100 |
175.08 |
|
Remarks:
Confirmatory survey and approval of QAPof pipe has been completed
Work Program Made On:
30-03-2015 } ?>
Updation of work program on:
01-04-2015
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-December-2015 | 68.87 lakh | 2. | 22-March-2016 | 21.12 lakh | 3. | 17-June-2016 | 29.97 lakh | 4. | 25-October-2016 | 17.51 lakh | 5. | 07-January-2017 | 14.19 lakh | 6. | 31-May-2017 | 18.19 lakh |
Total |
169.85 lakh |
% Payment |
97 % |
|
Advance Amount: 6.91 lakh
Recovered Amount: 6.91 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 81 No. of Test Done : 81 No. of Test Passed : 81 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 93.32 |
Number of Notice(s) issued: 115 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 6 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-10-2016 | Office building, Rudraprayag | Almost complete | Goutam Sengupta | Construction Supervisor | DSC WS ADB Chamoli | See Pic |
2. | 18-10-2016 | Office building | Finishing works | Ashok Negi | DPM | PIU WS | See Pic |
3. | 27-04-2015 | Sujibagadh Rurapayag | Conformatory survey | Owais A Shah | QC | DSC ADB WS | See Pic |
4. | 07-04-2015 | Old Intake chamber | Work not started yet | Owais A Shah | QC | DSC ADB WS | See Pic |
5. | 07-04-2015 | Old ofice structure | Work not started | Owais A Shah | QC | DSC ADB WS | See Pic |
6. | 31-03-2015 | Old office building | Work not started yet | Owais A Shah | QC | DSC ADB WS | See Pic |
|
|