Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bageshwar-Water-Supply-Scheme Work Completed
Project: UEAP-WS UID: 7102 Sanction Cost: 339.00  lakh Length: KM.
District: Bageshwar Block: Bageshwar Constituency: Bageshwar Circle:
DEA: DEA WS Kapkot DSC: DSC Scope: Design & Supervision Type: Not known
Procurement:
Package No.: 2102        Package Name:  UK/UEAP-WSS/UJS/KU/01/lot2        Tender Date: 16-09-2014        Current Status: Agreement signed        Achieved on Date: 15-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-WSS/UJS/KU/01/lot2      Contractor Name: Kashmirilal Constructions (P) Ltd.
Start Date:  01-12-2014      Intended Completion Date:  30-06-2017      Original End Date:  31-05-2016
Total Bond Cost: 38330950 (383.31 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 4676260 for 244 days        LD Analysis for Milestone2: calculated LD is Rs 4484610 for 234 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Infiltration Well/Tube Well1.00 No130.0001-01-201531-08-20161.00 No1.00 No33.72130.00
2.Rehabilitation of WTP/HFRF 1.00 No12.0001-10-201528-02-20161.00 No1.00 No3.1112.00
3.Demolition of old structures1.00 No0.3601-03-201531-05-20151.00 No1.00 No0.090.36
4.Pipe Line Works with (Main/ Distribution)500.00 m17.2401-02-201531-12-2015500.00 m500.00 m4.4717.24
5.Electrical and Instrumentation work3.00 No93.6801-10-201531-03-20163.00 No3.00 No24.393.68
6.Mechanical Work4.00 No111.7401-03-201531-01-20164.00 No4.00 No28.98111.74
7.Env. Man & Moni Plan1.00 Job5.5701-12-201431-05-20161.00 Job1.00 Job1.455.57
8.Provisional Sum1.00 Job15.0001-12-201431-05-20161.00 Job1.00 Job3.8915.00
Total Amount: 385.59 100   385.59
Remarks: Confirmatory survey and approval of QAP of Pipe & Pumps has been completed        Work Program Made On: 30-03-2015        Updation of work program on:       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-November-201527.52  lakh
2.19-March-201681.08  lakh
3.18-June-201654.84  lakh
4.17-August-201649.63  lakh
5.25-October-201638.22  lakh
6.07-January-201732.96  lakh
7.03-March-201749.85  lakh
8.21-June-201742.93  lakh
9.24-August-201725.04  lakh
Total 402.07  lakh
% Payment 104.9 %
Advance Amount:  43.07  lakh        Recovered Amount:  43.07  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 95.11
Number of Notice(s) issued: 127

Mobile Pic Upload

Number of Pics Available on Web Repository: 48
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-04-2017Bageshwar I wellCable alignment properly done at Bageshwar I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
2.18-04-2017Bageshwar I wellI well painting work Completed.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
3.08-03-2017Bageshwar I wellChannel fixing work at I well walkway bridgeRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
4.23-01-2017Bageshwar I wellAE UJS visited at I Well site for inspection of work progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
5.21-01-2017Dehradun PIU OfficeEMP TrainingBikash Kumar DasConstuction SupervisorDSC WS ADB Bageshwar See Pic
6.14-01-2017Bageshwar I wellGM Sir, EE Sir, JE UJS, CS DSC visited at Bageshwar I Well site.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
7.13-01-2017Bageshwar I wellSubmersibal pump installation work going on progress inside I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
8.12-01-2017Bageshwar I wellI well Submersibal pump reached at site and installation work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
9.23-12-2016Bageshwar WSSEnvironment Consultation at Bageshwar by Dr. Nutan Gupta(Envir. Sp.PMU)Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
10.23-12-2016Bageshwar I wellPump is running at Bageshwar I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
11.18-12-2016Thakurdwara at BageshwarAlum godown at finishing stageRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
12.15-12-2016Bageshwar I wellFlooring work going on progress at I wellRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
13.15-12-2016Bageshwar I wellSkirting work going on progress inside I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
14.07-12-2016Bageshwar I wellLevel sensor fitting work going on progress at I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
15.05-12-2016Bageshwar I wellEarthing work at Pump House Going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
16.26-11-2016Alum Godown(WTP at Thakurdwara, Bageshwar)Final and finishing stageRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
17.26-11-2016Bageshwar I wellFinishing stageRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
18.02-11-2016Bageshwar I wellTrail run commissioning going on progress from the date of 01/11/16.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
19.26-10-2016Bageshwar I well Pump houseSubmersibal Pump installation work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
20.18-10-2016I well bageshwarCleaningAshok NegiDPMPIU WS See Pic