Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kapkot-Water-Supply-Scheme Work Completed
Project: UEAP-WS UID: 7101 Sanction Cost: 598.00  lakh Length: KM.
District: Bageshwar Block: Kapkot Constituency: Bageshwar Circle:
DEA: DEA WS Kapkot DSC: DSC Scope: Design & Supervision Type: Not known
Procurement:
Package No.: 2101        Package Name:  UK/UEAP-WSS/UJS/KU/01/lot1        Tender Date: 16-09-2014        Current Status: Agreement signed        Achieved on Date: 15-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-WSS/UJS/KU/01/lot1      Contractor Name: Kashmirilal Constructions (P) Ltd.
Start Date:  01-12-2014      Intended Completion Date:  28-02-2017      Original End Date:  31-05-2016
Total Bond Cost: 53380185 (533.8 lakh)        Variation Cost: 1656042.84 (16.56 lakh)    Hence Total Bond Cost is   55036227.84 (550.36 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 4163640 for 156 days        LD Analysis for Milestone2: calculated LD is Rs 3683220 for 138 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Infiltration Well/Tube Well1.00 No128.0001-12-201431-10-20151.00 No1.00 No23.87128.00
2.Pipe Line Works with (Main/ Distribution)7641.00 m209.1101-02-201531-12-20157711.00 m7711.00 m38.99209.11
3.Electrical and Instrumentation work1.00 No38.7001-07-201531-05-20171.00 No1.00 No7.2238.70
4.Mechanical Work4.00 No128.3501-07-201531-03-20164.00 No4.00 No23.93128.35
5.Env. Man & Moni Plan1.00 Job5.1801-12-201431-05-20161.00 Job1.00 Job0.975.18
6.Provisional Sum1.00 Job27.0001-12-201431-05-20161.00 Job1.00 Job5.0327.00
Total Amount: 536.34 100   536.34
Remarks: Confirmatory survey and approval of QAP of pipe has been completed.       Work Program Made On: 30-03-2015        Updation of work program on: 08-06-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.20-October-201554.42  lakh
2.18-November-2015100.85  lakh
3.22-March-201667.74  lakh
4.23-June-2016156.55  lakh
5.17-August-201619.53  lakh
6.25-October-201640.92  lakh
7.03-March-201714.65  lakh
8.31-May-201752.01  lakh
Total 506.67  lakh
% Payment 92.07 %
Advance Amount:  67.68  lakh        Recovered Amount:  67.68  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 94.62
Number of Notice(s) issued: 118

Mobile Pic Upload

Number of Pics Available on Web Repository: 51
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.20-07-2017Binsar TankBinsar Tank protection work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
2.20-07-2017Binsar 200KL TankTank exavation work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
3.28-04-2017Kapkot I wellInside view of Pump HouseRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
4.28-04-2017Kapkote I WellSite view of I wellRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
5.02-04-2017Kapkot I WellAll works are completed.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
6.16-03-2017Kapkote I wellChain link fencing work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
7.09-03-2017Kapkot I wellChain link fencing work going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
8.07-03-2017Kapkot I wellAE, JE(UJS) and CS DSC visited Kapkot I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
9.04-03-2017Kapkot I wellExtra Item work inspection taken by FPIU and DSCRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
10.03-03-2017I. Well kapkotFencing workBikash Kumar DasConstuction SupervisorDSC WS ADB Bageshwar See Pic
11.03-03-2017I. Well, KapkotGate fixingBikash Kumar DasConstuction SupervisorDSC WS ADB Bageshwar See Pic
12.03-03-2017Kapkot I wellExtra item works going on progress.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
13.22-01-2017Kapkote I WellFire buckets fixed at I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
14.13-01-2017Kapkot I-wellInformation board fixed at KapkotRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
15.12-01-2017Kapkot I wellI Well painting work completed.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
16.31-12-2016Kapkote I wellAutomation(SCADA) is working at Kapkote I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
17.29-12-2016Kapkote I wellFinal coat Painting work at Kapkote I wellRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
18.23-12-2016Kapkote WSSEnvironment consultation at Kapkote Nagarpanchayat Office by Dr Nutan Gupta (Environment Sp.PMU)Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
19.21-12-2016Kapkote I WellFinal coat painting and site devlopment work at I well.Rajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic
20.19-12-2016Kapkote I wellAE UJS with DSC visited Kapkote I WellRajesh UpadhyayProject ManagerUEAP-WS Bageshwar See Pic