Dwarahat Agreement signed
Project: UEAP-CA UID: 7015 Sanction Cost: 88.23  lakh Length: KM.
District: Almora Block: unknown Constituency: unknown Circle:
DEA: DEA CA DSC: DSC Scope: supervision Type: H3
Procurement:
Package No.: 2001        Package Name:  UK/UEAP-CA/P1/01        Tender Date: 05-09-2014        Current Status: Agreement signed        Achieved on Date: 26-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UK/UEAP-CA/P1/01      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  20-03-2015      Intended Completion Date:  20-06-2016     
Total Bond Cost: 114957868 (1149.58 lakh)       
Sub Project Cost: 88.23  lakh       
LD Analysis for Milestone1: calculated LD is Rs 8736808 for +152 days        LD Analysis for Milestone2: calculated LD is Rs 8794287 for 153 days       
Component Wise Progress
No Physical Progress.
Remarks: No Remarks       Work Program Made On:        Updation of work program on:       
Work Program Status:Work Program Not Made Yet
Financial Progress
SNo. Date Payment
1.29-October-20150.68  lakh
2.11-January-201640.29  lakh
3.31-May-201626.55  lakh
Total 67.52  lakh
% Payment76.53 %
Advance Amount:  114.96  lakh        Recovered Amount:  16.63  lakh        Balance to be Recovered  98.32  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported( Work program not made hence analysis may not be realistic).
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): Query, Borrow pits, DG set
Detailed report of this subproject
Quality
Test Information not Available.
Quality ranking not done.
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 1
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-07-2015Helipad site at DwarahatEarthwork in progressRupeshTLUEAP CA See Pic